Cheat sheet

NEBOSH PSM Cheat Sheet

Practice this exam

Process safety leadership

  • Not published of exam
  • Process Safety Basics Leadership + Culture Performance Indicators Major Accident Lessons Management of Change

Management of process risk

  • Not published of exam
  • Risk Techniques HAZOP Guide Words Bow-tie + LOPA Control Hierarchy Asset Integrity Permit-to-Work Handover + Contractors UK Regulatory Frame

Process safety hazard control

  • Not published of exam
  • Operating Limits Safety-Critical Standards Utilities + Static Dangerous Substances Reaction Hazards Bulk Storage

Fire and explosion protection

  • Not published of exam
  • Fire + Explosion Types Detection + Protection Dust Explosions Emergency Preparedness

Quick Facts

  • Unit PSM1 (single unit)
  • Questions 40 multiple-choice
  • Extended 10 scenario questions
  • Time 90 minutes
  • Pass 60% = 24 of 40
  • Grades Pass or Refer
  • Elements 4 syllabus elements
  • Hours 28 taught + 20 private
  • Level SCQF 7, 5 credits
  • Sittings Monthly, 24-hour window
  • Results 15 working days
  • Spec October 2023

Case Study Lessons LE

  • Piper permits, Flixborough change, Buncefield overfill
  • Texas City: injury rates misled Bhopal: minimise inventory Seveso: off-site information

Process vs Personal Safety LE

Process safety

  • Loss of containment
  • Rare, catastrophic outcome
  • Engineering plus management

Personal safety

  • Slips, trips, handling
  • Frequent, lower consequence
  • Behaviour and PPE
  • Catastrophe vs individual injury

PSM1 Syllabus Map LE

  • Element 1 Process safety leadership 4 hours
  • Element 2 Management of process risk 9 hours
  • Element 3 Process safety hazard control 10 hours
  • Element 4 Fire and explosion protection 5 hours
  • Taught minimum 28 hours tuition
  • Private study About 20 hours
  • Paper coverage At least one per element
  • Mark weightings NEBOSH publishes none

Leading vs Lagging Indicators LE

Leading

  • Checks controls working
  • Proactive measurement
  • Inspections completed on time

Lagging

  • Counts failures occurred
  • Reactive measurement
  • Losses of containment
  • Before vs after failure

Process Safety Basics LE

  • Process safety Prevents catastrophic loss of containment
  • Personal safety Prevents individual worker injury
  • PSM system System preventing major incidents
  • Major accident Fire, explosion, toxic release
  • Loss of containment Energy or substance escapes
  • Incident (ISO 45001) Event causing or risking harm
  • Hazard realisation Worst-case consequence pathway
  • Barrier Control between hazard and harm

Leadership + Culture LE

  • Board visibility Directors own major accident risk
  • PSM-critical roles Responsibilities defined and assigned
  • Accountability Held at every level
  • Resources Human, financial and physical
  • Objectives Reviewed and published openly
  • Worker consultation Committees, groups, safety circles
  • Competence Knowledge, skills, experience, reliability
  • Competency matrix Maps training to roles

Performance Indicators LE

  • Leading indicator Checks controls before failure
  • Lagging indicator Counts failures already happened
  • Dual assurance Pair leading with lagging
  • HSG254 HSE process safety indicators HSE
  • Benchmarking Compare practice between organisations
  • Corporate memory Design and modification records kept
  • Incident investigation Find causes, share lessons
  • External sources HSE, CSB, trade bodies

Major Accident Lessons LE

  • Piper Alpha 1988 Permit and handover failure
  • Buncefield 2005 Overfill protection must be independent
  • Texas City 2005 Injury rates hid process risk
  • Flixborough 1974 Unassessed temporary plant modification
  • Bhopal 1984 Minimise hazardous inventory
  • Seveso 1976 Drove EU major-hazard law

Management of Change LE

  • Trigger Plant, process or people change
  • Hazard review Proportionate risk analysis first
  • Authorisation Competent person signs off
  • Safety-critical removal Senior management sanction required
  • Documentation Records retain process knowledge
  • Consultation Inform everyone affected
  • Training Given where change requires
  • Temporary change Managed like a permanent one

HAZOP Guide Words PR

  • NO | MORE | LESS | REVERSE | OTHER THAN
  • AS WELL AS: contamination PART OF: wrong ratio Pair with flow/pressure/temp Deviation = word + parameter

Preventive vs Mitigative Barriers PR

Preventive

  • Left of bow-tie
  • Stops the top event
  • Trips, permits, inspection

Mitigative

  • Right of bow-tie
  • Limits the consequences
  • Bunds, foam, evacuation
  • Stop it vs limit it

Which Study To Use PR

  • Concept or pre-modification → HAZID ( Broad hazards )
  • Line-by-line P&ID review → HAZOP ( Guide words )
  • Test barrier adequacy → LOPA ( Count IPLs )
  • Show barriers visually → Bow-tie ( Threats to consequences )
  • Component failure modes → FMEA
  • Mitigation after an event → Event tree ( Forward branching )
  • Quick team brainstorm → What-if
  • Numerical societal risk → QRA ( Quantitative )

Risk Techniques PR

  • HAZID Early broad hazard identification
  • HAZOP Guide-word deviation study
  • Bow-tie Barriers around a top event
  • Event tree Forward from initiating event
  • FMEA Component failure modes, effects
  • What-if Structured brainstorm questions
  • Qualitative Descriptive likelihood and consequence
  • Quantitative Numerical risk, QRA
  • ALARP Cost grossly disproportionate to benefit

Bow-tie Shape PR

  • Threats -> top event -> consequences
  • Left: preventive barriers Right: mitigative barriers Knot: loss of containment Escalation factors weaken barriers

HAZOP vs LOPA PR

HAZOP

  • Finds deviations
  • Guide words on nodes
  • Qualitative team study

LOPA

  • Tests barrier sufficiency
  • Counts independent layers
  • Semi-quantitative, order-of-magnitude
  • Find hazards vs size protection

Permit Picker PR

  • Welding, cutting, grinding → Hot work permit
  • Non-spark maintenance → Cold work permit
  • Work on electrical systems → Electrical permit
  • Vessel or tank entry → Entry permit ( Gas test first )
  • Breaking containment → Isolation certificate ( Lock out, tag out )
  • Adjacent simultaneous work → Cross-referenced permits
  • Routine task, own procedure → No permit needed

HAZOP Guide Words PR

  • NO / NONE No flow, no reaction
  • MORE High flow, pressure, temperature
  • LESS Low level, low flow
  • REVERSE Backflow into the supply
  • AS WELL AS Contamination plus intended flow
  • PART OF Wrong composition ratio
  • OTHER THAN Wrong material or activity
  • Parameters Flow, pressure, temperature, level
  • Node Section of P&ID studied
  • Chair Independent leader, mixed team

Control Hierarchy Order PR

  • Inherent, eliminate, substitute, segregate, engineer, admin, PPE
  • Passive beats active PPE is last Emergency response only mitigates

HAZID vs HAZOP PR

HAZID

  • Concept and early design
  • Includes non-process hazards
  • Broad and fast

HAZOP

  • Detailed design, P&IDs
  • Process deviations only
  • Slow and thorough
  • Wide early vs deep later

Bow-tie + LOPA PR

  • Threat Cause on the left
  • Top event Loss of containment
  • Consequence Outcome on the right
  • Preventive barrier Stops threat becoming top event
  • Mitigative barrier Limits consequence after release
  • Escalation factor Degrades or defeats a barrier
  • Escalation control Protects the weakened barrier
  • IPL Independent protection layer
  • IPL test Independent, effective, auditable
  • PFD Probability of failure on demand
  • Instrumented trip Sensor, logic, final element

COMAH Lower vs Upper Tier PR

Lower tier

  • Notify the authority
  • MAPP required
  • Public information duty

Upper tier

  • Safety report required
  • On-site emergency plan
  • Feeds off-site plan
  • Inventory decides the duties

Control Hierarchy PR

  • Inherent safety Design the hazard out
  • Elimination Minimise or remove inventory
  • Substitution Use a less hazardous material
  • Segregation Spacing between plant items
  • Engineering Passive preferred over active
  • Administrative Procedures and behaviour
  • PPE Last resort only
  • Emergency response Mitigates after the release

Asset Integrity PR

  • Asset integrity Equipment performs as intended
  • Design stage Maintainable and inspectable
  • Planned preventive Scheduled before failure
  • Condition monitoring Act on measured deterioration
  • Breakdown maintenance Run to failure
  • Risk-based inspection Effort follows failure consequence
  • Calibration Risk-based instrument accuracy checks
  • Ageing plant Life extension and obsolescence
  • Records Inspection and maintenance evidence

Permit-to-Work (HSG250) PR

  • Purpose Controls non-routine hazardous work
  • Scope Exact task and location
  • Duration Validity period stated
  • Isolation Lock out, tag out
  • Cross-reference Link to other open permits
  • Acceptance Named person confirms understanding
  • Gas testing Specific control before entry
  • Hot work Spark or flame producing
  • Cold work Non-spark maintenance tasks
  • Electrical work Own permit type
  • Hand-back Plant returned, permit closed
  • Not required Routine work under procedure

Handover + Contractors PR

  • Two-way handover Both parties share responsibility
  • Face to face Verbal plus written log
  • Time allowed Questions and clarification permitted
  • Plant walk Demonstrate the actual state
  • Selection Competence, not lowest price
  • Induction Site hazards and rules
  • Supervision Named site representative
  • Audit Before, during and after
  • HSG159 HSE managing contractors guide HSE

UK Regulatory Frame PR

  • COMAH 2015 GB major accident hazard rules
  • Seveso III EU directive COMAH implements
  • Lower tier Smaller dangerous substance inventory
  • Upper tier Larger inventory, extra duties
  • Competent Authority HSE plus environment regulator
  • MAPP Major accident prevention policy
  • Safety report Upper tier duty only
  • Emergency plan test At least every three years
  • Public information Duty on both tiers
  • DSEAR zones Classify explosive atmosphere areas

FARSI Performance Standards HA

  • Functionality Availability Reliability Survivability Interdependency
  • F: what it does A: uptime proportion R: works on demand S: survives the event I: depends on others

Bonding vs Earthing HA

Bonding

  • Links two conductors
  • Equalises potential between items
  • Stops sparks across gaps

Earthing

  • Links item to ground
  • Drains charge away
  • Needs low-resistance path
  • Between items vs ground

Barrier Picker HA

  • Prevent tank overfill → Independent high-level trip
  • Contain runaway pressure → Designed reactor containment
  • Remove reaction heat fast → Crash cooling
  • Relieve overpressure safely → Vent to knock-out drum
  • Stop flame travelling → Flame arrester
  • Remove the oxygen → Nitrogen blanketing
  • Limit spill spread → Bund ( 110% largest tank )
  • Protect steel from fire → Passive fire protection

Operating Limits HA

  • Safe operating envelope Upper and lower safe limits
  • Operating procedure Step-by-step written instruction
  • Verification Procedures kept current, accurate
  • Alarm response Alert, inform, guide operator
  • Pre-start-up review Confirm plant ready for service
  • Start-up types Planned, unplanned, emergency, staged
  • Shutdown Follow the written sequence
  • Shared services Check impact on neighbours

Flashpoint vs Auto-ignition HA

Flashpoint

  • Lowest vapour-producing temperature
  • Needs an ignition source
  • Classifies flammable liquids

Auto-ignition

  • Ignites with no spark
  • Hot surface temperature
  • Higher than flashpoint
  • Spark needed vs not

Safety-Critical Standards (FARSI) HA

  • Safety-critical element Failure could cause major accident
  • Functionality What it must do
  • Availability Proportion of time working
  • Reliability Performs when demanded
  • Survivability Works during the event
  • Interdependency Relies on other systems
  • Proof testing Shows the standard still met

Utilities + Static HA

  • Saturated steam At its boiling temperature
  • Superheated steam Heated above saturation temperature
  • Water hammer Condensate slug shocks pipework
  • Thermal expansion Trapped liquid overpressures pipe
  • Draining vacuum Collapses tanks and vessels
  • Cooling towers Legionella and vapour fog
  • Inert gas uses Purge, blanket, freeze pipelines
  • Nitrogen risk Asphyxiation without warning
  • Bonding Equalises charge between items
  • Earthing Drains charge to ground
  • Power outage Generators and UPS backup

Dangerous Substances HA

  • Flashpoint Vapour ignites momentarily, spark applied
  • LEL Below it, too lean
  • UEL Above it, too rich
  • Flammable range Between LEL and UEL
  • Explosive Explodes given oxygen, enough energy
  • Oxidising Readily accepts electrons
  • Physical form Gas, vapour, liquid, dust
  • Dense vapour Collects in pits and drains

Reaction Hazards HA

  • Exothermic Releases heat
  • Endothermic Absorbs heat
  • Thermal runaway Heat generated exceeds cooling
  • Typical causes Cooling loss, wrong charge, catalyst
  • Containment Reactor withstands maximum pressure
  • Crash cooling Rapid emergency heat removal
  • Quenching Drown or dilute contents
  • Emergency venting Dump to scrubber or flare

Bulk Storage HA

  • Overfilling Buncefield-type ground vapour cloud
  • Vacuum collapse Emptying without adequate venting
  • Brittle fracture Cold, sudden shell failure
  • Creep Slow deformation under stress
  • Floating roof Rim seal fire risk
  • Landing the roof Vapour space forms beneath
  • Bund capacity 110% of largest tank HSE
  • Siting Distance from people, plant
  • Lightning Protection and bonding needed
  • Warehousing Segregate incompatible dangerous goods

Triangle + Dust Pentagon FI

  • Fuel + oxygen + ignition (+ dispersion + confinement)
  • Triangle: first three Pentagon: dust needs five Remove one, no explosion

Venting vs Suppression FI

Explosion venting

  • Weak panel or disc
  • Relieves pressure outward
  • Directed to safe place

Suppression

  • Detects pressure rise
  • Injects extinguishant fast
  • Explosion stays inside
  • Release pressure vs stop it

Fire Scenario Picker FI

  • Pressurised leak ignites → Jet fire ( Impingement escalates )
  • Liquid pool ignites → Pool fire ( Radiant heat )
  • Open cloud ignites late → Flash fire ( Little overpressure )
  • Congested cloud ignites → UVCE ( Flame accelerates )
  • Cloud inside a building → CVCE ( Confinement )
  • Flame heats LPG vessel → BLEVE ( Fireball )
  • Dust cloud in duct → Primary explosion
  • Settled dust disturbed → Secondary explosion ( Housekeeping )

Fire + Explosion Types FI

  • Fire triangle Fuel, oxygen, ignition source
  • Heat transfer Conduction, convection, radiation
  • Jet fire Pressurised release, directional flame
  • Pool fire Spreading liquid, wide radiation
  • Flash fire Cloud burns, little overpressure
  • BLEVE Vessel bursts, fireball follows
  • UVCE Unconfined vapour cloud explosion
  • CVCE Confined vapour cloud explosion
  • Ignition sources Sparks, hot surfaces, static

DSEAR Zones FI

  • 0 continuous, 1 occasional, 2 rare
  • Zone 0: Category 1G Zone 1: Category 2G Zone 2: Category 3G Dusts: 20, 21, 22

Passive vs Active Fire Protection FI

Passive

  • No power or action
  • Coatings, walls, spacing
  • Buys escape time

Active

  • Needs detection or operation
  • Water, foam, sprinklers
  • Can fail on demand
  • Always there vs activated

Detection + Protection FI

  • Gas detection Finds leaks before ignition
  • Flame detection Optical sensing of fire
  • Line heat detection Temperature rise along cable
  • Passive protection Coatings, walls, no power
  • Active protection Water or foam, manual/automatic
  • Hazardous area zoning Selects ignition-protected equipment
  • Flame arrester Stops flame passing through
  • Explosion venting Weak panel relieves pressure
  • Suppression Injects extinguishant during explosion
  • Automatic isolation Closes to stop spread
  • Atmosphere control Inerting below oxygen limit
  • Tank farm foam Pourers and fixed monitors

Dust Explosions FI

  • Five conditions Fuel, oxygen, ignition, dispersion, confinement
  • Primary explosion Inside vessel or duct
  • Secondary explosion Settled dust lifted, ignites
  • Housekeeping Removes settled dust layers
  • Extraction Captures dust at source
  • Substitution Granules or paste instead
  • Nitrogen inerting Prevents explosive dust atmosphere
  • Relief venting Vents to a safe place
  • Strong construction Plant siting withstands pressure

Emergency Preparedness FI

  • On-site plan Operator's internal response
  • Off-site plan Local authority prepares it
  • Scenarios Chosen by likelihood, consequence
  • Alerting Warn workers, neighbours, services
  • Command roles Delegated responsibilities, named people
  • Accounting Muster and headcount system
  • Vulnerable people Planned for specifically
  • Emergency shutdown Plant and services stopped
  • Media liaison Controlled information release
  • Table-top test Theoretical scenario exercise
  • Live drill Practical evacuation rehearsal

Common Traps

Process vs personal safety

  • Personal safety: slips, falls ≠ Process safety: loss of containment

Prevent vs mitigate

  • Preventive barriers stop initiation ≠ Mitigative barriers limit consequences

HAZOP vs LOPA

  • HAZOP finds deviations ≠ LOPA counts protection layers

Indicators

  • Leading indicators check controls ≠ Lagging indicators count failures

Bonding vs earthing

  • Bonding equalises between items ≠ Earthing drains to ground

Flashpoint vs auto-ignition

  • Flashpoint needs a spark ≠ Auto-ignition needs no spark

Venting vs suppression

  • Venting releases pressure outward ≠ Suppression injects extinguishant inside

COMAH tiers

  • Lower tier: MAPP, notify ≠ Upper tier adds safety report

Jet vs pool fire

  • Jet fire: pressurised release ≠ Pool fire: spreading liquid

Flammable limits

  • Below LEL, too lean ≠ Above UEL, too rich

Last Minute

  • 1. PSM1 = 40 questions, 90 minutes
  • 2. Pass = 60%, 24 of 40
  • 3. Grades are Pass or Refer
  • 4. 10 questions are extended scenarios
  • 5. Process safety = loss of containment
  • 6. Leading checks controls; lagging counts failures
  • 7. HAZOP = deviations; LOPA = layers
  • 8. Bow-tie: left prevents, right mitigates
  • 9. FARSI grades safety-critical performance standards
  • 10. Flixborough = change; Piper Alpha = permits
  • 11. Buncefield = overfill; Texas City = start-up
  • 12. Bhopal = inventory; Seveso = EU law
  • 13. Bund holds 110% largest tank
  • 14. Zone 0 continuous; Zone 2 rare
  • 15. Upper tier adds safety report
  • 16. Emergency plans tested every 3 years
  • 17. Bonding equalises; earthing drains away
  • 18. Passive protection needs no power

NEBOSH HSE Certificate in Process Safety Management

  • Practice Questions 112 questions Study Guide 30 topics Cheat Sheet 217 facts Flashcards 50 cards Shorts 1 short Blogs 1 blog Free CE

Same family resources

  • Explore More NEBOSH Health and Safety Qualifications
  • Continue into nearby exams from the same family. Each card keeps practice questions, study guides, flashcards, videos, and articles in one place.

NEBOSH Certificate in Fire Safety

  • Practice Questions 100 questions Free CE

NEBOSH Environmental Management Certificate

  • Practice Questions 100 questions Free CE

NEBOSH Health and Safety Management for Construction

  • Practice Questions 100 questions Free CE

NEBOSH HSE Certificate in Managing Stress at Work (NEBOSH / HSE, UK)

  • Practice Questions 100 questions Free CE

NEBOSH HSE Introduction to Incident Investigation (NEBOSH / HSE, UK)

  • Practice Questions 100 questions Free CE

NEBOSH International Diploma in Environmental Management

  • Practice Questions 100 questions Free CE

More From This Family

  • Videos and articles for deeper review.
  • Article NEBOSH PSM Exam Guide 2026: Format, Topics and Free Practice 15 min read