PRINCE2 Practitioner
Prince2 PrinciplesEnglish
Exam overviewPractice session
A Project Manager is tailoring the Project Initiation Documentation (PID) and Project Log for a low-risk internal IT upgrade. The Project Board wants minimal administrative overhead. Which approach best applies the PRINCE2 7 principle 'tailor to suit the project'?
Loading your practice session…