A Product Owner is choosing between two Product Backlog items of similar effort. Item A is expected to generate $10K/week of value but has $100K cost of delay if released next quarter. Item B is expected to generate $40K/week with no time-sensitivity. Using Cost of Delay reasoning typical of WSJF, which should ship FIRST?