Cheat sheet

CCM (Certified Construction Manager) Cheat Sheet

Practice this exam

Program & Project Management

  • 20% of exam
  • Delivery Methods Project Phases Program Mgmt Stakeholder Mgmt

Cost Management

  • 10% of exam
  • Estimating & Budgeting Earned Value Mgmt GMP Contingency

Time Management

  • 10% of exam
  • CPM Scheduling Schedule Formats Float Fast-Tracking

Contract Administration

  • 10% of exam
  • Contract Types Contract Administration RFI Change Orders

Quality Management

  • 10% of exam
  • QA and QC Mock-Ups Commissioning Non-Conformance

Safety Management

  • 10% of exam
  • Safety Program OSHA JHA PPE

Risk Management

  • 10% of exam
  • Risk Management Process Insurance and Bonds Risk Register Mitigation

Professional Practice

  • 10% of exam
  • Ethics and Roles CMAA Standards RIC Experience Fiduciary Duty

Sustainability

  • 5% of exam
  • Sustainability Practices LEED Life-Cycle Assessment Waste Mgmt

Technology

  • 5% of exam
  • CM Technology Tools BIM Clash Detection Digital Twin

Quick Facts

  • Exam CCM
  • Credential Certified Construction Manager
  • Questions 175 total (150 scored)
  • Time 240 min (4 hrs)
  • Pass Score 72%
  • Format CBT via PSI
  • Level Advanced (RIC experience req.)
  • Blueprint CMCI Handbook v4.1 (2021)

Delivery Method Risk Spectrum PP

  • DBB -> CMAR -> Design-Build -> IPD
  • DBB: most separation CMAR: CM joins early DB: single responsibility IPD: shared risk and reward

CMAR vs Design-Build PP

CMAR

  • CM at risk
  • Separate designer contract
  • GMP set after design

Design-Build

  • Single combined contract
  • Design and build merged
  • One point of responsibility
  • Two contracts versus one

Delivery Method Picker PP

  • Owner wants fixed price → DBB ( Design finished first )
  • Need speed and GMP control → CMAR ( CM joins during design )
  • Single point of responsibility → DB ( One contract, one entity )
  • Max collaboration and shared risk → IPD ( Multi-party shared agreement )
  • Owner self-manages trade contracts → Multi-Prime ( Separate direct contracts )

Delivery Methods PP

  • DBB Sequential design-bid-build
  • DB Single design-build contract
  • CMAR CM-at-risk with GMP
  • CM Agency CM acts as agent
  • IPD Shared risk and reward
  • Multi-Prime Owner holds separate contracts
  • DBOM Design-build-operate-maintain

Project Phases PP

  • Pre-Design Feasibility and programming
  • Schematic Design Early concept design
  • Design Development Refine design details
  • Construction Documents Bid-ready drawings and specs
  • Procurement Bid and award
  • Construction Phase Build and control
  • Closeout Punch list and turnover
  • Post-Occupancy Warranty and evaluation

Program and Stakeholder Mgmt PP

  • Program Mgmt Multi-project oversight
  • PMP Project management plan
  • WBS Work breakdown structure
  • Stakeholder Mgmt Engage all parties
  • Owner's Rep Acts for owner

EVM Core Formulas CO

  • CV=EV-AC | SV=EV-PV | CPI=EV/AC | SPI=EV/PV
  • CV: cost variance SV: schedule variance CPI: cost efficiency SPI: schedule efficiency

CPI vs SPI CO

CPI

  • Measures cost efficiency
  • EV divided by AC

SPI

  • Measures schedule efficiency
  • EV divided by PV
  • Cost versus schedule

Cost Variance Response CO

  • CPI below 1.0 → Investigate cost overrun ( Spending more than earned )
  • SPI below 1.0 → Investigate schedule slip ( Behind planned progress )
  • CPI and SPI both low → Escalate to owner ( Recovery plan needed )
  • EAC exceeds approved budget → Request change order ( Reforecast completion cost )

Estimating and Budgeting CO

  • ROM Estimate Rough order of magnitude
  • Conceptual Estimate Early, low detail
  • Detailed Estimate Quantity takeoff based
  • GMP Guaranteed maximum price
  • Contingency Reserve for unknowns
  • Life-Cycle Cost Total ownership cost

Earned Value Management CO

  • PV Planned value (BCWS)
  • EV Earned value (BCWP)
  • AC Actual cost (ACWP)
  • CPI Cost performance index
  • SPI Schedule performance index
  • CV EV minus AC
  • SV EV minus PV
  • EAC Forecast final cost

Schedule Levels TI

  • Master -> Baseline -> Look-ahead -> Daily
  • Master: whole project Baseline: approved plan Look-ahead: two to six weeks Daily: field execution

Critical Path vs Float TI

Critical Path

  • Zero float
  • Longest duration path
  • Delay delays whole project

Float

  • Slack time available
  • Can delay safely
  • Non-critical activities only
  • No slack versus slack

Schedule Delay Response TI

  • Owner-caused delay occurs → Time extension granted ( Excusable and compensable )
  • Contractor-caused delay occurs → No time extension ( Non-excusable delay )
  • Weather beyond normal range → Excusable, non-compensable delay ( Time only, no cost )
  • Need faster completion date → Crash or fast-track ( Adds cost or risk )

CPM Scheduling TI

  • CPM Critical path method
  • Critical Path Longest, zero-float path
  • Float Slack before delay
  • Free Float Delay without successor impact
  • Total Float Delay without finish impact
  • Predecessor Must-precede activity
  • Milestone Zero-duration marker
  • Fast-Tracking Overlap sequential phases
  • Crashing Add resources, shorten

Schedule Formats TI

  • Gantt Chart Bar chart timeline
  • PDM Precedence diagram method
  • Look-Ahead Schedule Short-term 2-6 weeks
  • Baseline Schedule Approved original plan
  • Schedule Update Progress versus baseline
  • Delay Analysis TIA or as-built

RFI vs Submittal CO

RFI

  • Clarifies design intent
  • A question, not approval

Submittal

  • Shop drawings or product data
  • Confirms spec compliance
  • Ask versus confirm

Contract Types CO

  • Lump Sum Fixed total price
  • Unit Price Price per unit
  • Cost-Plus-Fee Cost plus fixed fee
  • GMP Contract Cost-plus with a cap
  • T&M Time and materials

Contract Administration CO

  • RFI Request for information
  • Submittal Shop drawing review
  • Change Order Approved scope or cost change
  • PCO Potential change order
  • ASI Architect's supplemental instruction
  • Notice to Proceed Start authorization
  • Punch List Final defect list
  • Retainage Withheld payment percent

QA vs QC QU

QA

  • Process-focused
  • Prevents defects
  • Ongoing procedures

QC

  • Product-focused
  • Detects defects
  • Inspection and testing
  • Prevent versus detect

QA and QC QU

  • QA Process-focused prevention
  • QC Product-focused inspection
  • Mock-Up Sample for approval
  • Commissioning Verify systems perform
  • Non-Conformance Work fails specification
  • ITP Inspection and test plan

Safety Program SA

  • OSHA Federal safety regulator
  • JHA Job hazard analysis
  • Competent Person OSHA-authorized hazard identifier
  • Toolbox Talk Daily safety briefing
  • PPE Personal protective equipment
  • OSHA 300 Log Injury and illness log
  • Fall Protection Required above six feet

Risk Response Options RI

  • Avoid, Transfer, Mitigate, or Accept
  • Avoid: eliminate exposure Transfer: insurance or contract Mitigate: reduce impact Accept: retain and monitor

Bid Bond vs Performance Bond RI

Bid Bond

  • Guarantees bid is honored
  • Protects before contract award

Performance Bond

  • Guarantees full completion
  • Protects after contract award
  • Before award versus after

Risk Response Selection RI

  • Risk is high and avoidable → Avoidance ( Eliminate the exposure )
  • Risk transferable to third party → Transfer ( Insurance or subcontract )
  • Risk manageable in-house → Mitigation ( Reduce likelihood and impact )
  • Risk is low impact → Acceptance ( Retain and monitor )

Risk Management Process RI

  • Risk ID Find potential risks
  • Risk Register Log of tracked risks
  • Mitigation Reduce likelihood and impact
  • Transfer Insurance or contract
  • Avoidance Eliminate the exposure
  • Acceptance Retain known risk
  • Contingency Reserve Cost and time buffer

Insurance and Bonds RI

  • Builder's Risk Property damage coverage
  • GL Insurance General liability coverage
  • Bid Bond Guarantees bid commitment
  • Performance Bond Guarantees contract completion
  • Payment Bond Guarantees sub and supplier pay
  • Indemnification Shifts liability by contract

Ethics and Roles PR

  • CCM Ethics Conditions and Conduct agreement
  • RIC Responsible-in-charge experience
  • Fiduciary Duty Act in owner's interest
  • Standard of Care Reasonable professional skill level
  • CMAA SOP Standards of Practice

Sustainability Practices SU

  • LEED USGBC green building rating
  • Life-Cycle Assessment Environmental impact review
  • Commissioning Agent Verifies green performance
  • Waste Mgmt Plan Reduce and recycle debris
  • Energy Modeling Predicts building performance

CM Technology Tools TE

  • BIM 3D model coordination
  • Clash Detection Model conflict check
  • CDE Common data environment
  • PM Software Procore, e-Builder, etc.
  • Drone Survey Aerial progress monitoring
  • Digital Twin Virtual asset replica

Common Traps

QA ≠ QC

  • QA prevents defects proactively ≠ QC detects defects reactively

Float ≠ Critical Path

  • Float allows scheduling slack ≠ Critical path has zero slack

CMAR ≠ Design-Build

  • CMAR keeps designer separate ≠ Design-Build merges into one contract

RFI ≠ Submittal

  • RFI asks a question ≠ Submittal confirms spec compliance

Mitigation ≠ Avoidance

  • Mitigation reduces risk impact ≠ Avoidance eliminates risk entirely

CPI ≠ SPI

  • CPI measures cost performance ≠ SPI measures schedule performance

Bid Bond ≠ Performance Bond

  • Bid bond covers pre-award ≠ Performance bond covers post-award

Last Minute

  • 1. Ten domains, PPM heaviest at 20%
  • 2. 175 questions total, 150 scored
  • 3. 240 minutes, 72% passing score
  • 4. CBT delivered via PSI, not Prometric
  • 5. CPI or SPI below 1.0 warns
  • 6. Critical path activities have zero float
  • 7. QA prevents; QC detects defects
  • 8. CMAR joins early; Design-Build merges roles
  • 9. RFI asks; submittal confirms compliance
  • 10. Avoid, transfer, mitigate, or accept risk
  • 11. Retainage withholds a payment percentage
  • 12. CCM recertifies every three years

CCM Certified Construction Manager