Egypt Engineering Consultant Civil

Egypt Engineering Consultant — Civil (استشاري مدني)

Construction Management And QcEnglish
Exam overview

Practice session

In a project network diagram, Activity D has a duration of 6 days. Its Early Start is ES = Day 10 and Late Start is LS = Day 14. Activity D has two immediate successors: Activity E (ES = Day 16) and Activity F (ES = Day 18). What are the Total Float (TF) and Free Float (FF) for Activity D?

Loading your practice session…