In a project network diagram, Activity D has a duration of 6 days. Its Early Start is ES = Day 10 and Late Start is LS = Day 14. Activity D has two immediate successors: Activity E (ES = Day 16) and Activity F (ES = Day 18). What are the Total Float (TF) and Free Float (FF) for Activity D?