11.4 Forecasting: EAC, ETC, VAC & TCPI

AACE Certified Cost Technician CCT

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: AACE Certification, Ethics & Total Cost Management Framework

1.1 About the AACE CCT Exam & Certification Pathway 1.2 AACE Canons of Ethics & Professional Practice 1.3 Total Cost Management (TCM) Framework Architecture 1.4 Cost Engineering Terminology & Core Concepts 1.5 Strategic Asset Management: Asset Performance, Assessment & Configuration Control

2 Chapter 2: Elements of Cost, Labor, Materials & Indirects

2.1 Cost Classification & Cost Behavior 2.2 Labor Costs, Craft Rates & Labor Burden 2.3 Materials & Equipment Cost Fundamentals 2.4 Job-Site Indirects & Home Office Overhead Allocation 2.5 Cost Dimensions: Life Cycles, Perspective, Influence & the Legal Dimension

3 Chapter 3: Engineering Economics: Time Value of Money & Depreciation

3.1 Time Value of Money & Cash Flow Diagrams 3.2 Uniform Series & Equivalence Factors 3.3 Nominal vs. Effective Interest Rates & Inflation 3.4 Depreciation Methods & Asset Write-Down

4 Chapter 4: Capital Budgeting, NPV, IRR & Life Cycle Costing

4.1 Net Present Value (NPV) & Present Worth Analysis 4.2 Internal Rate of Return (IRR) & MARR 4.3 Payback Period & Benefit-Cost Ratio Analysis 4.4 After-Tax Cash Flow Analysis & Life Cycle Costing

5 Chapter 5: Statistics, Probability & Decision Models

5.1 Descriptive Statistics & Measures of Dispersion 5.2 Probability Concepts & Distributions 5.3 Decision Trees & Expected Monetary Value (EMV) 5.4 Linear Programming & Optimization Models 5.5 Physical Measurement, Unit Systems & Quantity Conversions

6 Chapter 6: Organization, Communications & Project Management Basics

6.1 Organizational Structures & Project Roles 6.2 Communications Management & Project Reporting 6.3 Cost Data Management & Historical Normalization

7 Chapter 7: Cost Estimating Principles & Classification Systems

7.1 Estimating Fundamentals & Basis of Estimate 7.2 AACE 18R-97 Cost Estimate Classification System 7.3 Conceptual & Parametric Estimating Methods 7.4 Detailed Estimating & Estimate Closeout

8 Chapter 8: Allowances, Escalation, Location Factors & Contingency

8.1 Allowances vs. Contingency vs. Management Reserve 8.2 Location Factors & Escalation Analysis 8.3 Contingency Determination & Risk Analysis

9 Chapter 9: Project Planning, WBS & CPM Scheduling

9.1 Work Breakdown Structure (WBS) & Scope Definition 9.2 Activity Definition, Precedence & Dependencies 9.3 Critical Path Method (CPM) Forward & Backward Pass 9.4 Float Calculations & Schedule Compression 9.5 Requirements Elicitation, Plan Implementation & Plan Validation

10 Chapter 10: PERT Estimating, Progress Measurement & Schedule Control

10.1 PERT Three-Point Estimating & Network Variance 10.2 Progress Measurement & Rules of Credit 10.3 Schedule Baseline Maintenance & Change Control

11 Chapter 11: Earned Value Management (EVM): Variances, Indices & Forecasting

11.1 EVM Foundations & Core Parameters 11.2 Cost & Schedule Variances 11.3 Performance Indices 11.4 Forecasting: EAC, ETC, VAC & TCPI

12 Chapter 12: Procurement, Contract Types & Administration

12.1 Contract Types & Risk Allocation Spectrum 12.2 Procurement Process, Solicitation & Bidding 12.3 Surety Bonds & Project Insurance 12.4 Contract Administration, Changes & Claims

13 Chapter 13: Project Risk Management: Identification, Analysis & Response

13.1 Risk Management Planning & Identification 13.2 Qualitative & Quantitative Risk Analysis 13.3 Risk Response Strategies & Risk Control

14 Chapter 14: Quality Management, Value Engineering & Resource Management

14.1 Quality Concepts & Cost of Quality (COQ) 14.2 Quality Control Tools & Continuous Improvement 14.3 Value Engineering & Value Methodology 14.4 Resource Management, Leveling & Learning Curve Theory 14.5 Environmental, Health & Safety (EHS) Cost Management

11.4 Forecasting: EAC, ETC, VAC & TCPI

Key Takeaways Explain This Topic AI

Estimate at Completion (EAC) projects the final total cost of a project, calculated under specific future performance assumptions: typical continuing efficiency (EAC = BAC / CPI), atypical isolated variances (EAC = AC + [BAC - EV]), or combined cost-schedule pressure (EAC = AC + [(BAC - EV) / (CPI * SPI)]).

Estimate to Complete (ETC = EAC - AC) quantifies the additional financial resources required to finish all outstanding project scope, which can be derived mathematically or calculated via a bottom-up physical re-estimate.

Variance at Completion (VAC = BAC - EAC) projects the final budget variance, where positive values denote a cost surplus and negative values represent a projected cost overrun.

The To-Complete Performance Index (TCPI) determines the cost efficiency that must be maintained on all remaining work to achieve a specific financial objective, calculated against the original budget (TCPI_BAC = [BAC - EV] / [BAC - AC]) or a revised estimate (TCPI_EAC = [BAC - EV] / [EAC - AC]).

If the calculated TCPI based on BAC exceeds the current cumulative CPI by more than 0.10 (10%), achieving the original budget is statistically and operationally unachievable, necessitating a formal rebaseline to an approved EAC.

Last updated: September 2026

11.4 Forecasting: EAC, ETC, VAC & TCPI

Quick Summary: Historical variances and indices ( C V , S V , C P I , S P I CV, SV, CPI, SPI C V , S V , CP I , SP I ) describe past performance. However, executive project governance requires predictive forecasting: How much will the project ultimately cost, how much additional cash is needed to finish, and how efficiently must the remaining work be executed? EVM answers these questions through Estimate at Completion (EAC) , Estimate to Complete (ETC) , Variance at Completion (VAC) , and the To-Complete Performance Index (TCPI) . Selecting the correct EAC formula depends strictly on management's assumptions regarding whether past performance was typical (will persist), atypical (one-off event), or constrained by immovable schedule deadlines ( C P I × S P I CPI \times SPI CP I × SP I ). When evaluated against current CPI, TCPI provides an indispensable mathematical "reality check" on baseline feasibility.

1. Principles of Predictive Cost Forecasting

In capital projects, waiting until project closeout to recognize an overrun is professional negligence. Earned Value Management provides statistical forecasting mechanisms that project final financial outcomes early in the project lifecycle. +-----------------------------------------------------------------------------------+

  • | EVM FORECASTING TERMINOLOGY |
  • | |
  • | - BAC: Budget at Completion --> The original authorized baseline budget |
  • | - EAC: Estimate at Completion --> The forecasted final total project cost |
  • | - ETC: Estimate to Complete --> Forecasted additional funds needed to end |
  • | - VAC: Variance at Completion --> Projected final overrun or surplus |
  • | - TCPI: To-Complete Perf. Index --> Required efficiency on remaining work |
  • +-----------------------------------------------------------------------------------+
  • 2. Estimate at Completion (EAC) Formulations & Assumptions

There is no single "universal" EAC equation. Cost engineers select from four primary formulations based on explicit, defensible assumptions regarding future project conditions. +-----------------------------------------------------------------------------------+

  • | THE FOUR EAC FORMULATIONS |
  • +-----------------------------------------------------------------------------------+
  • | CASE 1: TYPICAL FUTURE PERFORMANCE (Default / Continuing Trend) |
  • | Assumption: Future work will proceed at the current cumulative CPI. |
  • | $$\mathbf{EAC = \frac{BAC}{CPI}} = AC + \frac{BAC - EV}{CPI}$$ |
  • +-----------------------------------------------------------------------------------+
  • | CASE 2: ATYPICAL FUTURE PERFORMANCE (One-Off Past Variances) |
  • | Assumption: Past variances were anomalies; remaining work proceeds at |
  • | the planned baseline budget rate (Future CPI = 1.0). |
  • | $$\mathbf{EAC = AC + (BAC - EV)}$$ |
  • +-----------------------------------------------------------------------------------+
  • | CASE 3: COMBINED COST & SCHEDULE CONSTRAINTS (Hard Fixed Deadlines) |
  • | Assumption: Both cost efficiency and schedule delays will impact the |
  • | cost of remaining work (e.g., crashing to meet firm date). |
  • | $$\mathbf{EAC = AC + \frac{BAC - EV}{CPI \times SPI}}$$ |
  • +-----------------------------------------------------------------------------------+
  • | CASE 4: COMPREHENSIVE BOTTOM-UP RE-ESTIMATE (Fundamental Re-forecast) |
  • | Assumption: Original baseline assumptions are invalid; fresh QTO done. |
  • | $$\mathbf{EAC = AC + \text{Bottom-Up ETC}}$$ |
  • +-----------------------------------------------------------------------------------+
  • Detailed Analysis of EAC Assumptions
  • Case 1: Typical Performance ( E A C = B A C / C P I EAC = BAC / CPI E A C = B A C / CP I )

Operational Context: The default standard across AACE and DoD projects. It assumes that the organizational, labor, environmental, and commercial productivity experienced to date represents the "new normal" for the remainder of the project.

Mathematical Identity: Notice that: E A C = A C + B A C − E V C P I = A C + B A C C P I − E V C P I EAC = AC + \frac{BAC - EV}{CPI} = AC + \frac{BAC}{CPI} - \frac{EV}{CPI} E A C = A C + CP I B A C − E V ​ = A C + CP I B A C ​ − CP I E V ​ Because E V / C P I = E V / ( E V / A C ) = A C EV / CPI = EV / (EV / AC) = AC E V / CP I = E V / ( E V / A C ) = A C , the actual costs cancel out: E A C = A C + B A C C P I − A C = B A C C P I EAC = AC + \frac{BAC}{CPI} - AC = \frac{BAC}{CPI} E A C = A C + CP I B A C ​ − A C = CP I B A C ​ Both formulations yield the exact same mathematical result.

Case 2: Atypical Performance ( E A C = A C + [ B A C − E V ] EAC = AC + [BAC - EV] E A C = A C + [ B A C − E V ] )

Operational Context: Used only when past variances were caused by non-recurring, isolated "black swan" events (e.g., a one-time Category 5 hurricane, an isolated supplier bankruptcy, or an unforeseen geotechnical sinkhole that has been fully remediated).

Mechanism: The project absorbs the actual cost incurred to date ( A C AC A C ), and assumes all remaining physical scope ( B A C − E V BAC - EV B A C − E V ) will be executed exactly at the original budgeted rate ( C P I f u t u r e = 1.00 CPI_{future} = 1.00 CP I f u t u re ​ = 1.00 ).

Case 3: Combined Cost and Schedule ( E A C = A C + [ ( B A C − E V ) / ( C P I × S P I ) ] EAC = AC + [(BAC - EV) / (CPI \times SPI)] E A C = A C + [( B A C − E V ) / ( CP I × SP I )]

Operational Context: Applied when a project has an immovable contractual completion date with severe delay damages. When a project is behind schedule ( S P I < 1.0 SPI < 1.0 SP I < 1.0 ), the project manager must accelerate remaining work through overtime, second shifts, and expedited freight. These corrective measures inflate labor inefficiency, compounding the existing cost distress ( C P I < 1.0 CPI < 1.0 CP I < 1.0 ). Dividing remaining work by the Critical Ratio ( C P I × S P I CPI \times SPI CP I × SP I ) produces the most conservative (highest cost) forecast.

Case 4: Bottom-Up Re-estimate ( E A C = A C + Bottom-Up ETC EAC = AC + \text{Bottom-Up ETC} E A C = A C + Bottom-Up ETC )

Operational Context: When actual site conditions deviate so drastically from baseline assumptions that statistical index projections become useless, the project team executes a complete bottom-up re-estimate of remaining work packages (new quantity takeoffs, crew builds, and vendor bids). This becomes the Bottom-Up ETC.

  • 3. Estimate to Complete (ETC) & Variance at Completion (VAC)
  • Estimate to Complete (ETC)

Estimate to Complete (ETC) represents the expected additional cash outlay required to finish all outstanding project scope from the status date onward: E T C = E A C − A C \mathbf{ETC = EAC - AC} ETC = EAC − AC

If calculating ETC directly based on typical future performance: E T C t y p i c a l = B A C − E V C P I \mathbf{ETC_{typical} = \frac{BAC - EV}{CPI}} ET C typical ​ = CPI BAC − EV ​

Variance at Completion (VAC)

Variance at Completion (VAC) projects the final monetary surplus or deficit at project closeout: V A C = B A C − E A C \mathbf{VAC = BAC - EAC} VAC = BAC − EAC +-----------------------------------------------------------------------------------+

  • | VAC INTERPRETATION MATRIX |
  • | |
  • | VAC > 0 (+) --> Favorable Cost Surplus (Project will finish UNDER budget) |
  • | VAC = 0 --> On Budget (Project will finish exactly at approved baseline) |
  • | VAC < 0 (-) --> Unfavorable Cost Overrun (Project will EXCEED approved budget) |
  • +-----------------------------------------------------------------------------------+

Caution

The VAC Subtraction Trap: Notice that V A C = B A C − E A C VAC = BAC - EAC V A C = B A C − E A C . It is not E A C − B A C EAC - BAC E A C − B A C . If your project has a B A C = $ 1 , 000 , 000 BAC = \text{\textdollar}1,000,000 B A C = $ 1 , 000 , 000 and an forecasted E A C = $ 1 , 200 , 000 EAC = \text{\textdollar}1,200,000 E A C = $ 1 , 200 , 000 , the calculation is: V A C = $ 1 , 000 , 000 − $ 1 , 200 , 000 = − $ 200 , 000 VAC = \$1,000,000 - \$1,200,000 = -\$200,000 V A C = $1 , 000 , 000 − $1 , 200 , 000 = − $200 , 000 The negative sign correctly indicates an unfavorable overrun of $200,000 .

4. To-Complete Performance Index (TCPI)

The To-Complete Performance Index (TCPI) is the efficiency benchmark of future project performance. It defines the cost efficiency that the project team must achieve on all remaining work to meet a specified management financial goal. T C P I = Work Remaining Funds Remaining = B A C − E V Target Ceiling − A C \mathbf{TCPI = \frac{\text{Work Remaining}}{\text{Funds Remaining}} = \frac{BAC - EV}{\text{Target Ceiling} - AC}} TCPI = Funds Remaining Work Remaining ​ = Target Ceiling − AC BAC − EV ​

Depending on whether management's target ceiling is the original budget ( B A C BAC B A C ) or an approved revised forecast ( E A C EAC E A C ), cost technicians use one of two distinct TCPI formulations: +-----------------------------------------------------------------------------------+

  • | THE TWO TCPI FORMULATIONS |
  • +-----------------------------------------------------------------------------------+
  • | 1. TCPI BASED ON BAC (Target: Finish within Original Authorized Budget): |
  • | $$\mathbf{TCPI_{BAC} = \frac{BAC - EV}{BAC - AC}}$$ |
  • | |
  • | 2. TCPI BASED ON EAC (Target: Finish within Approved Revised Forecast): |
  • | $$\mathbf{TCPI_{EAC} = \frac{BAC - EV}{EAC - AC}}$$ |
  • +-----------------------------------------------------------------------------------+
  • Practical Interpretation of TCPI Values

Unlike CPI (where higher is better), TCPI represents a required hurdle rate:

T C P I > 1.0 TCPI > 1.0 TCP I > 1.0 (Demanding): The team must operate more efficiently than originally budgeted to meet the target. E.g., T C P I = 1.25 TCPI = 1.25 TCP I = 1.25 means the remaining work must achieve $1.25 of progress for every $1.00 spent (a 25% productivity improvement).

T C P I = 1.0 TCPI = 1.0 TCP I = 1.0 (Baseline): The remaining work can be executed exactly at the original baseline efficiency.

T C P I < 1.0 TCPI < 1.0 TCP I < 1.0 (Lenient): The team can perform less efficiently than budgeted and still meet the target. This occurs when an expanded E A C EAC E A C budget envelope has been approved.

The TCPI Feasibility "Reality Check" (The Rule of 0.10)

Cost technicians evaluate the operational credibility of project recovery plans by comparing T C P I B A C TCPI_{BAC} TCP I B A C ​ against the current cumulative C P I CPI CP I : +-----------------------------------------------------------------------------------+

  • | THE TCPI FEASIBILITY REALITY CHECK |
  • | |
  • | If: TCPI_BAC - CPI_cumulative > 0.10 (10 Percentage Points) |
  • | --> The target BAC is STATISTICALLY AND OPERATIONALLY UNREALISTIC. |
  • | --> Management cannot achieve the plan; a formal EAC rebaseline is required. |
  • +-----------------------------------------------------------------------------------+

Example: If a contractor has a cumulative C P I = 0.82 CPI = 0.82 CP I = 0.82 , and the calculated T C P I B A C = 1.15 TCPI_{BAC} = 1.15 TCP I B A C ​ = 1.15 , the contractor is claiming they will improve craft productivity from 0.82 0.82 0.82 to 1.15 1.15 1.15 (a delta of + 0.33 +0.33 + 0.33 , or a 40% leap in productivity). In construction and engineering, sustained 40% productivity spikes never happen. The plan is a statistical delusion.

5. Master Numerical Case Study: Complete EVM Project Lifecycle

The Project: Constructing a regional electrical transmission switching station.

  • Authorized Budget at Completion (BAC): $5,000,000
  • Project Duration: 10 Months
  • Status Cutoff Date: End of Month 5 (Midpoint)

Status Date Financial & Schedule Data:

Scheduled Progress: The baseline schedule planned for 60% of total scope to be completed by Month 5.

Actual Physical Progress: Independent field engineering surveys verify that exactly 50% of the physical scope has been installed and inspected.

Cumulative Accounting Costs: The project job ledger records total cumulative actual costs of $3,000,000 ( A C AC A C ) incurred through the end of Month 5.

  • Step 1: Calculate the Four Core Parameters
  • B A C = $ 5 , 000 , 000 BAC = \mathbf{\text{\textdollar}5,000,000} B A C = $ 5 , 000 , 000 (Authorized budget)

P V = B A C × % Scheduled = $ 5 , 000 , 000 × 0.60 = $ 3 , 000 , 000 PV = BAC \times \% \text{ Scheduled} = \text{\textdollar}5,000,000 \times 0.60 = \mathbf{\text{\textdollar}3,000,000} P V = B A C × % Scheduled = $ 5 , 000 , 000 × 0.60 = $ 3 , 000 , 000

E V = B A C × % Physical Complete = $ 5 , 000 , 000 × 0.50 = $ 2 , 500 , 000 EV = BAC \times \% \text{ Physical Complete} = \text{\textdollar}5,000,000 \times 0.50 = \mathbf{\text{\textdollar}2,500,000} E V = B A C × % Physical Complete = $ 5 , 000 , 000 × 0.50 = $ 2 , 500 , 000

  • A C = $ 3 , 000 , 000 AC = \mathbf{\text{\textdollar}3,000,000} A C = $ 3 , 000 , 000 (Recorded expenditures)
  • Step 2: Calculate Absolute and Percentage Variances

Cost Variance ( C V CV C V ): C V = E V − A C = $ 2 , 500 , 000 − $ 3 , 000 , 000 = − $ 500 , 000 ( Unfavorable / Over Budget ) CV = EV - AC = \$2,500,000 - \$3,000,000 = -\mathbf{\$500,000} \quad (\text{Unfavorable / Over Budget}) C V = E V − A C = $2 , 500 , 000 − $3 , 000 , 000 = − $500 , 000 ( Unfavorable / Over Budget )

Schedule Variance ( S V SV S V ): S V = E V − P V = $ 2 , 500 , 000 − $ 3 , 000 , 000 = − $ 500 , 000 ( Unfavorable / Behind Schedule ) SV = EV - PV = \$2,500,000 - \$3,000,000 = -\mathbf{\$500,000} \quad (\text{Unfavorable / Behind Schedule}) S V = E V − P V = $2 , 500 , 000 − $3 , 000 , 000 = − $500 , 000 ( Unfavorable / Behind Schedule )

Cost Variance Percentage ( C V % CV\% C V % ): C V % = ( C V E V ) × 100 = ( − $ 500 , 000 $ 2 , 500 , 000 ) × 100 = − 20.0 % CV\% = \left(\frac{CV}{EV}\right) \times 100 = \left(\frac{-\$500,000}{\$2,500,000}\right) \times 100 = -\mathbf{20.0\%} C V % = ( E V C V ​ ) × 100 = ( $2 , 500 , 000 − $500 , 000 ​ ) × 100 = − 20.0%

Schedule Variance Percentage ( S V % SV\% S V % ): S V % = ( S V P V ) × 100 = ( − $ 500 , 000 $ 3 , 000 , 000 ) × 100 = − 16.67 % SV\% = \left(\frac{SV}{PV}\right) \times 100 = \left(\frac{-\$500,000}{\$3,000,000}\right) \times 100 = -\mathbf{16.67\%} S V % = ( P V S V ​ ) × 100 = ( $3 , 000 , 000 − $500 , 000 ​ ) × 100 = − 16.67%

Step 3: Calculate Performance Indices

Cost Performance Index ( C P I CPI CP I ): C P I = E V A C = $ 2 , 500 , 000 $ 3 , 000 , 000 = 0.8333 CPI = \frac{EV}{AC} = \frac{\$2,500,000}{\$3,000,000} = \mathbf{0.8333} CP I = A C E V ​ = $3 , 000 , 000 $2 , 500 , 000 ​ = 0.8333 (The project earns only $0.833 of value for every $1.00 spent).

Schedule Performance Index ( S P I SPI SP I ): S P I = E V P V = $ 2 , 500 , 000 $ 3 , 000 , 000 = 0.8333 SPI = \frac{EV}{PV} = \frac{\$2,500,000}{\$3,000,000} = \mathbf{0.8333} SP I = P V E V ​ = $3 , 000 , 000 $2 , 500 , 000 ​ = 0.8333 (Work is progressing at only 83.3% of the planned schedule pace).

Critical Ratio ( C R CR CR ): C R = C P I × S P I = 0.8333 × 0.8333 = 0.6944 CR = CPI \times SPI = 0.8333 \times 0.8333 = \mathbf{0.6944} CR = CP I × SP I = 0.8333 × 0.8333 = 0.6944 (Severe distress: C R < 0.80 CR < 0.80 CR < 0.80 indicates immediate corrective action required).

Step 4: Forecast Final Costs Across EAC Scenarios

Calculate work remaining: Work Remaining = B A C − E V = $ 5 , 000 , 000 − $ 2 , 500 , 000 = $ 2 , 500 , 000 \text{Work Remaining} = BAC - EV = \text{\textdollar}5,000,000 - \text{\textdollar}2,500,000 = \mathbf{\text{\textdollar}2,500,000} Work Remaining = B A C − E V = $ 5 , 000 , 000 − $ 2 , 500 , 000 = $ 2 , 500 , 000 .

Scenario A: Typical Future Performance (Cumulative CPI will continue) E A C t y p = B A C C P I = $ 5 , 000 , 000 0.8333 = $ 6 , 000 , 000 EAC_{typ} = \frac{BAC}{CPI} = \frac{\$5,000,000}{0.8333} = \mathbf{\$6,000,000} E A C t y p ​ = CP I B A C ​ = 0.8333 $5 , 000 , 000 ​ = $6 , 000 , 000 E T C t y p = E A C − A C = $ 6 , 000 , 000 − $ 3 , 000 , 000 = $ 3 , 000 , 000 ETC_{typ} = EAC - AC = \$6,000,000 - \$3,000,000 = \mathbf{\$3,000,000} ET C t y p ​ = E A C − A C = $6 , 000 , 000 − $3 , 000 , 000 = $3 , 000 , 000 V A C t y p = B A C − E A C = $ 5 , 000 , 000 − $ 6 , 000 , 000 = − $ 1 , 000 , 000 ( Overrun of $ 1.0 M ) VAC_{typ} = BAC - EAC = \$5,000,000 - \$6,000,000 = -\mathbf{\$1,000,000} \quad (\text{Overrun of } \$1.0\text{M}) V A C t y p ​ = B A C − E A C = $5 , 000 , 000 − $6 , 000 , 000 = − $1 , 000 , 000 ( Overrun of $1.0 M )

Scenario B: Atypical Future Performance (Past variance was an isolated event; remaining work at budget) E A C a t y p = A C + ( B A C − E V ) = $ 3 , 000 , 000 + $ 2 , 500 , 000 = $ 5 , 500 , 000 EAC_{atyp} = AC + (BAC - EV) = \$3,000,000 + \$2,500,000 = \mathbf{\$5,500,000} E A C a t y p ​ = A C + ( B A C − E V ) = $3 , 000 , 000 + $2 , 500 , 000 = $5 , 500 , 000 E T C a t y p = E A C − A C = $ 5 , 500 , 000 − $ 3 , 000 , 000 = $ 2 , 500 , 000 ETC_{atyp} = EAC - AC = \$5,500,000 - \$3,000,000 = \mathbf{\$2,500,000} ET C a t y p ​ = E A C − A C = $5 , 500 , 000 − $3 , 000 , 000 = $2 , 500 , 000 V A C a t y p = B A C − E A C = $ 5 , 000 , 000 − $ 5 , 500 , 000 = − $ 500 , 000 ( Overrun of $ 500 k ) VAC_{atyp} = BAC - EAC = \$5,000,000 - \$5,500,000 = -\mathbf{\$500,000} \quad (\text{Overrun of } \$500\text{k}) V A C a t y p ​ = B A C − E A C = $5 , 000 , 000 − $5 , 500 , 000 = − $500 , 000 ( Overrun of $500 k )

Scenario C: Combined Cost and Schedule Constraints (Hard deadline / Overtime acceleration) E A C c o m b = A C + B A C − E V C P I × S P I = $ 3 , 000 , 000 + $ 2 , 500 , 000 0.8333 × 0.8333 = $ 3 , 000 , 000 + $ 2 , 500 , 000 0.6944 = $ 6 , 600 , 000 EAC_{comb} = AC + \frac{BAC - EV}{CPI \times SPI} = \$3,000,000 + \frac{\$2,500,000}{0.8333 \times 0.8333} = \$3,000,000 + \frac{\$2,500,000}{0.6944} = \mathbf{\$6,600,000} E A C co mb ​ = A C + CP I × SP I B A C − E V ​ = $3 , 000 , 000 + 0.8333 × 0.8333 $2 , 500 , 000 ​ = $3 , 000 , 000 + 0.6944 $2 , 500 , 000 ​ = $6 , 600 , 000 E T C c o m b = E A C − A C = $ 6 , 600 , 000 − $ 3 , 000 , 000 = $ 3 , 600 , 000 ETC_{comb} = EAC - AC = \$6,600,000 - \$3,000,000 = \mathbf{\$3,600,000} ET C co mb ​ = E A C − A C = $6 , 600 , 000 − $3 , 000 , 000 = $3 , 600 , 000 V A C c o m b = B A C − E A C = $ 5 , 000 , 000 − $ 6 , 600 , 000 = − $ 1 , 600 , 000 ( Overrun of $ 1.6 M ) VAC_{comb} = BAC - EAC = \$5,000,000 - \$6,600,000 = -\mathbf{\$1,600,000} \quad (\text{Overrun of } \$1.6\text{M}) V A C co mb ​ = B A C − E A C = $5 , 000 , 000 − $6 , 600 , 000 = − $1 , 600 , 000 ( Overrun of $1.6 M )

Step 5: Evaluate To-Complete Performance Indices (TCPI)

1. TCPI to Achieve the Original Baseline Budget ( B A C = $ 5 , 000 , 000 BAC = \text{\textdollar}5,000,000 B A C = $ 5 , 000 , 000 ): Work Remaining = B A C − E V = $ 5 , 000 , 000 − $ 2 , 500 , 000 = $ 2 , 500 , 000 \text{Work Remaining} = BAC - EV = \$5,000,000 - \$2,500,000 = \$2,500,000 Work Remaining = B A C − E V = $5 , 000 , 000 − $2 , 500 , 000 = $2 , 500 , 000 Funds Remaining in BAC = B A C − A C = $ 5 , 000 , 000 − $ 3 , 000 , 000 = $ 2 , 000 , 000 \text{Funds Remaining in BAC} = BAC - AC = \$5,000,000 - \$3,000,000 = \$2,000,000 Funds Remaining in BAC = B A C − A C = $5 , 000 , 000 − $3 , 000 , 000 = $2 , 000 , 000 T C P I B A C = B A C − E V B A C − A C = $ 2 , 500 , 000 $ 2 , 000 , 000 = 1.25 TCPI_{BAC} = \frac{BAC - EV}{BAC - AC} = \frac{\$2,500,000}{\$2,000,000} = \mathbf{1.25} TCP I B A C ​ = B A C − A C B A C − E V ​ = $2 , 000 , 000 $2 , 500 , 000 ​ = 1.25

Feasibility Reality Check:

Current cumulative C P I CPI CP I is 0.833 .

Required future C P I CPI CP I is 1.250 .

Δ = T C P I B A C − C P I = 1.250 − 0.833 = + 0.417 \Delta = TCPI_{BAC} - CPI = 1.250 - 0.833 = +\mathbf{0.417} Δ = TCP I B A C ​ − CP I = 1.250 − 0.833 = + 0.417 (a 50% productivity leap!).

Because Δ = 0.417 ≫ 0.10 \Delta = 0.417 \gg 0.10 Δ = 0.417 ≫ 0.10 , achieving the original $5,000,000 BAC is statistically impossible under the Christensen stability rule. Management cannot recover.

2. TCPI to Achieve the Realistic Revised Forecast ( E A C t y p = $ 6 , 000 , 000 EAC_{typ} = \text{\textdollar}6,000,000 E A C t y p ​ = $ 6 , 000 , 000 ): Funds Remaining in EAC = E A C − A C = $ 6 , 000 , 000 − $ 3 , 000 , 000 = $ 3 , 000 , 000 \text{Funds Remaining in EAC} = EAC - AC = \$6,000,000 - \$3,000,000 = \$3,000,000 Funds Remaining in EAC = E A C − A C = $6 , 000 , 000 − $3 , 000 , 000 = $3 , 000 , 000 T C P I E A C = B A C − E V E A C − A C = $ 2 , 500 , 000 $ 3 , 000 , 000 = 0.8333 TCPI_{EAC} = \frac{BAC - EV}{EAC - AC} = \frac{\$2,500,000}{\$3,000,000} = \mathbf{0.8333} TCP I E A C ​ = E A C − A C B A C − E V ​ = $3 , 000 , 000 $2 , 500 , 000 ​ = 0.8333

Feasibility Reality Check:

Required future efficiency ( T C P I E A C = 0.8333 TCPI_{EAC} = 0.8333 TCP I E A C ​ = 0.8333 ) matches the current cumulative performance ( C P I = 0.8333 CPI = 0.8333 CP I = 0.8333 ).

This target is highly achievable because the team only needs to maintain its existing operating rhythm without further degradation.

Step 6: Master Summary Matrix of Forecasting Results

  • Metric / Scenario Governing Equation Numerical Value Variance from BAC Managerial Interpretation
  • Baseline BAC Approved PMB $5,000,000 Baseline Contractually authorized budget ceiling

EAC (Typical) B A C / C P I BAC / CPI B A C / CP I $6,000,000 -$1,000,000 Most probable outcome if current trends persist

ETC (Typical) E A C − A C EAC - AC E A C − A C $3,000,000 — Additional cash required to complete project

VAC (Typical) B A C − E A C BAC - EAC B A C − E A C -$1,000,000 Overrun Projected final cost deficit at completion

EAC (Atypical) A C + ( B A C − E V ) AC + (BAC - EV) A C + ( B A C − E V ) $5,500,000 -$500,000 Best-case outcome if past variance was a 1-off event

EAC (Combined) A C + [ ( B A C − E V ) / ( C P I × S P I ) ] AC + [(BAC - EV) / (CPI \times SPI)] A C + [( B A C − E V ) / ( CP I × SP I )] $6,600,000 -$1,600,000 Worst-case outcome under hard schedule crunch

TCPI (BAC) ( B A C − E V ) / ( B A C − A C ) (BAC - EV) / (BAC - AC) ( B A C − E V ) / ( B A C − A C ) 1.25 Unrealistic Requires unachievable 50% productivity jump

TCPI (EAC) ( B A C − E V ) / ( E A C − A C ) (BAC - EV) / (EAC - AC) ( B A C − E V ) / ( E A C − A C ) 0.833 Realistic Requires maintaining existing productivity rate

6. Exam Watch: High-Yield Traps & Rules of Thumb

Warning

The EAC Formula Selection Trap: Exam questions will state: "Variances experienced to date are considered non-recurring and future work will proceed as originally planned. What is the EAC?" Candidates who reflexively calculate B A C / C P I BAC / CPI B A C / CP I will get the question wrong! When variances are non-recurring/atypical, use E A C = A C + ( B A C − E V ) EAC = AC + (BAC - EV) E A C = A C + ( B A C − E V ) .

Caution

The TCPI Denominator Confusion: In T C P I B A C TCPI_{BAC} TCP I B A C ​ , the denominator is ( B A C − A C ) (BAC - AC) ( B A C − A C ) . In T C P I E A C TCPI_{EAC} TCP I E A C ​ , the denominator is ( E A C − A C ) (EAC - AC) ( E A C − A C ) . The numerator is always the identical work remaining: ( B A C − E V ) (BAC - EV) ( B A C − E V ) . Never put ( E A C − E V ) (EAC - EV) ( E A C − E V ) in the numerator!

Tip

VAC Sign Conventions: A positive VAC ( V A C > 0 VAC > 0 V A C > 0 ) is favorable (finishing under budget with a cash surplus). A negative VAC ( V A C < 0 VAC < 0 V A C < 0 ) is unfavorable (finishing over budget with an overrun). Always evaluate VAC as B A C − E A C BAC - EAC B A C − E A C .

Loading diagram... EVM Forecasting Decision Logic Tree