In the Critical Path Method (CPM), an activity has an Early Start (ES) of day 4, an Early Finish (EF) of day 9, a Late Start (LS) of day 7, and a Late Finish (LF) of day 12. What is the Total Float (slack) of this activity, and is it on the critical path?