EGEL Plus Ingeniería Mecatrónica

CENEVAL EGEL Plus Ingeniería Mecatrónica (EGEL Plus IMECATRO)

Integracion De TecnologiasEnglish
Exam overview

Practice session

An automation retrofit project has these activities: A, design (4 weeks); B, procure parts (6 weeks, after A); C, write the PLC program (3 weeks, after A); D, assemble the cell (2 weeks, after B); E, integration and testing (2 weeks, after C and D). Using the critical path method, what is the project duration, and how much total float does activity C have?

Loading your practice session…