Cheat sheet

ICC B1 Residential Cheat Sheet

Practice this exam

Code Administration

  • 4% of exam
  • Project Admin Permits Reports CO Stop Work

Building Planning

  • 8% of exam
  • Unit Separation Site Location Room Dimensions Egress Windows Stairs

Footings and Foundations

  • 16% of exam
  • Footings Foundation Walls Anchor Bolts Drainage Backfill

Floor Construction

  • 14% of exam
  • Joists Bearing Notching Subflooring Crawlspaces

Wall Construction

  • 27% of exam
  • Studs Headers Bracing Fireblocking WRB

Roof and Ceiling

  • 14% of exam
  • Attics Rafters Trusses Sheathing Flashing

Public Safety

  • 17% of exam
  • Egress Handrails Guards Alarms Safety Glazing

Quick Facts

  • Exam B1
  • Credential Residential Building Inspector
  • Questions 60
  • Time 2 hours
  • Format Open book
  • Scope IRC dwellings
  • Pass 75 scaled
  • Provider ICC

Permit vs CO AD

Permit

  • Starts legal work
  • Before construction
  • Scope approval

CO

  • Allows occupancy
  • After final
  • Use approval
  • Start work vs occupy

Inspection Picker AD

  • Missing approved plans → Stop review ( Baseline absent )
  • Unlisted product → AHJ approval ( Alternative path )
  • Work concealed → Inspection required ( Verify first )
  • Unsafe condition → Stop work ( Immediate risk )
  • Defect found → Correction notice ( Document fix )
  • Final compliant → CO ( Occupancy )
  • Question asks scope → IRC chapter ( Find authority )
  • Local conflict → Jurisdiction rule ( Local controls )

Project Admin AD

  • AHJ Code authority
  • Approved plans Inspection baseline
  • Permit Work authorization
  • Inspection report Field record
  • Correction notice Defect direction
  • Stop work Unsafe halt
  • CO Occupancy approval

Building Planning PL

  • Townhouse limit Three stories
  • Unit separation Rated assembly
  • Site plan Location check
  • Grade slope Drain from foundation
  • Flood elevation Local/FEMA check
  • Room area Minimum floor area
  • Light/vent Opening compliance

Anchor Bolts FO

  • Half, seven, six, twelve
  • 1/2 in bolt 7 in embed 6 ft spacing 12 in ends

Dampproof vs Waterproof FO

Dampproof

  • Moisture resistance
  • Damp soil
  • Basic coating

Waterproof

  • Water pressure
  • Hydrostatic risk
  • Stronger system
  • Dampness vs water pressure

Code Table Picker FO

  • Footing size → Soil/load table
  • Foundation wall → Backfill table
  • Joist span → Span table
  • Header size → Header table
  • Rafter span → Rafter table
  • Sheathing fasteners → Fastening schedule
  • Concrete strength → Weathering table
  • Roof covering → Slope table

Foundation Core FO

  • Frost depth Below frost line
  • Footing width Use load table
  • Footing drains Basement/crawlspace drainage
  • Wall thickness Backfill-driven table
  • Unbalanced fill Wall design cue
  • Dampproofing Moisture resistance
  • Waterproofing Hydrostatic protection
  • Backfill brace Support before fill

Concrete and Anchors FO

  • Slab thickness 3-1/2 in
  • Base course 4 in fill
  • Concrete strength Weathering table
  • Anchor diameter 1/2 in min
  • Anchor embed 7 in min
  • Anchor spacing 6 ft max
  • End distance 12 in max
  • Lap splice 40 bar diameters

Joist Cuts FL

  • Thirds rule cuts, two-inch edge
  • 1/3 max No middle notches 2 in edge Check engineered

Bearing vs Span FL

Bearing

  • Support length
  • Load transfer
  • End condition

Span

  • Clear distance
  • Table lookup
  • Species/load dependent
  • Resting length vs distance

Floor Framing FL

  • Lumber grade Marking required
  • Joist span Species/grade table
  • Wood bearing 1-1/2 in
  • Masonry bearing 3 in
  • Notch depth 1/3 max
  • Middle third No notches
  • Bored holes 2 in edge
  • Sill plate Preservative-treated

Floor Systems FL

  • Engineered joists Manufacturer drawings
  • Subfloor Thickness/span grade
  • Decking Fastener schedule
  • Crawl access Opening required
  • Crawl vent Screened ventilation
  • Draftstops Concealed-space blocks
  • Decay risk Moisture contact

Bracing vs Sheathing WA

Bracing

  • Lateral resistance
  • Wall line
  • Load path

Sheathing

  • Panel material
  • Thickness/fasteners
  • May brace
  • Function vs material

Wall Framing WA

  • Stud spacing Table condition
  • Load path Loads to foundation
  • Header span Opening/load table
  • Steel studs Marking compliance
  • Wall bracing Lateral resistance
  • Fireblocking Vertical fire stops
  • Garage separation Gypsum barrier
  • Safety glazing Label required

Wall Coverings WA

  • WRB Water-resistive barrier
  • Sheathing Thickness/fasteners
  • Veneer support Anchorage/backing
  • Siding clearance Above grade
  • Stucco lath Fastened support
  • Shower walls Approved finish
  • Masonry grout Where required
  • Mortar joints Thickness check

Rafter vs Truss RO

Rafter

  • Field framed
  • Span table
  • Collar ties

Truss

  • Engineered assembly
  • Approved drawings
  • No field cuts
  • Prescriptive vs engineered

Roof and Ceiling RO

  • Attic access Opening required
  • Attic vent Net free area
  • Rafter span Species/load table
  • Rafter bearing Support required
  • Collar ties Uplift restraint
  • Trusses Approved drawings
  • Roof sheathing 8d schedule
  • Flashing Water diversion
  • Roof slope Covering limit
  • Chimney clearance Combustible separation

Egress Window SA

  • 20 wide, 24 high, 44 sill
  • 20 in width 24 in height 44 in sill 5.7 sq ft

Guard vs Handrail SA

Guard

  • Fall prevention
  • Open side
  • Sphere limits

Handrail

  • Grip support
  • Along stair
  • Height range
  • Block fall vs grip

Safety Picker SA

  • Sleeping room → EERO ( Escape/rescue )
  • Open side high → Guard ( Fall risk )
  • Stair walking → Handrail ( Graspable )
  • Bedroom level → Smoke alarm
  • Fuel appliance → CO alarm
  • Garage attached → CO alarm
  • Hazardous glazing → Safety glazing
  • Concealed chase → Fireblocking

Egress and Stairs SA

  • Hall width 36 in
  • Max riser 7-3/4 in
  • Min tread 10 in
  • Headroom 6 ft 8 in
  • Max flight 12 ft 3 in
  • Landing depth 36 in
  • EERO sill 44 in max
  • EERO area 5.7 sq ft

Stair Numbers SA

  • Seven-three-quarter up, ten across
  • Riser max Tread min Headroom 6-8 Flight 12-3

Public Safety SA

  • Smoke alarms Bedrooms/levels
  • CO alarms Fuel/garage trigger
  • Cooking offset 10 ft preferred
  • Deck guard Over 30 in
  • Guard height 36 in surface
  • Stair guard 34 in min
  • Baluster opening 4 in sphere
  • Triangle opening 6 in sphere
  • Handrail grip Graspable profile

Common Traps

Grade vs normal EERO

  • Grade allows 5.0 ≠ Above needs 5.7

Stair guard vs deck guard

  • Stair guard 34 ≠ Deck guard 36

Wood vs masonry bearing

  • Wood bearing 1-1/2 ≠ Masonry bearing 3

Permit vs inspection

  • Permit authorizes work ≠ Inspection verifies work

Rafter vs truss cuts

  • Rafters table-driven ≠ Trusses need approval

Dampproof vs drain

  • Coating resists moisture ≠ Drain relieves water

Last Minute

  • 1. Weights: 4,8,16,14,27,14,17
  • 2. B1: 60 questions, 2 hours
  • 3. Open book: know tables
  • 4. IRC scope: dwellings/townhouses/accessory
  • 5. EERO: 20x24, 44 sill
  • 6. Stairs: 7-3/4 riser, 10 tread
  • 7. Anchor bolts: 1/2, 7, 6
  • 8. Joists: no middle-third notches
  • 9. Guards: 30 trigger, 36 high
  • 10. Final compliant: issue CO

ICC Residential Building Inspector (B1)

  • Practice Questions 102 questions Study Guide 44 topics Cheat Sheet 88 facts Flashcards 50 cards Videos 1 video Blogs 2 blogs 1 Job Wiki Free CE Podcast