EGEL Plus Informática

CENEVAL EGEL Plus Informática (EGEL Plus INFO)

Gestion De Proyectos InformaticosEnglish
Exam overview

Practice session

In the Critical Path Method (CPM), an activity has an Early Start (ES) of day 4, an Early Finish (EF) of day 9, a Late Start (LS) of day 7, and a Late Finish (LF) of day 12. What is the Total Float (slack) of this activity, and is it on the critical path?

Loading your practice session…