Periodic Requirements

  • 13% of exam
  • Qualification Map Source Hierarchy Scope Planning Assessment Materials EICR Documents

Safety Management

  • 5% of exam
  • Safe Isolation Instrument Control GS38 Leads Risk Assessment Live Testing

Periodic Inspection

  • 17% of exam
  • Inspection Evidence EICR Codes Extent Limitations Sampling

Periodic Testing

  • 65% of exam
  • Continuity Polarity Insulation Resistance Earthing Loop Fault RCD Functional Phase Test Selection Results Interpretation

Quick Facts

  • Qualification City & Guilds 2391-51
  • Award Level 3 Award
  • Scope Existing electrical installations
  • Mandatory unit 2391-501
  • Online test 2391-051
  • Online items 40 multiple-choice questions
  • Online time 90 minutes
  • Online condition Open book; invigilated
  • Online pass Approximately 75%
  • Pass adjustment Reliability adjusted
  • Visual task 30 minutes
  • Practical task 150 minutes
  • Short-answer task 60 minutes
  • Guided learning 41 hours
  • Total time 55 hours
  • Entry profile Experienced electrotechnical candidates
  • BS 7671 edition Check live assessment materials

Report Pack RE

  • Report, inspections, circuits, results, recipient guidance.
  • EICR Inspection schedule Circuit schedule Test results Recipient guidance

2391-51 vs 2391-50 RE

2391-51

  • Existing installations
  • Periodic condition reporting
  • EICR focus

2391-50

  • New or altered work
  • Initial verification
  • EIC focus
  • Match award to installation stage

Assessment Reference Picker RE

  • Taking online test → Paper references only
  • Taking visual Task A → No references
  • Performing practical Task B → No reference materials ( During testing )
  • Confirming Task B results → Permitted references ( After testing )
  • Taking short-answer Task C → Permitted paper references
  • Using calculations → Non-programmable calculator
  • Selecting publication edition → Follow assessment instructions
  • Adding navigation aids → Use compliant page tabs

Qualification Map RE

  • 2391-51 Periodic inspection award Exact scope
  • 2391-501 Mandatory unit Pass required
  • 2391-051 Online multiple-choice test Pass required
  • Assessment Online test plus assignment
  • Qualification level Level 3
  • GLH 41 guided hours
  • TQT 55 total hours
  • Candidate profile Experienced electrical practitioner
  • Newcomers Qualification not suitable

Assignment Tasks RE

  • Visual thirty; practical one-fifty; written sixty.
  • Task A visual Task B practical Task C short-answer

2391-51 vs 2391-52 RE

2391-51

  • Periodic pathway only
  • Existing installations

2391-52

  • Combined pathway
  • Initial plus periodic
  • Do not borrow combined content

Online Blueprint RE

  • Requirements 5 questions 13%
  • Safety management 2 questions 5%
  • Periodic inspection 7 questions 17%
  • Periodic testing 26 questions 65%
  • Online total 40 questions
  • Online duration 90 minutes
  • Online format Multiple-choice
  • Online result Pass or fail
  • Indicative pass Approximately 75%

Extent vs Limitation RE

Extent

  • Planned coverage
  • Agreed before work

Limitation

  • Restricts planned coverage
  • Reason must be recorded
  • Do not disguise reduced scope

Source Hierarchy RE

  • EAWR Workplace electrical safety law
  • Health-safety law Statutory duties
  • BS 7671 National wiring standard
  • Guidance Note 3 Inspection-testing guidance
  • GS38 Electrical test equipment guidance
  • Existing records Planning evidence
  • Previous certificates Installation history
  • Manufacturer data Equipment-specific criteria

Scope Planning RE

  • Purpose Continued-service safety assessment
  • Extent Agreed inspection coverage
  • Limitation Recorded excluded access
  • Sampling Representative inspection selection
  • Defects found Expand sampling appropriately
  • Operational constraints Plan disruption controls
  • Records review Identify installation history
  • Client agreement Confirm extent beforehand
  • Inspector duty Record accurate findings

EICR Documents RE

  • EICR Condition assessment report
  • Inspection schedule Inspected-item record
  • Circuit details Circuit identification schedule
  • Test results Measured-values schedule
  • Recipient guidance Report-use instructions
  • Extent entry Coverage clearly stated
  • Limitations entry Restrictions clearly justified
  • Next inspection Recommended interval recorded

Assessment Materials RE

  • Online test Paper references permitted
  • Online references BS7671 OSG GN3
  • Electronic references Not permitted online
  • Visual Task A No references
  • Practical Task B Confirm results only
  • Short-answer Task C Paper references permitted
  • Calculator Non-programmable scientific permitted
  • Personal notes Not permitted
  • Highlighting Permitted
  • Page tabs Paper markers permitted
  • Short cross-references Permitted
  • A4:2026 Published current amendment
  • A3:2024 Valid through 15 October 2026
  • Installation transition Either edition through 15 Oct 2026
  • Assessment edition Follow live City & Guilds materials

Isolation Sequence SA

  • Identify, inform, isolate, secure, prove, test, reprove.
  • Identify source Inform users Secure isolation Prove-test-reprove

Dead vs Live Tests SA

Dead tests

  • Supply securely isolated
  • Continuity and insulation
  • Prove dead first

Live tests

  • Supply energised
  • Loop and prospective current
  • Additional controls required
  • Never energise dead-test instruments

Safe Isolation Path SA

  • Work area confirmed → Identify every source
  • Affected users identified → Inform before isolation
  • Correct circuit confirmed → Operate isolation device
  • Circuit isolated → Lock against reconnection
  • Warning needed → Attach caution notice
  • Tester selected → Prove on known source
  • Tester proven → Confirm conductors dead
  • Dead confirmed → Reprove voltage indicator
  • Alternative source possible → Repeat source controls

Safe Isolation SA

  • Identify Correct supply and circuit
  • Inform Notify affected persons
  • Isolate Disconnect every relevant source
  • Secure Prevent reconnection
  • Prove tester Verify before testing
  • Test conductors Confirm dead safely
  • Reprove tester Verify after testing
  • Stored energy Discharge and control
  • Alternative supplies Identify every source

Calibration vs Before-Use Check SA

Calibration

  • Periodic accuracy assurance
  • Traceable maintenance record

Before-use check

  • Immediate condition check
  • Required each use
  • One never replaces the other

Instrument Control SA

  • Correct function Match intended measurement
  • Measurement category Match electrical environment
  • Voltage rating Suit expected system voltage
  • GS38 leads Protected probes and leads
  • Before-use check Inspect instrument condition
  • Calibration Maintain verified accuracy
  • Known source Prove voltage indicator
  • Instrument identifier Record traceable details
  • Live measurement Apply additional controls

Code Order IN

  • Danger, potential, improve, investigate—code actual risk.
  • C1 = danger C2 = potential C3 = improve FI = investigate

EICR vs EIC IN

EICR

  • Reports current condition
  • Uses classification codes
  • Periodic inspection output

EIC

  • Certifies installation work
  • Initial verification output
  • No condition codes
  • 2391-51 centres on EICR

Observation Code Picker IN

  • Danger exists now → C1 ( Immediate action )
  • Potential danger exists → C2 ( Urgent remediation )
  • Safety improvement advised → C3 ( Recommendation )
  • Danger possibly concealed → FI ( Investigate promptly )
  • Only C3 observations → Satisfactory ( No C1 C2 FI )
  • Any C1 found → Unsatisfactory ( Danger present )
  • Any C2 found → Unsatisfactory ( Potential danger )
  • Any FI found → Unsatisfactory ( Risk unresolved )

Inspection Evidence IN

  • Visual inspection Observe accessible condition
  • Touch Check looseness or heat safely
  • Hearing Detect abnormal operation
  • Smell Detect overheating evidence
  • IP suitability Match environmental exposure
  • Damage Assess safety significance
  • Deterioration Assess continued service
  • Alterations Check safety impact
  • Accessibility Record genuine restrictions
  • Inspection first Inform test selection

C1 vs C2 IN

C1

  • Danger present
  • Immediate action required

C2

  • Potentially dangerous
  • Urgent remedial action
  • Distinguish present from potential

Sampling and Limitation Picker IN

  • Scope is negotiable → Agree extent first
  • Sampling is proposed → Choose representative sample
  • Defect appears → Increase sample appropriately
  • Access is impossible → Record genuine limitation
  • Shutdown is restricted → Record operational limitation
  • Test risks damage → Adapt test method
  • Test must be omitted → Document exact reason
  • Evidence remains insufficient → Consider FI coding

EICR Codes IN

  • C1 Danger present Immediate action
  • C2 Potentially dangerous Urgent action
  • C3 Improvement recommended Advisory
  • FI Further investigation required Without delay
  • Unsatisfactory Any C1 C2 FI
  • C3 only May remain satisfactory
  • Code basis Actual safety risk
  • Observation State defect precisely
  • Recommendation Match identified risk

C3 vs FI IN

C3

  • Improvement recommended
  • Risk already assessable
  • Can remain satisfactory

FI

  • Risk unresolved
  • Investigation required promptly
  • Makes report unsatisfactory
  • Uncertainty about danger means FI

Inspection vs Testing IN

Inspection

  • Uses senses
  • Finds visible condition
  • Guides test selection

Testing

  • Uses instruments
  • Produces measured evidence
  • Confirms electrical performance
  • Inspect before choosing periodic tests

Test Evidence TE

  • Predict, measure, compare, interpret, record.
  • Expected value Actual value Current criterion Reasoned conclusion

Ze vs Zs TE

Ze

  • External loop impedance
  • Measured near origin

Zs

  • Complete circuit loop
  • Includes circuit conductors
  • Calculated Zs uses Ze plus R1R2

Periodic Test Picker TE

  • Verify protective paths → Continuity test ( Dead test )
  • Verify ring conductors → End-to-end tests ( Dead test )
  • Detect insulation damage → Insulation resistance ( Protect electronics )
  • Verify conductor identity → Polarity checks ( Context controls )
  • Verify electrode resistance → Earth electrode test
  • Measure external loop → Ze test ( Live precautions )
  • Measure complete loop → Zs test ( Live precautions )
  • Find prospective current → PFC test ( Record highest )
  • Verify RCD performance → RCD instrument ( Apply current criteria )
  • Verify three-phase rotation → Phase sequence tester
  • Verify device operation → Functional test
  • Assess voltage drop → Measured conductor resistance

Continuity Polarity TE

  • Protective continuity Verify protective conductor paths
  • Main bonding Confirm continuity
  • Ring line Measure end-to-end continuity
  • Ring neutral Measure end-to-end continuity
  • Ring CPC Measure end-to-end continuity
  • Cross-connections Reveal ring irregularities
  • R1 plus R2 Circuit protective path
  • Polarity Confirm correct conductor connection
  • Dead continuity Never test energised

R1+R2 vs r1+r2 TE

R1+R2

  • Circuit protective path
  • Point-specific value

r1+r2

  • Ring end-to-end sum
  • Whole ring conductors
  • Capital and lowercase differ

Insulation Resistance TE

  • Purpose Detect insulation deterioration
  • Dead test Isolate before testing
  • Sensitive equipment Protect before test
  • SPDs Disconnect when practicable
  • Connected equipment Prevent test damage
  • Separated circuits Verify required separation
  • Parallel paths Interpret measured resistance carefully
  • Test voltage Select current standard value
  • Result Compare current permitted criteria

Earthing Loop Fault TE

  • Earth electrode Measure electrode resistance
  • Ze External loop impedance
  • Zs Complete circuit loop impedance
  • Zs relationship Ze plus R1 plus R2
  • PEFC Prospective earth fault current
  • PSCC Prospective short-circuit current
  • PFC Highest relevant prospective current
  • Loop test Live-test precautions required
  • Result comparison Use current permitted limits

RCD Functional Phase TE

  • RCD instrument test Verify disconnection performance
  • RCD test button Functional operation only
  • RCD type Select compatible test method
  • Fault protection Verify applicable criteria
  • Additional protection Verify applicable criteria
  • Phase sequence Confirm correct rotation
  • Functional testing Operate controls and devices
  • Isolation devices Confirm effective operation
  • Manufacturer instructions Apply device-specific guidance

Test Selection TE

  • Fixed sequence Not recommended periodically
  • Inspection findings Drive test choices
  • Installation condition Adapt testing safely
  • Installation use Consider operational risk
  • Extent Apply agreed coverage
  • Limitations Document constrained testing
  • Omitted test Record reason clearly
  • Temperature Correct affected results
  • Conductor length Interpret resistance proportionally
  • Parallel conductors Account for parallel paths
  • Connected load Prevent false readings
  • Nulling Compensate test leads

Results Interpretation TE

  • Expected result Predict before testing
  • Measured result Record actual value
  • Permitted limit Use current assessment reference
  • Unexpected value Investigate before coding
  • Temperature correction Apply where relevant
  • Parallel path May lower resistance
  • Voltage drop Use measured conductor resistance
  • Circuit load Include design conditions
  • Documentation Transfer results accurately

Common Traps

Universal Test Sequence

  • Memorised fixed order ≠ Risk-selected periodic testing

Age-Based Coding

  • Old installation automatically defective ≠ Code actual safety risk

C3 Outcome

  • C3 automatically unsatisfactory ≠ C3-only may be satisfactory

RCD Test Button

  • Button proves disconnection time ≠ Instrument verifies performance

Reference Access

  • Same rules every task ≠ Task-specific material permissions

Electronic Books

  • Electronic references online ≠ Paper references online

C1 and C2

  • Both mean immediate danger ≠ Present versus potential danger

Inspection Timing

  • Test everything first ≠ Inspect then select tests

Calibration Assurance

  • Calibration replaces checks ≠ Check condition before use

Prospective Fault Current

  • Record lowest reading ≠ Record highest relevant value

Limitations

  • Silent exclusions acceptable ≠ Record and justify restrictions

Award Identity

  • 2391-51 equals wiring exam ≠ 2391-51 assesses periodic work

Last Minute

  • 1. Confirm 2391-51 periodic scope
  • 2. Testing carries 65% online
  • 3. Requirements carry 13% online
  • 4. Inspection carries 17% online
  • 5. Safety carries 5% online
  • 6. Carry permitted paper references
  • 7. Check live assessment edition
  • 8. Remove prohibited personal notes
  • 9. Know task-specific reference rules
  • 10. Visual Task A forbids references
  • 11. Prove voltage indicator twice
  • 12. Lock isolation against reconnection
  • 13. Identify every possible supply
  • 14. Inspect before selecting tests
  • 15. Record agreed extent and limitations
  • 16. Increase sampling after defects
  • 17. Use suitable instrument category
  • 18. Check leads meet GS38
  • 19. Record instrument identifiers
  • 20. Verify calibration status
  • 21. Classify actual safety risk
  • 22. C1 means danger present
  • 23. C2 means potentially dangerous
  • 24. C3 means improvement recommended
  • 25. FI requires further investigation
  • 26. C1 C2 FI mean unsatisfactory
  • 27. No universal periodic test sequence
  • 28. Document adapted or omitted tests
  • 29. Compare results using current criteria
  • 30. Complete every EICR schedule

City & Guilds 2391-51 Periodic Inspection & Testing of Electrical Installations

  • Practice Questions 233 questions Study Guide 27 topics Cheat Sheet 152 facts Flashcards 50 cards Podcast