Cheat sheet

OSHA 510 Cheat Sheet

Practice this exam

OSH Act and OSHA Policy

  • 12% of exam
  • General Duty Clause Multi-Employer Policy Competent vs Qualified Person Penalty Structure Hierarchy of Controls

Falls (Subpart M)

  • 18% of exam
  • Fall Protection Triggers Guardrail Specifications PFAS Requirements Safety Nets and CAZ Ladder Safety Rules

Electrical (Subpart K)

  • 10% of exam
  • Overhead Line Clearance GFCI Protection Lockout Tagout Rules Qualified Electrical Worker

Struck-By and Caught-In

  • 10% of exam
  • Struck-By Vehicles Rigging Inspection Nail Gun Safety Caught-In Hazards Formwork and Steel Erection

Health Hazards (Subpart D)

  • 15% of exam
  • Silica PEL and Controls Lead Exposure Limits Asbestos Classification Noise and Hearing HazCom and Heat Illness

Excavations (Subpart P)

  • 10% of exam
  • Cave-In Protection Trigger Soil Classification Sloping and Shoring Excavation Inspection

Scaffolds (Subpart L)

  • 10% of exam
  • Scaffold Load Factor Scaffold Inspection Fall Protection at 10ft Height to Base Ratio

Recordkeeping (1904)

  • 10% of exam
  • Fatality and Injury Reporting OSHA 300 Log Recordable Criteria Inspection Priority Order

Cranes, PPE and Fire

  • 15% of exam
  • Crane Operator Certification Crane Power Line Clearance PPE Cost Rules Hot Work and Fire Watch

Quick Facts

  • Course OSHA #510
  • Focus 29 CFR 1926
  • Duration 4 days, 32 hours
  • Attendance 100% required
  • Grading Pass/fail exam
  • Prerequisite For OSHA #500 Trainer
  • Fall Trigger 6 feet
  • Silica PEL 50 μg/m³

Hierarchy of Controls OS

  • Eliminate, substitute, engineer, administer, then PPE last
  • Elimination Substitution Engineering Administrative PPE

Competent vs Qualified Person OS

Competent Person

  • Identifies hazards daily
  • Corrects them promptly

Qualified Person

  • Holds technical credentials
  • Designs engineered solutions
  • Different roles, same site safety

OSH Act Foundations OS

  • OSH Act 1970 Safe workplace authority
  • General Duty Clause Recognized hazard rule
  • 29 CFR 1926 Construction standards
  • 29 CFR 1910 General industry standards
  • 29 CFR 1904 Recordkeeping standards
  • Hierarchy of Controls Elimination to PPE order

Serious vs Willful Violation OS

Serious

  • Up to $16,550
  • No intent required

Willful

  • Up to $165,514
  • Intentional disregard shown
  • Intent raises the penalty cap

Multi-Employer and Penalties OS

  • Creating Employer Caused the hazard
  • Exposing Employer Workers are exposed
  • Correcting Employer Responsible for fixing
  • Controlling Employer Site-wide safety authority
  • Competent Person Inspects and corrects hazards
  • Qualified Person Designs technical solutions
  • Willful/Repeated Cap $165,514 per violation
  • Failure to Abate $16,550 per day

Focus Four FA

  • Falls, struck-by, caught-in, electrocution
  • Falls Struck-By Caught-In Electrocution

6ft vs 10ft Trigger FA

General Construction

  • 6-foot fall trigger
  • Subpart M rule

Scaffolds

  • 10-foot fall trigger
  • Subpart L rule
  • Scaffolds get a higher trigger

Fall Protection Picker FA

  • General construction 6ft+ → Guardrail net or PFAS ( Pick per site conditions )
  • Scaffold work 10ft+ → Guardrail or PFAS
  • Steel erection connector → 15-foot trigger applies
  • Leading edge work → Controlled access zone
  • Low-slope roof work → Warning line plus monitor ( Not standalone protection )
  • Portable ladder setup → 4:1 pitch ratio
  • Vertical rise 19in+ → Stairway or ladder required

Fall Protection Triggers FA

  • General Fall Trigger 6 feet to lower level
  • Scaffold Fall Trigger 10 feet Subpart L
  • Steel Erection Trigger 15 feet for connectors
  • Guardrail Top Rail 42 inches ±3 inches
  • Guardrail Mid-Rail About 21 inches high
  • Toeboard Minimum 3.5 inches high
  • Guardrail Strength Withstand 200 lbs force
  • Ramp Guardrail Trigger 6 feet or more

Fall Protection Systems FA

  • PFAS Free Fall Limit Maximum 6 feet
  • PFAS Arresting Force Maximum 1,800 lbs
  • PFAS Anchor Point Minimum 5,000 lbs
  • Safety Net Distance Within 30 feet
  • Safety Net Extension 8 to 13 feet
  • Net Drop Test Every 6 months
  • CAZ Control Line 6 to 25 feet back
  • Ladder Pitch Ratio 4:1 base to height
  • Stairway Trigger 19 inches vertical rise

Electrical Hazards EL

  • Overhead Line Clearance 10 feet up to 50kV
  • Line Clearance Above 50kV +4 inches per 10kV
  • Crane Line Clearance 20 feet up to 350kV
  • Crane Clearance Above 350kV 50 feet minimum
  • GFCI Trip Current 5 milliamps or more
  • GFCI Trip Time About 1/40 second
  • Grounding Threshold 50 volts or more
  • LOTO Standard 29 CFR 1926.417
  • Qualified Electrical Worker Task-specific hazard training

Struck-By and Caught-In ST

  • Leading Struck-By Cause Vehicles and mobile equipment
  • Reverse Alarm Rule Audible alarm or spotter
  • Rigging Inspection Before each use or shift
  • Nail Gun Trigger Sequential mode required
  • Machine Guarding Standard 29 CFR 1926.300
  • Caught-In Definition Crushed between two objects
  • Formwork Inspection Before each concrete pour
  • Steel Erection Plan Written site-specific plan

PEL Quick Recall HE

  • Silica and lead fifty, asbestos tenth, noise ninety
  • Silica 50 Lead 50 Asbestos 0.1 Noise 90

Silica vs Lead PEL HE

Silica

  • PEL 50 μg/m³
  • Action level 25

Lead

  • PEL 50 μg/m³
  • Action level 30
  • Same PEL, different action levels

Health Hazard PELs HE

  • Silica PEL 50 μg/m³ TWA
  • Silica Action Level 25 μg/m³
  • Lead PEL 50 μg/m³ TWA
  • Lead Action Level 30 μg/m³
  • Lead Removal BLL 50 μg/dL
  • Lead Return BLL Below 40 μg/dL twice
  • Asbestos PEL 0.1 f/cc TWA
  • Asbestos Excursion Limit 1.0 f/cc, 30 min
  • Noise PEL 90 dBA TWA

Health Hazard Controls HE

  • Noise Action Level 85 dBA TWA
  • Silica Engineering Controls Wet methods or LEV
  • HazCom Standard 29 CFR 1926.59
  • SDS Requirement Accessible for every chemical
  • Heat Illness Framework Water rest shade acclimatization
  • Demolition Survey Competent person before start
  • Utility Shutoff Required before demolition begins
  • Asbestos Class I Highest-risk removal work

Soil Types Flatten EX

  • A holds steepest, B middle, C flattest
  • Type A Type B Type C Stable Rock

Type A vs Type C Soil EX

Type A

  • Most stable soil
  • 0.75:1 slope

Type C

  • Least stable soil
  • 1.5:1 slope
  • Less stable needs flatter slope

Excavation Protection Picker EX

  • Depth 5 feet+ → Protective system required
  • Depth 4 feet+ → Safe egress within 25ft
  • Soil tests Type A → 0.75:1 slope allowed
  • Soil tests Type B → 1:1 slope allowed
  • Soil tests Type C → 1.5:1 slope allowed
  • Entirely stable rock → No sloping required
  • Benching method chosen → Only Type A or B
  • Materials near edge → Keep spoil 2ft back

Excavation Basics EX

  • Cave-In Protection Trigger 5 feet or deeper
  • Egress Trigger 4 feet or deeper
  • Egress Distance Within 25 feet lateral
  • Type A Soil 0.75:1 slope, 53°
  • Type B Soil 1:1 slope, 45°
  • Type C Soil 1.5:1 slope, 34°
  • Stable Rock No sloping needed
  • Spoil Pile Setback At least 2 feet
  • Excavation Inspection Daily and after rain

Scaffold Basics SC

  • Scaffold Safety Factor 4 times max load
  • Suspension Rope Factor 6 times max load
  • Scaffold Fall Trigger 10 feet height
  • Scaffold Inspection Competent person each shift
  • Freestanding Tie Ratio 4:1 height to base
  • Mobile Scaffold Ratio 3:1 height to base
  • Plank Support Spacing 8 feet on center
  • Plank Overhang 6 to 12 inches

Recordable vs Reportable RE

Recordable

  • Goes on OSHA 300
  • Meets 1904.7 criteria

Reportable

  • Called into OSHA fast
  • Fatality or hospitalization
  • Reportable events are always urgent

Reporting and Penalty Picker RE

  • Worker fatality occurs → Report to OSHA in 8h
  • Hospitalization amputation or eye loss → Report to OSHA in 24h
  • Violation is serious → Up to $16,550
  • Violation is willful or repeated → Up to $165,514
  • Abatement date missed → $16,550 per day
  • Employer has 11+ workers → Keep OSHA 300 log
  • Imminent danger found → Top inspection priority

Recordkeeping Essentials RE

  • Fatality Report Window 8 hours
  • Hospitalization Report Window 24 hours
  • OSHA 300 Log Injury and illness log
  • OSHA 300A Posting February 1 to April 30
  • Recordable Threshold 11 or more employees
  • Recordable Criteria Beyond first aid treatment
  • Top Inspection Priority Imminent danger conditions
  • Crane Record Retention At least 12 months

PASS Extinguisher Use CR

  • Pull, aim, squeeze, sweep the fire
  • Pull Aim Squeeze Sweep

Cranes, PPE and Fire CR

  • Crane Operator Certification NCCCO NCCER or CIC
  • Signal Person Qualification Third-party or employer evaluator
  • Crane Shift Inspection Visual check each shift
  • Crane Annual Inspection Every 12 months maximum
  • PPE Cost Rule Employer-provided at no cost
  • Hot Work Extinguisher 10-lb ABC dry chemical
  • Fire Watch Duration 30 minutes after work
  • Oxygen-Deficient Atmosphere Below 19.5% oxygen

Common Traps

6ft vs 10ft Confusion

  • General trigger is 6ft ≠ Scaffold trigger is 10ft

Serious vs Willful Mix-Up

  • Both need OSHA citation ≠ Willful requires intent shown

Silica PEL vs Action Level

  • PEL is 50 μg/m³ ≠ Action level is 25

Warning Line Alone Fails

  • Not a standalone system ≠ Needs a safety monitor

Type C Is Weakest Soil

  • Least stable of three ≠ Needs the flattest slope

Competent Is Not Qualified

  • Competent finds daily hazards ≠ Qualified designs technical systems

Crane Clearance Beats General Rule

  • General rule is 10ft ≠ Crane rule is 20ft

Last Minute

  • 1. Fall protection trigger: 6 feet
  • 2. Scaffold fall trigger: 10 feet
  • 3. Guardrail top rail: 42 inches
  • 4. Silica PEL: 50 μg/m³
  • 5. Lead action level: 30 μg/m³
  • 6. Asbestos PEL: 0.1 f/cc
  • 7. Noise PEL: 90 dBA
  • 8. Report fatality: within 8 hours
  • 9. Report hospitalization: within 24 hours
  • 10. Excavation protection trigger: 5 feet
  • 11. Scaffold safety factor: 4 times
  • 12. Competent person inspects scaffolds daily
  • 13. PFAS free fall limit: 6ft
  • 14. Multi-employer policy: four employer roles

OSHA 510 Occupational Safety and Health Standards for Construction

  • Practice Questions 100 questions Study Guide 33 topics Cheat Sheet 98 facts Flashcards 50 cards Games 43 terms Shorts 4 short s Blogs 2 blogs
  • Word games 43 terms Guess the Term T E R M S Read the clue and guess the term in 6 tries. Word games 43 terms Term Match Swap tiles to line up three of the same term. Word games 43 terms Term Pairs ? ✓ ✓ ? ? Flip two cards at a time to find matching terms. Word games 43 terms Term Search Q T E R M X Find five hidden terms in a grid of letters.