Cheat sheet
IOSH Managing Safely Cheat Sheet
Introducing Managing Safely
- Not published of exam
- Why Manage Safely Moral Legal Financial Accident Cost Iceberg Accountability
Assessing Risks
- Not published of exam
- Risk Assessment Steps 5x5 Risk Matrix Project Marking Scheme Project Row Builder
Controlling Risks
- Not published of exam
- ERIC PD Hierarchy Control Toolkit Control Picker Collective vs Personal
Understanding Responsibilities
- Not published of exam
- Law and Duties Enforcement and Systems Criminal vs Civil Law Improvement vs Prohibition
Understanding Hazards
- Not published of exam
- Six Hazard Categories Exposure Values Height, Handling, Fire Extinguishers and Electricity Stress Management Standards
Investigating Incidents
- Not published of exam
- Incident Definitions RIDDOR Reporting RIDDOR Picker Immediate vs Root Cause
Measuring Performance
- Not published of exam
- Performance Indicators Audit Evidence and Rates Monitoring Picker Inspection vs Audit
Quick Facts
- Course IOSH Managing Safely
- Modules 7 modules
- Duration Three days equivalent
- Assessment Paper plus project
- Project pass 23 of 38
- Project time Two hours maximum
- Project hazards Four hazards required
- Risk matrix 5x5, max 25
- Paper format Not published by IOSH
- Certificate Does not expire
- Refresher One day, three-year window
- Audience Managers and supervisors
Why Manage Safely IN
- Moral case Nobody harmed by work
- Legal case Criminal duties, civil claims
- Financial case Accidents drain money
- Responsibility Duty to act
- Accountability Cannot be delegated
- Delegation Tasks pass down only
- Insured costs Claims, damaged plant
- Uninsured costs Lost time, investigation, overtime
- Cost iceberg Uninsured costs hidden below
Five Risk Steps AS
- Identify Assess Control Record Review
- Identify: the hazards Assess: who and how Control: use hierarchy Record: five plus employees Review: change or incident
Hazard vs Risk AS
Hazard
- Potential to cause harm
- Property of the thing
- No numbers needed
Risk
- Likelihood times consequence
- Rated out of 25
- Changes with controls
- Source vs chance
Project Row Builder AS
- Choosing a hazard → Pick significant, not trivial
- Describing the hazard → Name the harm source
- Listing who is harmed → Quantify each group
- Rating current risk → Likelihood times consequence
- Adding further controls → Mix hard and soft
- Rating residual risk → Lower the likelihood
- Assigning an action → Job title plus date
Risk Assessment Steps AS
- Step 1 Identify the hazards
- Step 2 Assess the risks
- Step 3 Control the risks
- Step 4 Record your findings
- Step 5 Review the controls
- Record trigger Five or more employees
- Suitable and sufficient Proportionate, covers significant hazards
- Review trigger Incident or significant change
- Vulnerable groups Young, new, expectant, lone
Project Marks Add Up AS
- 1 + 9x4 + 1 = 38
- Top of form: 1 Each hazard row: 9 Four rows: 36 Bottom of form: 1 Pass: 23 of 38
5x5 Risk Matrix AS
- Likelihood Rate 1 to 5
- Consequence Rate 1 to 5
- Risk rating Likelihood times consequence
- Scale Rating out of 25 IOSH
- Examiner tolerance Within plus or minus one Project
- Rating 15-16 Urgent action expected IOSH
- Residual rating Must be lower
- Consequence 5 Foreseeable death
Project Marking Scheme AS
- Top of form 1 mark
- Each hazard row 9 marks available
- Four hazard rows 36 marks total
- Bottom of form 1 mark
- Total marks 38 marks
- Pass mark 23 of 38
- Not a hazard Lose all nine marks
- Time guide Two hours maximum
ERIC PD Hierarchy CO
- Eliminate Reduce Isolate Control PPE Discipline
- Eliminate: remove hazard Reduce: substitute safer Isolate: guard or enclose Control: safe system PPE: last resort Discipline: monitor and enforce
Safe System vs Permit CO
Safe system
- Defined working method
- Every routine task
- From the risk assessment
Permit
- Written authorisation
- High-risk jobs only
- Signed off, time limited
- Method vs authorisation
Control Picker CO
- Hazard can be removed → Eliminate ( Best option )
- Safer substitute exists → Reduce ( Substitution )
- Keep people away → Isolate ( Guard or barrier )
- Change how work runs → Control ( Safe system )
- Residual risk still remains → PPE ( Last resort )
- Controls being ignored → Discipline ( Monitor, enforce )
ERIC PD Hierarchy CO
- Eliminate Remove the hazard 1
- Reduce Substitute safer option 2
- Isolate Enclosures, barriers, guarding 3
- Control Safe systems, training, rotation 4
- PPE Last resort protection 5
- Discipline Monitor and enforce 6
- Collective first Protects everyone automatically
- Personal last Needs individual compliance
Collective vs Personal CO
Collective
- Protects everyone at risk
- Works without user action
- Guard rail
Personal
- Protects one person
- Needs correct use
- Harness and lanyard
- Automatic vs dependent
Control Toolkit CO
- Reasonably practicable Risk versus time, money
- Gross disproportion Sacrifice far outweighs risk
- Safe system of work Defined method from assessment
- Permit to work Written high-risk authorisation
- Permit examples Hot work, confined spaces
- Competence Skills, knowledge, experience, training
- Supervision Cover while still learning
- PPE rules Suitable, maintained, free of charge
HSG65 Plan Do Check Act RE
- Plan Do Check Act
- Plan: policy and objectives Do: organise, control risks Check: measure performance Act: review and improve
Criminal vs Civil Law RE
Criminal
- State prosecutes breach
- Fines and imprisonment
- HSE or council
Civil
- Injured person sues
- Compensation for loss
- Negligence claim
- Punish vs compensate
Law and Duties RE
- HSWA 1974 Main UK safety act
- Section 2 Employer duties to employees
- Section 7 Employee care and co-operation
- Section 8 No interference or misuse
- Written policy Five or more employees
- MHSWR 1999 Assessment and arrangements duties
- Criminal law Punishment, fines, imprisonment
- Civil law Negligence, compensation claims
- Three knowledge tests Common, industry, expert
Improvement vs Prohibition RE
Improvement
- Breach must be fixed
- Stated compliance period
- Appeal suspends notice
Prohibition
- Stops dangerous activity
- Serious injury risk
- Appeal does not suspend
- Fix it vs stop it
Enforcement and Systems RE
- Improvement notice Fix breach within period
- Prohibition notice Stop dangerous activity
- Appeal window 21 days to tribunal
- Appeal effect Improvement suspended, prohibition stands
- HSE inspectors Factories, construction, agriculture, hospitals
- Local authority Shops, offices, warehouses, hospitality
- HSG65 Plan, Do, Check, Act
- ISO 45001 OSH management system standard
Manual Handling TILE HA
- Task Individual Load Environment
- Task: how it moves Individual: the person Load: weight and shape Environment: space, floor, light
EAV vs ELV HA
Action value
- Triggers required action
- Noise 80 and 85
- Vibration 2.5
Limit value
- Must not be exceeded
- Noise 87 dB(A)
- Vibration 5.0
- Act vs never exceed
Height Equipment Picker HA
- Job can be done below → Avoid work at height ( First choice )
- Safe existing place available → Guarded platform ( Prevent falls )
- Work needs a platform → Tower or MEWP ( Collective )
- Low risk, 30 minutes → Ladder ( Short duration )
- Fall cannot be prevented → Net or airbag ( Minimise consequence )
- Only personal protection possible → Harness and lanyard ( Needs correct use )
Six Hazard Categories HA
- Physical Noise, vibration, radiation
- Chemical Dusts, fumes, solvents
- Biological Bacteria, viruses, mould
- Mechanical Machinery, moving parts
- Environmental Wet floors, lighting, temperature
- Organisational Workload, shifts, stress
Six Stress Standards HA
- Demands Control Support Relationships Role Change
- Demands: workload Control: autonomy Support: help available Relationships: behaviour Role: clarity Change: communication
Exposure Values HA
- Noise lower value 80 dB(A) daily
- Noise upper value 85 dB(A) daily
- Noise limit value 87 dB(A) daily
- Peak values 135, 137, 140 dB(C)
- Hand-arm EAV 2.5 m/s2 A(8)
- Hand-arm ELV 5.0 m/s2 A(8)
- COSHH duty Prevent or adequately control
- Asbestos duty Find, record, manage, plan
Height, Handling, Fire HA
- Height hierarchy Avoid, prevent, minimise
- Ladder use Low risk, short duration
- Short duration Maximum 30 minutes
- Ladder angle One out, four up
- TILE Task, Individual, Load, Environment
- Handling duty Avoid, assess, reduce
- Fire triangle Fuel, oxygen, heat
- Class A fire Wood, paper, textiles
- Class F fire Cooking oils and fats
Extinguishers and Electricity HA
- Water Red, Class A only
- Foam Cream, solids and liquids
- Dry powder Blue, liquids and electrical
- CO2 Black, electrical and liquids
- Wet chemical Yellow, cooking oils only
- Site voltage 110V centre tapped earth
- Voltage to earth Maximum 55 volts
- Safest tools Battery powered equipment
Stress Management Standards HA
- Demands Workload, patterns, environment
- Control Say over the work
- Support Encouragement, sponsorship, resources
- Relationships Conflict and unacceptable behaviour
- Role Clear, non-conflicting duties
- Change Managed and communicated well
Investigation Four Steps IN
- Gather Analyse Identify Plan
- Gather: facts and witnesses Analyse: why it happened Identify: controls needed Plan: actions, owners, dates
Immediate vs Root Cause IN
Immediate
- Agent of harm
- Visible at the scene
- Missing guard
Root
- Management system failing
- No maintenance plan
- Fixes many events
- Trigger vs system
RIDDOR Picker IN
- Worker killed at work → Notify without delay ( Report follows )
- Specified injury occurs → Report within 10 days
- Absent over seven days → Report within 15 days
- Absent four to seven days → Record only ( Not reportable )
- Written disease diagnosis → Report the disease
- Listed dangerous occurrence → Report within 10 days
Incident Definitions IN
- Accident Event causing injury, harm
- Incident Accident or near miss
- Near miss No harm, clear potential
- Undesired circumstance Conditions with harm potential
- Immediate cause Obvious agent of harm
- Underlying cause Workplace failure behind it
- Root cause Management system failing
- No-blame rule Find causes, not culprits
RIDDOR Reporting IN
- Death at work Notify without delay
- Specified injuries Report within 10 days
- Dangerous occurrences Report within 10 days
- Over-seven-day injury Report within 15 days
- Over-three-day injury Record, do not report
- Occupational disease Report on written diagnosis
- Responsible person Usually the employer
- Record contents Date, place, people, description
Active vs Reactive ME
Active
- Before harm occurs
- Inspections and training
- Leading indicators
Reactive
- After harm occurs
- Injuries and absence
- Lagging indicators
- Prevent vs count
Monitoring Picker ME
- Check conditions today → Inspection ( Frontline )
- Test the whole system → Audit ( Evidence based )
- Need independent challenge → External auditor
- Need low cost check → Internal auditor
- Measure effort invested → Leading indicator ( Active )
- Measure outcomes suffered → Lagging indicator ( Reactive )
Performance Indicators ME
- Active monitoring Checks before harm occurs
- Reactive monitoring Counts what went wrong
- Leading indicator Training done, actions closed
- Lagging indicator Injury and absence rates
- Inspection Frontline conditions on day
- Audit Systematic system examination
- Internal auditor Knows operation, less independent
- External auditor Independent, brings outside comparison
- Benchmarking Compare against similar organisations
Inspection vs Audit ME
Inspection
- Conditions on the day
- Frontline walk round
- Quick and frequent
Audit
- Whole management system
- Documents, interviews, observation
- Periodic and deep
- Snapshot vs system
Audit Evidence and Rates ME
- Document evidence Policies, records, assessments
- Interview evidence What people actually say
- Observation evidence What actually happens
- Good KPI Specific, measurable, owned, timed
- Incidence rate Injuries per 100,000 workers
- Rate purpose Compare sites, sectors, years
- Falling injury count May mean suppressed reporting
- Ill health lag Long latency hides exposure
Common Traps
Hazard vs risk
- Hazard is the source ≠ Risk is the chance
Accountability vs task
- Tasks can be delegated ≠ Accountability stays with you
Reduce vs isolate
- Reduce substitutes safer option ≠ Isolate separates people physically
Practicable vs reasonably practicable
- Practicable means technically possible ≠ Reasonably practicable weighs cost
Notice types
- Improvement fixes a breach ≠ Prohibition stops the work
Report vs record
- Over seven days reportable ≠ Over three days recorded
EAV vs ELV
- Action value triggers control ≠ Limit value must never be exceeded
Inspection vs audit
- Inspection checks conditions today ≠ Audit tests the system
Cause depth
- Immediate cause is visible ≠ Root cause is managerial
Residual rating direction
- Likelihood usually falls ≠ Consequence usually stays same
PPE placement
- PPE is last resort ≠ Never the first control
Fewer injuries claim
- Low counts may hide underreporting ≠ Ill health lags years
Last Minute
- 1. Seven modules, three days equivalent
- 2. Project pass mark: 23 of 38
- 3. Project needs four significant hazards
- 4. Risk rating = likelihood x consequence
- 5. 5x5 matrix maximum is 25
- 6. Residual rating must be lower
- 7. ERIC PD: PPE near bottom
- 8. Collective protection before personal protection
- 9. Record findings at five employees
- 10. Noise action values 80 and 85
- 11. Noise limit value is 87
- 12. Vibration EAV 2.5, ELV 5.0
- 13. Ladders: low risk, 30 minutes
- 14. Specified injuries: report 10 days
- 15. Over seven days: report 15 days
- 16. Improvement fixes; prohibition stops work
- 17. Active monitoring happens before harm
- 18. Audit tests system; inspection checks conditions
- 19. Immediate cause visible; root cause managerial
- 20. Certificate never expires; refresher recommended
IOSH Managing Safely
- Practice Questions 128 questions Study Guide 43 topics Cheat Sheet 137 facts Flashcards 50 cards