Maryland Law: Editorial Revision Group

  • Not published of exam
  • Grade Horsepower Thresholds Attendance & Monitoring Rules Exam, Renewal & Inspection Law Largest Single Unit Rule

Boilers, Valves & Safety Controls

  • Not published of exam
  • Boiler Types & ASME Codes Safety Valves & Gauge Glass Low-Water Cutoff & Controls Pumps & Steam Header Valves

Burners, Combustion & Emergencies

  • Not published of exam
  • Combustion, Draft & Purge Flame Safeguard Sequence Sequential & Emergency Operations Low-Water vs Tube Rupture

Water Treatment & Blowdown

  • Not published of exam
  • Scale, Sludge & Carryover Deaeration & Chemical Treatment Bottom vs Surface Blowdown Zeolite Softener Limits

Auxiliaries, Chillers & Electricity

  • Not published of exam
  • Condensers, NPSH & Pumps Chillers & Refrigeration Cycle Basic DC & AC Electricity Motor Overload Protection

Quick Facts

  • Licensing Board Maryland Board of Stationary Engineers
  • Exam Delivery PSI; qualification approval before scheduling
  • Scored Outline Count G5–G4: 60; G3–G1: 80
  • Possible Additional Items 5–10 experimental, unscored; extra time
  • Answering Time 120 minutes for scored examination
  • Passing Score 70%: 42/60 or 56/80
  • Book Policy G5–G4 approved open-book; G3–G1 closed-book
  • Licence Term Normally two years; statutory stagger exception
  • Revision Filters Five editorial groups; official outlines separate

Maryland 5-Grade Horsepower Ladder MD

  • 30-99 G5/G4, 100-299 G3, 300-499 G2, 500+ G1
  • G5: 30-99 HP non-public G4: 30-99 HP any building G3: 100-299; G2: 300-499; G1: 500+

Grades 5–4 vs Grades 3–1 PSI Exams MD

Grades 5 & 4

  • 60 scored-outline items; 120 minutes
  • Open book (approved references)
  • Need 42 correct (70%)

Grades 3, 2 & 1

  • 80 scored-outline items; 120 minutes
  • Closed book examination
  • Need 56 correct (70%)
  • 60 open-book vs 80 closed-book

Maryland License Grade Picker MD

  • Statutory heating-boiler definition applies → Stationary-service licensing definition excludes heating boilers ( Inspection obligations are a separate question )
  • Hot-water statutory heating definition → Pressure ≤160 psig OR temperature ≤250°F ( Statutory OR; distinct from ASME shorthand )
  • 30-99 HP in non-public building → Grade 5 Stationary Engineer
  • 30-99 HP in public building → Grade 4 Stationary Engineer
  • Largest single unit 100-299 HP → Grade 3 Stationary Engineer
  • Largest single unit 300-499 HP → Grade 2; 500+ HP Grade 1

Grade Horsepower & Trigger Rules MD

  • License Trigger Over 15 psi AND 30+ HP
  • 30 HP Equivalent About 1,003,000 Btu per hour
  • 1 Boiler HP Evaporates 34.5 lb/h from-and-at 212°F ≈33,475 Btu/h thermal output
  • Grade 5 Scope 30-99 HP, non-public building
  • Grade 4 Scope 30-99 HP, any building
  • Grade 3 Scope 100-299 HP largest single unit
  • Grade 2 Scope 300-499 HP largest single unit
  • Grade 1 Scope 500 HP or more; statutory conditions

2-Year Power Boiler Inspection Extension MD

  • Board may extend certificate interval; conditions must all qualify
  • Power boiler; Board-approved extension only Continuous internal treatment; experienced PE supervises Outage date, time and reason records Water analyses: ≤48 operating-hour intervals Annual external inspection remains separate

COMAR 09.17 Alarm vs Shutdown Picker MD

  • High stack flue gas temperature → Sound alarm AND shut burner
  • Steam high-pressure or low/high-water condition → Specified monitoring alarm and automatic shutdown
  • Low steam pressure or burner off → Alarm required; shutdown follows applicable safeguards ( Not shutdown triggers under section .07 )
  • Boiler shuts down automatically → Licensee/designee physically inspects before restart ( Qualifying system shutdown under section .07 )

Attendance: Qualified Monitoring Exceptions MD

  • G5, No Qualified Monitoring Visit every 24 operating hours minimum
  • G4 Public, No Monitoring Attend continuously; special school rule applies
  • G4 School, No Monitoring School hours; other hours ≥150 occupants
  • G5, Qualified Monitoring Weekly visit; 24-hour availability; daily log
  • G4–G1 Monitored Public Visit every eight open hours minimum
  • G3–G1 Monitored Non-Public Scheduled visits not required; duties remain
  • Qualifying Monitoring 24-hour computerized monitoring plus automatic controls
  • 300 HP or More Monitor, indicate AND record specified points
  • Qualifying Shutdown Manual Reset Licensee/designee physically inspects before restart
  • Monitored School G4 Exception School-hours/≥150-occupant condition still applies
  • All Monitored Attendance Exceptions Responsibility, 24-hour availability, daily log remain

Exam, Renewal & Inspection Law MD

  • G5-G4 Pass Mark 42 of 60 items correct 70%
  • G3-G1 Pass Mark 56 of 80 items correct 70%
  • Board FAQ: Reapply After Failure First 30 days; subsequent requests 60
  • PSI Registration Validity 90 days; fee nonrefundable, nontransferable
  • Score Validity Apply for license within 2 years
  • Expired > 24 Months Non-renewable; must retest
  • Covered Power Boiler Inspections Annual inspections; approved certificate extension possible
  • Accident Notice Notify Chief Inspector within 24h
  • Unauthorized Material During Examination Reject application; reexamination barred ≥1 year

PSI Outline Counts: Part 1 MD

  • General knowledge and problem solving G5–4: 20; G3: 10; G2–1: 5
  • Basic electricity G5–4: 5; G3: 5; G2–1: 5
  • Boiler types and equipment G5–4: 5; G3: 10; G2–1: 5
  • Burners and fuel train G5–4: 5; G3: 10; G2–1: 10
  • Pumps and valves G5–4: 5; G3: 10; G2–1: 10
  • Sequential operations G5–4: 0; G3: 10; G2–1: 10

PSI Outline Counts: Part 2 MD

  • Inspections and maintenance G5–4: 5; G3: 5; G2–1: 10
  • Central station and chillers G5–4: 0; G3: 5; G2–1: 5
  • Water treatment G5–4: 5; G3: 5; G2–1: 10
  • Emergency operations G5–4: 5; G3: 5; G2–1: 5
  • Auxiliary equipment G5–4: 5; G3: 5; G2–1: 5

Firetube vs Watertube Boilers BO

Firetube Boiler

  • Hot gases pass inside tubes
  • Large water volume, slower response
  • Often lower duty; design ratings govern

Watertube Boiler

  • Water circulates inside the tubes
  • Often faster response; design-dependent
  • Handles high pressures and loads
  • Gas in tubes vs water

Boiler Types, ASME & Fittings BO

  • ASME Section I Power-boiler construction; steam above 15 psig
  • ASME Section IV Heating-boiler construction; applicable limits and edition
  • ASME Section VIII Pressure-vessel construction; scope and exclusions apply
  • MAWP and Valve Settings At least one valve ≤MAWP Power boiler, COMAR .24G
  • Safety Valve Rule Direct connection; no shutoff valve
  • Try-Lever Test Movement check, not set-pressure calibration
  • Water Column Dampens surges; test per approved procedure
  • Non-Return Valve Prevents backflow when boiler pressure drops
  • Existing Power Boiler Additional Valves Settings ≤103% MAWP; full conditions apply

Operating Control vs High-Limit Control BO

Operating Control

  • Cycles or modulates burner daily
  • Holds normal operating pressure
  • Normal cycling follows control design

High-Limit Control

  • Independent protective limit on unsafe conditions
  • Setting coordinated with approved relief protection
  • Reset mode follows applicable code/design
  • Normal cycling vs safety lockout

Three Ts of Complete Combustion CO

  • Temperature, Turbulence, and Time with right oxygen
  • Temperature: ignite fuel Turbulence: mix air-fuel Time: burn before tubes

Low-Water Emergency vs Tube Rupture CO

Low-Water Condition

  • Secure heat input under emergency procedure
  • Dry/overheated boiler: no water addition
  • Inspect and obtain authorized restart clearance

Tube Rupture

  • Secure heat input under emergency procedure
  • Feedwater decision depends on boiler condition
  • Isolation follows equipment-specific approved procedure
  • Overheating risk vs rupture-specific response

Boiler Emergency Action Picker CO

  • Low water; dry/overheated boiler suspected → Secure heat input; no water addition ( Approved shutdown and inspection before restart )
  • Boiler tube ruptures on line → Approved emergency shutdown; keep personnel clear ( Condition/equipment determine feedwater and isolation )
  • Safety valve lifts repeatedly → Prevent overpressure; investigate controls through procedure ( Never gag or obstruct relief )
  • Burner trips on flame failure → Investigate cause; approved purge before restart ( No repeated blind resets )
  • Boiler accident or explosion occurs → Notify Chief Inspector within 24h

Burners, Draft & Flame Safeguard CO

  • 3 Ts of Combustion Temperature, turbulence, and time
  • Complete Hydrocarbon Combustion CO₂ and water; other products possible
  • Incomplete Sign Carbon monoxide, smoke, or soot
  • Forced Draft Fan pushes air toward combustion chamber
  • Induced Draft Fan draws combustion gases toward stack
  • Balanced Draft Both fans; controlled furnace pressure
  • Pre-Purge / Post-Purge Prescribed airflow clears accumulated combustibles
  • Flame Scanner Flame-safeguard system trips fuel upon failure

Bottom Blowdown vs Surface Blowdown WA

Bottom Blowdown

  • Drawn from lowest mud drum
  • Short, intermittent valve operation
  • Removes settled sludge solids

Surface Blowdown

  • Skims just below water line
  • Metered continuous or intermittent design
  • Controls total dissolved solids (TDS)
  • Settled sludge vs surface TDS

Water Problems: Treatment-Plan Decisions WA

  • TDS exceeds approved treatment-plan limit → Adjust blowdown under the approved plan ( No universal valve opening or flow )
  • Sludge settles in mud drum → Approved intermittent bottom-blowdown procedure
  • Calcium and magnesium hardness present → Verify softener and approved treatment plan
  • Dissolved oxygen causing tube pitting → Check deaeration and prescribed scavenger treatment ( Qualified treatment specialist sets chemical dose )

Water Treatment & Blowdown WA

  • Scale Hard deposits; hardness often contributes
  • Sludge Loose settled suspended solids
  • Dissolved Oxygen Causes localized tube metal pitting
  • Deaerator Heats and vents non-condensable gases
  • Oxygen Scavenger Chemically removes residual dissolved O2
  • Zeolite Softener Swaps Ca/Mg ions for sodium
  • Bottom Blowdown Short intermittent removal of sludge
  • Surface Blowdown TDS control; continuous or intermittent design

Four-Step Refrigeration Cycle Order AU

  • Compressor, Condenser, Expansion device, Evaporator in loop
  • Compressor: raises P and T Condenser: rejects heat Expansion drops P; Evaporator cools

Centrifugal vs Positive Displacement Pump AU

Centrifugal Pump

  • Uses rotating impeller velocity
  • Flow drops as pressure rises
  • Closed discharge can overheat; follow manufacturer

Positive Displacement

  • Moves fixed volume per stroke
  • Builds destructive pressure if blocked
  • Protect blocked discharge with approved relief
  • Variable flow vs fixed displacement

Auxiliaries, Pumps & Chillers AU

  • Elevated Deaerator Provides NPSH to feed pump
  • Cavitation Vapor bubbles form, then collapse
  • Surface Condenser Condenses exhaust; supports turbine vacuum
  • Economizer Preheats feedwater using flue gas
  • Compressor Raises refrigerant pressure and temperature
  • Condenser (Chiller) Rejects heat, liquefies refrigerant
  • Expansion Device Throttles pressure; refrigerant partly flashes
  • Evaporator Absorbs heat from building load

Basic Electricity & Motor Controls AU

  • Ohm's Law Volts equal amps times ohms E = I × R
  • DC Electric Power Watts equal volts times amps P = E × I; DC
  • Series Circuit Same current; voltages add up
  • Parallel Circuit Same voltage; branch currents add
  • Motor Overload Protects windings from sustained overcurrent
  • Fuses / Breakers Protect against short-circuit faults
  • Lockout / Tagout Isolate, lock, control stored energy, verify
  • AC Real Power Single-phase: V × I × power-factor

Common Traps

Single-Unit Capacity vs Plant Capacity

  • Licence grade: largest individual regulated unit ≠ Plant total: not the grade calculation

Engineer Licensing vs Equipment Inspection

  • Title 6.5: engineer grades and attendance ≠ Title 12-9: equipment inspection and certificates

Routine Feedwater vs Overheated Dry Boiler

  • Normal operation: maintain approved water level ≠ Overheated dry boiler: no water addition

Gauge Indication vs Verified Water Level

  • Motionless glass: potentially obstructed, not proof ≠ Approved verification: investigate uncertain water level

Softening vs Deaeration

  • Softener: exchanges calcium and magnesium ions ≠ Deaerator: heats and removes dissolved gases

Ordinary Reciprocity vs Military Recognition

  • Ordinary route: no out-of-state reciprocity ≠ Qualified military relocation: separate recognition provisions

Last Minute

  • 1. Trigger: >15 psi AND ≥30 HP
  • 2. Heating boilers: excluded from licensing definition
  • 3. Grade: largest single regulated unit
  • 4. Pass: 70% (42/60; 56/80)
  • 5. G5–4: approved open-book; G3–1: closed-book
  • 6. Reapplication: first 30 days; subsequent 60
  • 7. Power certificate extension: Board-approved, not automatic
  • 8. Required certification: display licence with photograph
  • 9. Identification: valid government-issued photo ID available
  • 10. Boiler accident notice: within 24 hours
  • 11. Safety relief: no intervening shutoff valve
  • 12. Dry/overheated boiler: no water addition
  • 13. Steam admission: equipment-specific approved pressure sequence
  • 14. Qualifying manual reset: physical inspection first

Maryland Boiler Operator

  • Practice Questions 349 questions Study Guide 27 topics Cheat Sheet 80 facts Flashcards 50 cards Games 20 terms 1 Job Wiki Podcast
  • Word games 20 terms Guess the Term T E R M S Read the clue and guess the term in 6 tries. Word games 20 terms Term Match Swap tiles to line up three of the same term. Word games 20 terms Term Pairs ? ✓ ✓ ? ? Flip two cards at a time to find matching terms. Word games 20 terms Term Search Q T E R M X Find five hidden terms in a grid of letters.