Safety
- 15% of exam
- Approach Boundaries PPE and Glove Classes LOTO and ESWC Meter Safety Ratings Shock Boundary Picker
Electrical Testing Fundamentals and Theory
- 25% of exam
- Ohm's Law and Power Three-Phase Relationships ANSI Device Numbers Drawings and Curves
Component Testing
- 55% of exam
- IR Test Voltages PI, DAR and IEEE 43 Transformer Testing Cable Testing Breaker Testing Instrument Transformers Grounding and Batteries
Systems and Commissioning
- 5% of exam
- Commissioning and Records NFPA 110 Load Tests As-Found vs As-Left Restore and Report
Quick Facts
- Exam NETA ETT Level 2
- Credential Certified Assistant Technician
- Items 100 multiple-choice
- Time 2 hours
- Pass 410 scaled (200-500)
- Format Closed-book, onsite proctored
- Delivery Pearson VUE
- Scheduling Set testing periods; schedule early
- Practice exam $100, one hour, 60-day review
- Eligibility 2 years, NAC employed
- Training 40 safety, 160 electrical hours
- Supervision Under Level 3 or 4
Ground Lead Order SA
- Ground end first, remove it last
- Apply: ground then conductor Remove: conductor then ground Both ends: equipotential zone Verify absence first
Level 2 vs Level 3 SA
Level 2
- Limited testing work
- Direct supervision required
- 15/25/55/5 weights
Level 3
- Supervises Levels 1-2
- Performs power switching
- 13/23/47/17 weights
- Assist vs supervise
Shock Boundary Picker SA
- 208 V panel, fixed parts → 3 ft 6 in limited
- 480 V, qualified entry → 1 ft 0 in restricted
- 13.8 kV gear, fixed parts → 5 ft 0 in limited
- 13.8 kV qualified entry → 2 ft 2 in restricted
- 25 kV gear, fixed parts → 6 ft 0 in limited
- Overhead movable conductor → 10 ft 0 in limited
- Unqualified person present → Qualified escort required
- Need arc flash boundary → Calculate it ( Not a voltage table )
Approach Boundaries SA
- Limited approach Unqualified needs qualified escort
- Restricted approach Qualified plus shock PPE
- Arc flash boundary 1.2 cal/cm2 incident energy
- Prohibited boundary Deleted in 2015 edition NFPA 70E
- 50-150 V fixed 3 ft 6 in limited
- 151-750 V fixed 3 ft 6 in limited
- 151-750 V restricted 1 ft 0 in
- 751 V-15 kV fixed 5 ft 0 in limited
- 751 V-15 kV restricted 2 ft 2 in
- 15.1-36 kV restricted 2 ft 7 in
- Movable conductor 10 ft through 72.5 kV
- Boundary table NFPA 70E 130.4(E)(a)
PPE Cal Ladder SA
- Four, eight, twenty-five, forty
- Cat 1: 4 cal/cm2 Cat 2: 8 cal/cm2 Cat 3: 25 cal/cm2 Cat 4: 40 cal/cm2
Limited vs Restricted Boundary SA
Limited
- Outer shock boundary
- Unqualified needs escort
- Fixed by voltage
Restricted
- Inner shock boundary
- Qualified plus shock PPE
- Documented work plan
- Escort vs shock PPE
PPE and Glove Classes SA
- PPE Category 1 4 cal/cm2 minimum rating
- PPE Category 2 8 cal/cm2 minimum rating
- PPE Category 3 25 cal/cm2 minimum rating
- PPE Category 4 40 cal/cm2 minimum rating
- Category limits exceeded Incident energy analysis required
- Glove Class 00 500 V ac maximum ASTM D120
- Glove Class 0 1,000 V ac maximum
- Glove Class 2 17,000 V ac maximum
- Glove Class 4 36,000 V ac maximum
- Glove retest Every 6 months OSHA 1910.137
- Sleeve and blanket retest Every 12 months
- Leather protectors Mechanical shield, not insulation
LOTO and ESWC SA
- OSHA 1910.147 Machine servicing energy control
- OSHA 1910.333 Electrical safety-related work practices
- OSHA 1910.269 Utility generation, transmission, distribution
- NFPA 70E Article 120 Electrically safe work condition
- Visual verification See the open gap
- Stored energy release Springs and capacitors
- Live-dead-live Prove tester before and after
- Temporary protective grounds Applied after voltage verified
- Equipotential zone Ground both work-zone ends
- Energized work permit Justifies infeasible de-energization
Meter Safety Ratings SA
- CAT II Receptacle-connected single-phase loads IEC 61010
- CAT III Building distribution, three-phase equipment
- CAT IV Service entrance, outdoor conductors
- Higher category Higher transient withstand
- Voltage alone Never proves meter suitability
- Meter fuses High-interrupt rated only
- Non-contact tester Never proves absence
- Known live source Needed to prove tester
Ohm's Law and Power TH
- V = I x R Ohm's law
- P = V x I Real power, watts
- P = I^2 x R Heating in loose joints
- P = V^2 / R Resistive load power
- Series circuit Resistances add, current equal
- Parallel circuit Below smallest branch resistance
- 1 ohm 1,000,000 microhms
- 1 megohm 1,000,000 ohms
- Contact resistance units Microhms
- Winding resistance units Milliohms
- Insulation resistance units Megohms or gigohms
Three-Phase Relationships TH
- Wye line voltage sqrt(3) x phase voltage
- Wye line current Equals phase current
- Delta line voltage Equals phase voltage
- Delta line current sqrt(3) x phase current
- 480 V wye 277 V to neutral
- Apparent power S sqrt(3) x VLL x IL
- Real power P S x power factor
- Power factor Watts over volt-amperes
- Voltage unbalance Max deviation over average
- Delta ground reference Needs grounding transformer
ANSI Device Numbers TH
- 27 Undervoltage IEEE C37.2
- 46 Negative sequence, phase balance
- 49 Thermal overload
- 50 Instantaneous overcurrent
- 51 Time overcurrent
- 52 AC circuit breaker
- 59 Overvoltage
- 67 Directional overcurrent
- 86 Lockout auxiliary relay
- 87 Differential
- Suffix N or G Ground element
- Suffix V Voltage-restrained element
Drawings and Curves TH
- One-line Power path, sources, ratings
- Three-line Each phase and secondary
- DC schematic Trip and close logic
- Connection diagram Terminal-by-terminal wiring
- TCC curve Operating time versus current
- Pickup Minimum operating current
- Time dial Shifts the 51 curve
- Coordination Downstream device clears first
- Short-circuit study Available fault current source
Level 2 Domain Weights CO
- Safety 15, Theory 25, Parts 55, Systems 5
- Safety: 15% Theory: 25% Component: 55% Systems: 5%
ATS vs MTS CO
ANSI/NETA ATS
- Before initial energization
- New installations
- Acceptance criteria
ANSI/NETA MTS
- In-service equipment
- Maintenance intervals
- Trend against baseline
- New install vs upkeep
IR Test Voltage Picker CO
- Manufacturer data exists → Manufacturer value ( Tables are fallback )
- 600 V switchgear bus → 1,000 V dc ( 100 Mohm )
- 5 kV class apparatus → 2,500 V dc ( 1,500 Mohm )
- 15 kV class apparatus → 2,500 V dc ( 5,000 Mohm )
- 480 V dry transformer → 1,000 V dc ( 500 Mohm )
- 4,160 V liquid transformer → 2,500 V dc ( 1,000 Mohm )
- 480 V motor stator → 500 V dc ( Table 100.11 )
- 13.8 kV stator winding → 5,000-10,000 V dc ( Table 100.11 )
- Reading below minimum → Investigate ( Do not hipot )
IR Test Voltages CO
- 250 V class 500 V dc 25 Mohm
- 600 V class 1,000 V dc 100 Mohm
- 5,000 V class 2,500 V dc 1,500 Mohm
- 15,000 V class 2,500 V dc 5,000 Mohm
- Table 100.1 role Used absent manufacturer data
- Select voltage by Equipment rating, not supply
- Below the minimum Investigate before energizing
- Guard terminal Diverts surface leakage current
- Temperature rule Halves per 10 C rise
CT Open, PT Short CO
- CT open kills; PT short kills
- CT: short the secondary PT: fuse the secondary PT: never back-feed Both mistakes are lethal
Insulation Resistance vs Hipot CO
Insulation resistance
- Lower dc voltage
- Nondestructive
- Megohm reading
Hipot
- High applied stress
- Pass or fail
- Can break insulation
- Measure vs stress
Which Test For What CO
- Suspect wet stator → Polarization index ( 10 over 1 )
- Ten minutes unavailable → DAR ( 60 over 30 )
- Bolted joint suspect → Micro-ohmmeter ( Four-wire Kelvin )
- Tap changer suspect → TTR on all taps ( 0.5 percent )
- Shorted transformer turns → Excitation current test
- Service-aged MV cable → VLF withstand ( Not dc hipot )
- Rank cable replacement → Tan delta ( Diagnostic )
- Lost vacuum suspected → Vacuum bottle integrity ( Megger cannot see )
- CT accuracy in doubt → Saturation test ( Knee point )
- Breaker did not trip → Primary injection ( Whole loop )
- Isolated ground rod → Fall-of-potential ( Disconnect electrode )
- Multi-grounded system → Clamp-on tester ( Parallel path needed )
- Surface contamination suspected → Guarded IR reading
PI, DAR and IEEE 43 CO
- PI 10-minute over 1-minute
- DAR 60-second over 30-second
- PI minimum 2.0 for Class B IEEE 43
- PI near 1.0 Moisture or contamination
- PI not required IR above 5,000 Mohm
- Ratios need no correction Same temperature both readings
- Form-wound after 1970 100 Mohm minimum
- Older and field windings kV + 1 Mohm
- Random-wound stators 5 Mohm minimum
- IEEE 43 base Corrects to 40 C
- NETA conversion base Corrects to 20 C
- Step-voltage test Disproportionate drop reveals aging
PI and DAR Times CO
- PI ten over one; DAR sixty over thirty
- PI: 10 min / 1 min DAR: 60 s / 30 s Minimum PI: 2.0 No temperature correction
DLRO vs Megohmmeter CO
DLRO
- Microhm range
- Four-wire Kelvin
- Conducting path
Megohmmeter
- Megohm range
- High dc voltage
- Insulating path
- Through vs across
Transformer Testing CO
- TTR tolerance Within 0.5 percent ANSI/NETA
- Test every tap Defects hide on unused
- Turns ratio a V1/V2 = I2/I1
- Impedance transforms By the ratio squared
- Subtractive polarity Reads less than applied
- Additive polarity Reads more than applied
- Additive permitted 200 kVA and below
- Excitation current pattern Center leg reads lower
- Liquid-filled, 0-600 V 1,000 V dc, 100 Mohm Table 100.5
- Dry-type, 0-600 V 1,000 V dc, 500 Mohm
- Liquid-filled, 601-5,000 V 2,500 V dc, 1,000 Mohm
- Winding resistance Finds loose or open
PI vs DAR CO
PI
- 10 min / 1 min
- IEEE 43 minimum 2.0
- Full charging curve
DAR
- 60 s / 30 s
- Quick screening ratio
- No IEEE minimum
- Long vs short ratio
Cable Testing CO
- VLF frequency About 0.1 Hz
- Why VLF works Charging current drops sharply
- DC hipot on XLPE Injects trapped space charge
- DC still acceptable on PILC laminated dielectrics
- Tan delta Loss over charging current
- Tip-up Loss rises with voltage
- Withstand test Go or no-go
- Diagnostic test Grades and trends condition
- Shield continuity Over 10 ohms per 1,000 ft
- Post-hipot grounding Drain trapped charge first
Bonding vs Grounding CO
Bonding
- Joins metal parts
- Carries fault current
- Operates the breaker
Grounding
- Reference to earth
- Lightning and static
- Poor fault path
- Clears faults vs references
Breaker Testing CO
- MCCB Sealed, fixed instantaneous trip
- ICCB Drawout, short-time capability
- LVPCB Maintainable, short-time withstand rating
- Thermal-magnetic trip Fixed curve, ambient sensitive
- Electronic trip Adjustable LSIG functions
- LSIG Long, short, instantaneous, ground
- Contact resistance current 100 A dc minimum IEEE C37.09
- Pole deviation limit 50 percent above lowest
- Primary injection Proves the whole loop
- Secondary injection Proves trip unit only
- Vacuum bottle integrity Overpotential across open gap
- Vacuum test hazard X-rays at high voltage
Primary vs Secondary Injection CO
Primary
- Whole current loop
- Finds bad CTs
- Commissioning test
Secondary
- Trip unit only
- Proves settings
- Misses sensors
- Loop vs logic
Instrument Transformers CO
- Open CT secondary Lethal voltage, core saturates
- Before lifting CT lead Install the shorting screw
- Short PT secondary Damaging fault current
- Back-feed a PT Full primary on terminals
- 600:5 CT 120:1 ratio
- Polarity marks H1 in, X1 out
- Reversed CT polarity Differential trips on load
- C400 class 400 V at 100 A IEEE C57.13
- C-class error limit 10 percent ratio error
- Saturation test Finds the knee point
- Burden Total secondary circuit load
Withstand vs Diagnostic CO
Withstand
- Go or no-go
- VLF or hipot
- May fault it
Diagnostic
- Condition number
- Tan delta, partial discharge
- Trendable
- Can energize vs remaining life
Grounding and Batteries CO
- Bonding Low-impedance fault return path
- Grounding Voltage reference to earth
- Earth as fault path Poor, will not clear
- Grounded conductor Neutral, carries load current
- Equipment grounding conductor Carries fault current only
- Fall-of-potential Three-point, 62 percent rule
- Clamp-on ground test Needs parallel return path
- Flooded cell Specific gravity, temperature corrected
- VRLA cell No hydrometer, ohmic trending
- IEEE 450 Vented lead-acid maintenance
- IEEE 1188 VRLA battery maintenance
- Capacity proof Discharge test only
CT vs PT Secondary CO
CT secondary
- Never open it
- Short before lifting
- Behaves as current source
PT secondary
- Never short it
- Never back-feed it
- Fused, voltage source
- Open kills vs short kills
Test Order Rule SY
- Components first, system function last
- As-found before adjusting As-left after work Function proves interaction
Restore and Report SY
- All component tests pass → System function test
- Relay element picks up → Verify breaker trips
- Before any adjustment → Record as-found
- After the work → Record as-left
- Grounds still applied → Remove conductor end first
- Ready to energize → Confirm settings match study
Commissioning and Records SY
- System function test After all component tests
- As-found data Recorded before any adjustment
- As-left data Baseline for next interval
- ATS functional test Simulate normal source loss
- NFPA 110 monthly 30 minutes under load
- Monthly load target 30 percent nameplate kW
- Annual supplemental test 50 percent then 75 percent
- Level 1 triennial 4 hours or class duration
- GFP performance test Required when first installed NEC 230.95
- Troubleshooting Find cause, not symptom
Common Traps
Boundary vs arc flash
- Shock boundaries from table ≠ Arc flash is calculated
Category vs severity
- Category is PPE rating ≠ Not a hazard score
De-energized vs safe
- De-energized only means opened ≠ Safe adds test and ground
Wrong OSHA rule
- 1910.147 covers machines ≠ 1910.333 covers electrical work
Prefix mistakes
- Contact resistance in microhms ≠ Insulation in megohms
Wrong correction base
- IEEE 43 uses 40 C ≠ NETA table uses 20 C
Resistance vs withstand
- Megohmmeter measures resistance ≠ Hipot applies dielectric stress
Wrong injection test
- Secondary proves trip unit ≠ Primary proves whole loop
Only one tap tested
- TTR needs every tap ≠ Unused taps hide defects
Vacuum vs insulation test
- Megger misses lost vacuum ≠ Overpotential across open gap
Neutral vs ground
- Neutral carries load current ≠ EGC carries fault current
Last Minute
- 1. Pass is 410 scaled, 200-500
- 2. 100 items, 2 hours, closed-book
- 3. Component Testing is 55 percent
- 4. Safety 15, Theory 25, Systems 5
- 5. 600 V class: 1,000 V dc
- 6. 5 kV class: 2,500 V dc
- 7. PI = 10 min / 1 min
- 8. DAR = 60 s / 30 s
- 9. Minimum PI is 2.0
- 10. TTR within 0.5 percent, every tap
- 11. Contact resistance at 100 A
- 12. Never open a CT secondary
- 13. Never back-feed a PT
- 14. Ground end first, conductor last
- 15. Arc flash boundary: 1.2 cal/cm2
- 16. PPE cal: 4, 8, 25, 40
- 17. Restricted at 480 V: 1 foot
- 18. Record as-found before adjusting
- 19. Function test after component tests
- 20. Practice exam: $100, one hour
NETA ETT Level II Certified Assistant
- Practice Questions 126 questions Study Guide 62 topics Cheat Sheet 172 facts Flashcards 50 cards Shorts 1 short Blogs 1 blog Free CE Podcast
Same family resources
- Explore More NETA ETT Certifications
- Continue into nearby exams from the same family. Each card keeps practice questions, study guides, flashcards, videos, and articles in one place.
NETA ETT Level I Trainee
- Practice Questions 100 questions Shorts 1 short Blogs 1 blog Free CE
NETA ETT Level III Senior Technician
- Practice Questions 100 questions Blogs 1 blog Free CE
NETA ETT Level IV Senior Technician
- Practice Questions 100 questions Free CE
More From This Family
- Videos and articles for deeper review.
- Article NETA Level 2 Exam Guide 2026: Eligibility, Format, Fees, and a Free Practice Plan 11 min read