Cheat sheet

NASCLA Contractor Cheat Sheet

Practice this exam

General Requirements

  • 22% of exam
  • Planning Estimating Safety Codes Controls

Procurement + Contracts

  • 27% of exam
  • Bidding Bonds Changes Submittals Closeout

Site Construction

  • 13% of exam
  • Soils Excavation Grading Drainage Erosion

Trade Coordination

  • 38% of exam
  • Concrete Masonry Metals Wood MEP

Quick Facts

  • Exam NASCLA commercial
  • Provider PSI
  • Format Open book
  • Questions 115
  • Time 5.5 hours
  • Pass 70 percent
  • Score 81 correct

Float vs Delay GE

Float

  • Available slack
  • May absorb slip

Delay

  • Schedule impact
  • May need change
  • Critical path controls

Exam Strategy GE

  • Open book Fast lookup required
  • Tabs Find references quickly
  • Index Use under pressure
  • Time budget About three minutes
  • Math Show units
  • Flagging Return later
  • Priority Contracts first

Project Controls GE

  • Critical path Controls finish date
  • Float Allowable slippage
  • Baseline Approved plan
  • Lookahead Near-term schedule
  • Takeoff Measure quantities
  • Unit price Cost per unit
  • Contingency Risk reserve

Contract Flow CO

  • Bid, bond, build, change, close.
  • Bid Bond Build Change Close

Bid vs Performance CO

Bid bond

  • Before award
  • Protects bid reliance

Performance bond

  • After award
  • Protects completion
  • Timing distinguishes them

Document Picker CO

  • Before bid change → Addendum
  • Clarify conflict → RFI
  • Show product data → Submittal
  • Fabrication detail → Shop drawing
  • Change agreed → Change order
  • Change directed → CCD
  • Payment requested → Pay application
  • Work nearly done → Punch list

Bidding + Bonds CO

  • Invitation Solicits bids
  • Addendum Prebid change
  • Bid bond Protects owner
  • Performance bond Guarantees completion
  • Payment bond Protects subs
  • Bid opening Public result
  • Responsible bidder Qualified bidder

Closeout CO

  • Punch, correct, document, warrant, final.
  • Punch Correct Document Warrant Final

RFI vs Submittal CO

RFI

  • Asks clarification
  • Information gap

Submittal

  • Shows proposed item
  • Review before work
  • Question versus review

Contract Admin CO

  • Change order Formal modification
  • CCD Directed change
  • RFI Request clarification
  • Submittal Review before install
  • Shop drawing Fabrication detail
  • Allowance Undefined cost reserve
  • Lien waiver Payment rights release

Substantial vs Final CO

Substantial

  • Owner can use
  • Punch list remains

Final

  • All work complete
  • Closeout delivered
  • Use before perfect

Site Safe SI

  • Classify, protect, access, inspect, control.
  • Classify Protect Access Inspect Control

Site Picker SI

  • Trench hazard → Protective system
  • Soil unknown → Classify soil
  • Water present → Dewatering plan
  • Slope needed → Grade stakes
  • Sediment risk → Erosion control
  • Backfill placed → Compact lifts
  • Concrete placed → Cure concrete
  • Envelope leak → Check flashing

Safety + Site SI

  • Competent person Corrects hazards
  • PPE Personal protection
  • Excavation Cave-in hazard
  • Soil class Protective system driver
  • Access Safe egress
  • Erosion Control sediment
  • Compaction Increase density

Slump vs Strength TR

Slump

  • Fresh consistency
  • Workability check

Strength

  • Hardened capacity
  • Cylinder test
  • Do not confuse

Concrete + Masonry TR

  • Slump Fresh workability
  • Curing Maintain moisture
  • Rebar Tension reinforcement
  • Control joint Planned crack
  • CMU Concrete masonry unit
  • Mortar Bonds units
  • Grout Fills cells

Metals + Wood TR

  • Structural steel Frame members
  • Bolt Mechanical fastener
  • Weld Fused connection
  • Joist Floor support
  • Stud Wall vertical
  • Sheathing Panel skin
  • Lumber grade Strength classification

Envelope + MEP TR

  • Flashing Water diversion
  • Vapor retarder Moisture control
  • Insulation Thermal resistance
  • Roofing Weather barrier
  • HVAC Air systems
  • Plumbing Water systems
  • Electrical Power systems

Common Traps

Open Book Overconfidence

  • Lookup must be fast ≠ Practice reference routes

Document Mixups

  • RFI asks questions ≠ Submittal shows products

Bond Timing

  • Bid before award ≠ Performance after award

Schedule Math

  • Critical path matters ≠ Float can vanish

Trade Detail Depth

  • General contractor level ≠ Coordinate disciplines

Last Minute

  • 1. Tab official references
  • 2. Practice index lookup
  • 3. Review contract documents
  • 4. Drill bond purposes
  • 5. Memorize site safety
  • 6. Check unit conversions
  • 7. Separate completion stages
  • 8. Manage question pacing

NASCLA Contractor

  • Practice Questions 200 questions Study Guide 49 topics Cheat Sheet 56 facts Flashcards 50 cards Shorts 3 short s Videos 1 video Blogs 1 blog Free CE Podcast