PMI DAF

PMI Disciplined Agile Foundations (DAF)

Lean KanbanEnglish
Exam overview

Practice session

A Kanban team wants to improve their process. Their current cycle time for feature delivery is 12 days. They notice that items often wait in a 'Ready for Development' column for 4 days. According to lean and Kanban thinking, what should the team do first?

Loading your practice session…