Safety

  • 5-15% of exam
  • PPE Hazardous energy Ladders and tools Impairment hazards

Communication with AHJs and Customers

  • 5-15% of exam
  • Test coordination Notifications Reports Restoration confirmation

Intermediate ITM Tasks

  • 30-40% of exam
  • Dry and wet systems Standpipes Deficiency classification Device-specific testing

ITM for Water Supplies

  • 25-35% of exam
  • Fire pumps Private mains Hydrants Water tanks

Internal Obstruction Investigation

  • 10-20% of exam
  • Triggers Internal assessment Investigation locations Evidence and remediation

Quick Facts

  • Questions 168 questions
  • Time limit 185 minutes
  • Passing score 500 scaled; not percentage
  • Score scale 0–700
  • Testing provider Pearson VUE test centers
  • Core standard NFPA 25 (2023)
  • Renewal cycle Three-year CPD cycle
  • Permitted references 20 / 25 / 72 / 291

Safety and Working Practices SA

  • PPE selection Match hazards, task, and employer assessment Assess
  • Hazardous energy Isolate; lock/tag; release; verify controls LOTO
  • Electrical exposure Qualified personnel and applicable electrical procedure Qualified
  • Confined-space entry Evaluate permit status before entry Classify
  • Atmosphere test sequence Oxygen, flammables, then toxic contaminants Sequence
  • Hazardous oxygen concentration Below 19.5% or above 23.5% Oxygen
  • Leaning ladder foot position Quarter of ladder working length 1:4
  • Landing ladder extension Three feet; secured-grasp alternative applies Access

Extended Impairment Options CO

  • Evacuate, Watch, Water, Control
  • Evacuate affected area Approved fire watch Temporary water supply Eliminate ignition sources Limit fuel load

Communication and Impairment Control CO

  • Impairment coordinator Owner designee; otherwise owner Owner
  • Planned impairment Authorize scope and coordinate before shutdown Before
  • Emergency impairment Notify and protect without delay Now
  • More than 10 hours/24 hours Arrange an approved mitigation option Threshold
  • Four extended-impairment options Evacuation, watch, water, ignition/fuel controls Options
  • Restoration verification Valves, pressures, controllers, alarms, required tests Verify
  • Tag colors Jurisdiction/program specific; no universal palette Local
  • Baseline system records Retain for system life Lifetime
  • Recurring ITM records One year after next same-type event Retention

Separate Sprinkler Sampling Groups IN

  • 50 / 25 / 20 / 20
  • Many standard: 50 Other fast: 25 ESFR/CMSA fast: 20 Dry: 20 Sample: greater of four/1%

Critical Deficiency vs Impairment IN

Critical deficiency

  • Material effect on system performance
  • Correct promptly; document actual condition

Impairment

  • System/function out of order
  • Coordinator manages notifications and mitigation
  • Evaluate actual effect on protection

Classify Findings by Actual Consequence IN

  • Required protection cannot operate → Initiate impairment procedure ( Notify owner and required parties promptly )
  • Function materially affected, still operating → Evaluate critical deficiency ( Use actual condition and applicable guidance )
  • No material effect on performance → Evaluate noncritical deficiency ( Document and arrange correction )
  • Sprinkler damaged or field painted → Apply sprinkler replacement requirements ( Assess affected protection; avoid automatic classification )
  • Pump cannot meet system demand → Treat as impairment ( Coordinate approved mitigation with responsible parties )
  • Curve degraded, demand still met → Apply pump deficiency classification ( Document, investigate, and report results )

Control Valves and Gauges IN

  • Sealed control valves Inspect weekly Weekly
  • Locked control valves Inspect monthly Monthly
  • Electrically supervised control valves Inspect quarterly Quarterly
  • Valve operation Exercise annually; verify position Annual
  • Gauge condition Check damage and operation monthly Monthly
  • Water-pressure reading Verify normal pressure quarterly Quarterly
  • Air/nitrogen-pressure reading Monthly; quarterly with qualifying supervision Conditional
  • System gauge accuracy Five years; 3% full-scale tolerance 5 years
  • FDC inspection Quarterly; accessibility, condition, obstruction Quarterly

Two Air-Leakage Test Methods IN

  • 40–2–3 or Normal–4–No Alarm
  • 40 psi test pressure Two-hour test Maximum three psi loss Or normal pressure four hours No low-air alarm

Partial Trip vs Full-Flow Trip IN

Partial-flow trip

  • Annual dry-valve trip option
  • Does not establish full-flow delivery

Full-flow trip

  • At least every three years
  • Evaluate water delivery and operation
  • Valve operation differs from delivery

Select Dry-System Test Objective IN

  • Annual dry-valve trip due → Verify valve operation ( Partial-flow allowed between required full-flow tests )
  • Three-year full-flow test due → Evaluate full-flow water delivery ( Use manufacturer instructions; approved impairment plan )
  • Quick-opening device test due → Perform quarterly operational test ( Separate from annual valve trip )
  • Three-year air-leakage test due → Select one permitted method ( Do not combine their acceptance criteria )
  • Preaction system identified → Determine actual interlock logic ( Single, double, and noninterlock differ )
  • Test complete → Verify system restoration ( Confirm pressures, valves, alarms, receiving status )

Sprinkler Laboratory Sampling IN

  • Many standard-response sprinklers Initial 50 years; then 10 50 / 10
  • Fast-response ESFR or CMSA Initial 20 years; then 10 20 / 10
  • Other fast-response sprinklers Initial 25 years; then 10 25 / 10
  • Dry sprinklers, either response Initial 20 years; then 10 20 / 10
  • Sprinklers installed 75 years Test/retest every five years 5 years
  • Harsh-service sprinklers Initial five years; assess conditions 5 years
  • Representative sample Greater of four or one percent Minimum
  • Removed laboratory samples Immediately replace with new sprinklers Replace

Sprinkler Sampling Age Is Type-Specific IN

Other fast-response

  • Initial twenty-five-year laboratory test
  • Normal retest every ten years

Fast-response ESFR/CMSA

  • Initial twenty-year laboratory test
  • Normal retest every ten years
  • Dry and harsh-service rules differ

Dry and Preaction Systems IN

  • Dry-valve exterior Inspect monthly Monthly
  • Dry-valve interior Inspect annually Annual
  • Quick-opening device operational test Test quarterly Quarterly
  • Dry-valve trip Annual; partial permitted between full-flow Annual
  • Dry full-flow trip At least every three years 3 years
  • Air-leakage pressure method 40 psi; 2h; ≤3 psi loss 3 years
  • Air-leakage normal-pressure alternative Four hours; low-air alarm remains inactive 3 years
  • Compressor/nitrogen generator maintenance Follow manufacturer; oil annually unless sooner Manufacturer

Preaction vs Deluge System IN

Preaction

  • Closed automatic sprinklers
  • Interlock type determines valve release

Deluge

  • Open sprinklers or nozzles
  • Valve release permits designed discharge
  • Identify the actual release logic

Alarms and Waterflow Tests IN

  • Mechanical waterflow alarm Test quarterly Quarterly
  • Vane/pressure waterflow switch Test semiannually Semiannual
  • Valve supervisory switch Test semiannually Semiannual
  • Dry-pipe low-air alarm Test annually Annual
  • Main drain usual interval Annual; quarterly for specified sole supplies Conditional
  • Main drain residual reduction 10%: identify cause; correct if necessary Investigate
  • Antifreeze solution Annual; before freezing weather Annual
  • Legacy antifreeze retained under 2023 ≤30% PG; ≤38% glycerine; no refill Conditional
  • Automatic air vent exterior Annual floor-level inspection; damage and leakage Annual
  • Air vent strainers/filters/screens Five-year inspection; flush clear or replace 5 years

Usual Annual Pump Flow Points WA

  • Zero, One, One-and-a-Half
  • Churn: zero flow Rated: 100% flow Peak: 150% flow Check supply limitations Compare permitted baseline

Electric vs Diesel No-Flow Test WA

Most electric pumps

  • Monthly no-flow test
  • At least ten minutes

Diesel pumps

  • Normally weekly no-flow test
  • At least thirty minutes
  • Check electric weekly exceptions and allowances

Fire Pump Test Parameters WA

  • Diesel no-flow test Weekly; at least 30 minutes Weekly
  • Most electric no-flow tests Monthly; at least 10 minutes Monthly
  • Electric weekly exceptions Check controller, turbine, suction, building conditions Conditional
  • Redundancy/risk-analysis allowances Verify actual applicable allowance Conditional
  • Usual annual flow points Churn, rated flow, 150% flow Annual
  • Annual curve comparison ≥95% baseline net pressure each point 95%
  • Other annual acceptance requirements System demand, rated flow, suction requirements Also
  • Net pressure simplified Discharge minus suction; corrections when applicable Pressure
  • NFPA 20 design envelope Not annual NFPA 25 acceptance substitute Scope

Mains, Hydrants, Tanks, Standpipes WA

  • Private fire-main flow test Every five years; compare supply performance 5 years
  • Hydrant operation and flushing Annual; ≥1 minute until debris clears Annual
  • Dry-barrel hydrant drainage Check drainage within 60 minutes Drainage
  • Tank exterior and supports Inspect quarterly Quarterly
  • Unprotected steel tank interior Inspect every three years 3 years
  • Other tank interiors Usual interval: five years 5 years
  • Tank water-level inspection Quarterly supervised; otherwise monthly Conditional
  • Class I/III standpipe flow test Five years; installed design demand 5 years
  • Standpipe test acceptance Required pressure at remote outlet(s) Design

Internal Assessment vs Obstruction Investigation OB

Routine assessment

  • Usual five-year condition review
  • Approved alternative methods may apply

Triggered investigation

  • Specific Chapter 14 condition exists
  • Five minimum examination locations in 2023
  • A condition finding can escalate scope

Assess Obstruction Evidence OB

  • Five-year assessment due → Assess internal piping condition ( Approved risk analysis can change frequency )
  • Main drain pressure falls 10% → Investigate reduction cause ( Valve/supply changes also explain reductions )
  • Chapter 14 trigger established → Conduct obstruction investigation ( Use five 2023 minimum examination locations )
  • Slime or tubercules found → Test for MIC indications ( Appearance alone cannot establish corrosion mechanism )
  • Obstructing material confirmed → Plan qualified complete flushing ( Manage impairment and verify corrective results )
  • Findings and limitations known → Document system-specific evidence ( Report locations, methods, results, and recommendations )

Obstruction Assessment and Investigation OB

  • Routine internal condition assessment Normally five years; approved risk alternative 5 years
  • Potentially obstructing foreign material Escalate to obstruction investigation Trigger
  • Corrosion-related internal leakage Check Chapter 14 investigation trigger Trigger
  • Dry-system delivery deterioration Apply occupancy-specific threshold and baseline Trigger
  • 2023 investigation locations Five specified locations; not old four Five
  • Investigation location 1 System/water control valve where provided 2023 minimum
  • Investigation location 2 Remote end of remotest cross-main 2023 minimum
  • Investigation location 3 Near-remote branch at cross-main connection Near most-remote branch line
  • Investigation location 4 End of that near-remote branch Same branch as location3
  • Investigation location 5 Branch attached to remotest low-point drain Directly connected piping
  • Slime or tubercules Test for MIC indications Evaluate
  • Obstructing material confirmed Qualified complete flushing program Remedy

Common Traps

Main Drain Is a Comparison

  • 10% residual reduction requires investigation ≠ It does not prove full-demand capacity

Air-Leakage Alternatives Differ

  • 40 psi / 2 h / ≤3 psi ≠ Normal pressure; 4h; no low-air alarm

Electric Monthly Has Exceptions

  • Weekly cases exist despite electric driver ≠ Check suction, turbine, controller, building conditions

Fast-Response Age Changed in 2023

  • Other fast-response starts at 25 years ≠ ESFR/CMSA fast-response: initial 20 years

Investigation Locations Changed

  • 2023 has five specified examination locations ≠ Older four-point lists are edition-specific

Impairment Timing and Choices

  • Notifications do not wait ten hours ≠ Fire watch is one approved option

Last Minute

  • 1. Level II: 168 questions, 185 minutes.
  • 2. Passing: 500 scaled; scale 0–700.
  • 3. Books: NFPA20–2022; NFPA25–2023; NFPA72–2022; NFPA291–2022.
  • 4. Main drain: investigate 10% residual reduction.
  • 5. QOD quarterly; dry trip annually.
  • 6. Dry full-flow trip: three years.
  • 7. Air leak: 40psi, 2h, ≤3psi loss.
  • 8. Alternative: normal pressure, 4h, no low-air-alarm.
  • 9. Other fast-response: 25-year initial sample.
  • 10. Dry sprinklers: 20-year initial sample.
  • 11. Sample: greater of four or 1%.
  • 12. Diesel: weekly, minimum 30 minutes.
  • 13. Most electric: monthly, minimum 10 minutes.
  • 14. Annual pump: ≥95% baseline; additional criteria.
  • 15. 2023 investigation: five specified examination locations.
  • 16. Impairment: notify promptly; approved mitigation.
  • 17. Restoration: verify valves, pressures, controllers, signals.

NICET Inspection and Testing of Water-Based Systems Level II

  • Practice Questions 111 questions Study Guide 50 topics Cheat Sheet 82 facts Flashcards 50 cards Games 40 terms Shorts 2 short s Blogs 1 blog Podcast
  • Word games 40 terms Guess the Term T E R M S Read the clue and guess the term in 6 tries. Word games 40 terms Term Match Swap tiles to line up three of the same term. Word games 40 terms Term Pairs ? ✓ ✓ ? ? Flip two cards at a time to find matching terms. Word games 40 terms Term Search Q T E R M X Find five hidden terms in a grid of letters.