Cheat sheet

PE Civil Construction Cheat Sheet

Practice this exam

Soil Mechanics

  • 8-11% of exam
  • Lateral Pressure Effective Stress Bearing Capacity Slope Stability

Site Layout & Development

  • 6-10% of exam
  • Staking & Benchmarks Horizontal Curves Vertical Curves Utility Verification

Material Properties

  • 6-10% of exam
  • Concrete Mix Soil Classification Steel Types Wood Types

Estimating Quantities & Costs

  • 8-11% of exam
  • Quantity Takeoff Cost Estimating Engineering Economics Earned Value

Project Planning & Scheduling

  • 9-14% of exam
  • CPM Network Float Resource Leveling Time-Cost Tradeoff

Production & Quality Control

  • 9-14% of exam
  • Material Testing Concrete Placement Weld & Bolt QC Compaction

Structural Mechanics

  • 9-14% of exam
  • Loads Statics Stress & Deflection Structural Systems

Hydraulics & Hydrology

  • 5-8% of exam
  • Runoff Methods Open-Channel Flow Detention Ponds Culverts

Construction Operations & Methods

  • 11-18% of exam
  • Cranes & Rigging Dewatering Equipment Selection Cut & Fill

Support of Construction Loads

  • 12-19% of exam
  • Formwork Falsework Shoring Bracing

Health & Safety

  • 5-8% of exam
  • OSHA Thresholds Fall Protection Excavation Safety Work Zone Safety

Quick Facts

  • Exam PE Civil Construction
  • Questions 80
  • Time 8 hrs (9-hr appt)
  • Pass Score Not published
  • Format CBT, Pearson VUE
  • Fee $400
  • Level PE licensure depth exam
  • Blueprint April 2024

Rankine Earth Pressure SO

  • Ka smallest, Kp largest, K0 in between
  • Ka: active minimum Kp: passive maximum K0: at-rest value

Total Stress vs Effective Stress SO

Total stress

  • Includes pore water pressure
  • Full overburden weight

Effective stress

  • Total minus pore pressure
  • Controls soil shear strength
  • Total minus pore equals effective

Soil Mechanics Formulas SO

  • Ka (1-sinφ)/(1+sinφ) Active
  • Kp (1+sinφ)/(1-sinφ) Passive
  • Effective stress Total stress minus pore pressure
  • FS (slope) Resisting force over driving force
  • Bearing capacity Ultimate soil support pressure
  • Consolidation settlement Time-dependent clay compression

Layout & Curve Basics SI

  • HI Elevation plus backsight reading
  • New elevation HI minus foresight reading
  • R 5729.58 divided by degree Arc def
  • PC/PT Curve start and end
  • Potholing Field-verify utility depth
  • Benchmark Known reference elevation point

Material Properties MA

  • Slump test Concrete workability measure
  • W/C ratio Lower ratio, higher strength
  • Air entrainment Freeze-thaw durability protection
  • Atterberg limits Soil plasticity classification test
  • USCS Unified soil classification system
  • Prestressed steel Pre- or post-tensioned strand

Earned Value Formulas ES

  • CV=EV-AC, SV=EV-PV, CPI=EV/AC, SPI=EV/PV
  • CV: cost variance SV: schedule variance CPI: cost efficiency SPI: schedule efficiency

CPI vs SPI ES

CPI

  • Cost performance measure
  • EV divided by AC

SPI

  • Schedule performance measure
  • EV divided by PV
  • Cost efficiency vs schedule efficiency

Estimating & Economics ES

  • Swell Loose volume exceeds bank
  • Shrinkage Compacted volume below bank
  • Load factor Bank volume over loose volume
  • Mass haul diagram Cumulative cut minus fill
  • NPV Discounted future cash flows
  • Break-even point Cost equals revenue point

Earned Value Management ES

  • PV Planned value, BCWS
  • EV Earned value, BCWP
  • AC Actual cost, ACWP
  • CV EV minus AC
  • SV EV minus PV
  • CPI EV divided by AC
  • SPI EV divided by PV
  • EAC BAC divided by CPI

Total Float vs Free Float PL

Total float

  • Delay without project delay
  • Equals LS minus ES

Free float

  • Delay without successor delay
  • Local activity slack only
  • Project delay vs next activity

Schedule Analysis Selection PL

  • Repetitive units like paving or piping → Line of balance
  • Complex activity logic ties → CPM network analysis
  • Need shorter overall duration → Crash the critical path
  • Resource demand is overallocated → Level the resources
  • Simple small straightforward project → Bar or Gantt chart

CPM Scheduling PL

  • ES/EF Forward-pass activity times
  • LS/LF Backward-pass activity times
  • Total float LS minus ES
  • Free float Delay without delaying successor
  • Critical path Longest path, zero float
  • Crashing Shorten duration, add cost
  • FS/SS/FF/SF Precedence relationship types

Resource & Linear Scheduling PL

  • Resource leveling Smooths peak resource demand
  • Line of balance Repetitive-unit production scheduling
  • Time-cost tradeoff Balances duration against cost
  • Bar chart Simple activity-timeline display
  • Precedence diagram Activity-on-node network method

QA/QC Field Control QU

  • Proctor test Maximum density reference standard
  • Nuclear density gauge Field compaction verification tool
  • Concrete maturity Strength from temperature-time
  • Cylinder break 28-day strength verification
  • Bolt torque check Verifies clamping force
  • Weld inspection NDT acceptance criteria check

Provided Design Standards QU

  • ACI 347R Formwork design guide
  • ACI SP-4 Formwork for concrete
  • AISC Manual Steel construction manual
  • ASCE 37-14 Construction loads standard
  • PCA EB001 Concrete mixtures guide
  • CFR 1926 OSHA construction safety rules

Structural Mechanics Basics ST

  • Dead load Permanent structure weight
  • Construction load Temporary erection-phase load
  • Bending stress Mc divided by I
  • Shear stress VQ divided by Ib
  • Deflection check Serviceability limit state
  • Combined stress Axial plus bending superposition

Hydraulics & Hydrology HY

  • Rational method Q equals C, i, A
  • Manning's equation Open-channel flow velocity
  • Time of concentration Longest travel-time path
  • Detention pond Temporarily stores peak runoff
  • SCS/NRCS method Curve-number runoff estimate
  • Culvert Cross-drainage conveyance structure

Swell vs Shrinkage OP

Swell

  • Loose volume expands
  • Excavated soil increases

Shrinkage

  • Compacted volume decreases
  • Falls below bank volume
  • Loose state vs compacted state

Earthwork Method Selection OP

  • Cut volume exceeds fill need → Waste to spoil area
  • Site needs additional fill material → Import from borrow pit
  • Optimizing haul cost and distance → Build mass haul diagram
  • Groundwater enters open excavation → Install dewatering system
  • Deep small-diameter foundation needed → Drilled shaft or pile

Equipment & Earthwork Operations OP

  • Cut/fill analysis Balances earthwork volumes
  • Borrow pit Imported off-site fill source
  • Crane capacity Read from load chart
  • Outrigger load Ground-bearing pressure check
  • Dewatering Wellpoint or sump control
  • Deep foundation install Pile or drilled shaft

Temporary Works Sequence SU

  • Form, then Falsework, then Shore, then Reshore
  • Form: shapes concrete Falsework: supports structure Shore: supports excavation Reshore: after stripping

Formwork vs Falsework SU

Formwork

  • Shapes fresh concrete
  • Resists lateral pressure

Falsework

  • Supports structure temporarily
  • Used before strength gain
  • Concrete shape vs structure support

Temporary Structure Selection SU

  • Support wet concrete → Formwork ( Shapes fresh concrete )
  • Support structure before strength gain → Falsework
  • Support excavated soil face → Shoring
  • Remove forms before full cure → Reshoring
  • Resist lateral wind or seismic → Bracing
  • Deep unstable-soil excavation wall → Trench box or sheeting

Temporary Structures SU

  • Formwork Shapes and contains concrete
  • Falsework Temporary structural support system
  • Shoring Supports excavation or structure
  • Reshoring Support after early stripping
  • Bracing Provides lateral stability
  • Support of excavation Retains adjacent soil face
  • Form pressure Rises with pour rate

Shoring vs Bracing SU

Shoring

  • Supports excavation walls
  • Vertical or lateral loads

Bracing

  • Provides lateral stability
  • Resists wind or seismic
  • Soil support vs overall stability

OSHA Trigger Depths HE

  • 5 ft dig, 6 ft fall, 20 ft engineer
  • 5ft: excavation protection 6ft: fall protection 20ft: PE-designed system

OSHA Trigger Depth/Height HE

  • Excavation reaches 5 feet deep → Protective system required
  • Excavation exceeds 20 feet deep → PE-designed system required
  • Working at 6 feet high → Fall protection required
  • Scaffold platform 10 feet high → Fall protection required
  • Ground movement risk exists → Protect regardless of depth

OSHA Construction Thresholds HE

  • Fall protection Required at 6 feet
  • Excavation protection Required at 5 feet
  • PE-designed system Required beyond 20 feet
  • Competent person Daily excavation inspections required
  • Soil Type A/B/C Most to least stable
  • Scaffold fall protection Required at 10 feet
  • MUTCD Part 6 Temporary traffic control rules

Common Traps

Swell ≠ Shrinkage

  • Swell: loose volume grows ≠ Shrinkage: compacted volume shrinks

Total Float ≠ Free Float

  • Total: whole-project delay slack ≠ Free: next-activity delay slack

Formwork ≠ Falsework

  • Formwork: shapes wet concrete ≠ Falsework: supports temporary structure

CPI ≠ SPI

  • CPI: measures cost efficiency ≠ SPI: measures schedule efficiency

Total Stress ≠ Effective Stress

  • Total: includes pore pressure ≠ Effective: controls soil strength

Active Pressure ≠ Passive Pressure

  • Active: soil moves away ≠ Passive: soil pushed inward

Equated Score ≠ Fixed Percentage

  • NCEES uses equated scoring ≠ No published cutoff percentage

Last Minute

  • 1. 80 questions, 8 exam hours
  • 2. 9-hour appointment includes tutorial and break
  • 3. No fixed passing score published
  • 4. Support of Loads weighs most
  • 5. Operations and Methods rank second
  • 6. Fall protection required at 6ft
  • 7. Excavation protection required at 5ft
  • 8. PE-designed system required beyond 20ft
  • 9. Critical path equals zero float
  • 10. CV equals EV minus AC
  • 11. SPI equals EV over PV
  • 12. Swell expands; shrinkage compacts volume

PE Civil: Construction

  • Practice Questions 200 questions Study Guide 48 topics Cheat Sheet 88 facts Flashcards 50 cards Shorts 3 short s Videos 1 video Blogs 1 blog 1 Job Wiki Free CE Podcast