2.4 Construction Estimating, Markup & Bid Preparation

Alabama HVAC Contractor License Exam

Track your progress as you read

Finished sections get a check mark.

1 Alabama HACR Laws, Rules & Licensing

1.1 Alabama HACR Board Authority, Licensing Pathways & Experience Requirements 1.2 Contractor Bonding, Insurance, Fees & Annual Renewal 1.3 Permits, Local Jurisdictions, Inspections & Disciplinary Actions

2 Contractor Business, Contracts, Estimating & Alabama Lien Law

2.1 Business Organization, Risk Management & Project Administration 2.2 Construction Contracts, Change Orders & Warranties 2.3 Alabama Mechanics' Lien Law & Financial Management 2.4 Construction Estimating, Markup & Bid Preparation 2.5 Project Management, Scheduling & Field Supervision 2.6 Risk Management, Contractor Insurance & Surety Bonds

3 Safety Standards, OSHA & EPA Section 608

3.1 OSHA Construction Safety (29 CFR 1926) for HVAC Contractors 3.2 EPA Section 608 Refrigerant Regulations & Recovery Requirements 3.3 Refrigerant Management, Leak Repair Rules & A2L Transition

4 General Technical Knowledge & Thermodynamics

4.1 Principles of Heat Transfer, Temperature & Pressure 4.2 The Mechanical Refrigeration Cycle & Refrigerant Properties 4.3 Psychrometrics & Air Properties for Humid Climates 4.4 Basic Electricity, Ohm's Law & Electrical Power for HVAC

5 Piping Systems, Refrigerant Lines & Fuel Gas Piping

5.1 Refrigerant Piping Sizing, Materials & Installation 5.2 Fuel Gas Piping Sizing & Installation (IRC Chapter 24) 5.3 Condensate Drain Systems & Trapping

6 System Sizing & ACCA Manual J Load Calculations

6.1 ACCA Manual J Fundamentals & Design Conditions 6.2 Envelope Loads: Conduction, Radiation & Fenestration 6.3 Infiltration, Ventilation & Internal Heat Gains

7 Duct System Design & ACCA Manual D

7.1 Airflow Principles, Static Pressure & Fan Performance 7.2 ACCA Manual D Duct Sizing & Friction Rate 7.3 Duct Materials, Installation Standards & Air Distribution

8 Heating & Cooling Equipment Operation

8.1 Heat Pump Systems & Supplemental Heating 8.2 Gas Furnaces & Combustion Systems 8.3 Air Conditioning Units, Compressors & Metering Devices

9 Mechanical Codes, Electrical Applications & Maintenance Diagnostics

9.1 Combustion Air & Venting Systems (IRC Chapter 24) 9.2 Electrical Applications for HVAC (NFPA 70 / NEC Article 440) 9.3 Preventative Maintenance, Troubleshooting & Plan Reading

10 Employment Law, Payroll Taxes & Contractor Finance

10.1 Federal & Alabama Labor Laws for HVAC Employers 10.2 Payroll, Employment Taxes & Worker Classification 10.3 Job Costing, Break-Even Analysis & Cash Flow Forecasting

11 Preventative Maintenance, Service Procedures & Commissioning

11.1 Preventative Maintenance Programs & Service Agreements 11.2 Filter, Coil & Drain Maintenance for Alabama's Humid Climate 11.3 Evacuation, Dehydration & Refrigerant Charging Procedures 11.4 Airflow Verification, Static Pressure Testing & Commissioning

12 Electrical Applications & Construction Documents

12.1 Electric Motors, Compressors & Motor Protection 12.2 Transformers, Control Circuits & Low-Voltage Wiring 12.3 Branch Circuits, Conductors, Grounding & Disconnects 12.4 Construction Documents, Specifications & Submittals

2.4 Construction Estimating, Markup & Bid Preparation

Key Takeaways Explain This Topic AI

A complete HVAC estimate is built from five direct-cost buckets - material, labor, labor burden, equipment, and subcontracts - before any overhead or profit is added.

Markup and margin are different arithmetic: markup is measured against cost, margin against selling price, and adding a 20% markup produces only a 16.7% gross margin.

To hit a target gross margin, divide total cost by (1 minus the margin), so $10,000 of cost at a 20% target margin must be sold for $12,500, a 25% markup.

Labor burden - FICA, FUTA, SUTA, workers compensation, general liability, and benefits - typically adds 25% to 45% on top of base wages and must be inside the estimate, not in overhead.

Lump sum, unit price, cost plus a fee, guaranteed maximum price, and time and material contracts shift cost risk differently, and the estimating method has to match the contract type.

Last updated: September 2026

2.4 Construction Estimating, Markup & Bid Preparation

Important

Why the exam cares : Estimating is one of the eighteen scored subject areas on the Alabama Heating and Air Conditioning examination. The questions are arithmetic, not opinion - they ask you to separate direct cost from overhead, to apply a markup correctly, or to recognize which contract type puts the cost overrun on the contractor. The single most-missed idea in the whole subject is the difference between markup and margin .

An estimate is a prediction of cost. A bid is a price. Contractors fail when they treat the two as the same number. This section walks the estimate from takeoff through the priced proposal.

Step 1: The Quantity Takeoff

The takeoff is a measured count of everything the job consumes, produced from plans, specifications, and a site survey - never from memory.

Measure in the unit you buy in. Duct board and sheet metal are taken off in square feet, refrigerant line set and flex duct in linear feet, registers and grilles in each, insulation in square feet of surface.

Take off by system, not by trip. List the condensing unit, air handler or furnace, coil, line set, pad, disconnect, whip, thermostat, filter cabinet, plenums, trunks, branches, boots, grilles, condensate line, float switch, and permits as separate lines. A single missing $180 float switch on 40 changeouts is $7,200 of unbilled cost.

Do not net out waste. Add a waste and shrink allowance - commonly 5% to 10% on sheet metal, flex, and insulation.

Record assumptions on the estimate sheet. Every assumption that later turns out to be wrong is a change order only if you wrote it down.

Step 2: The Five Direct-Cost Buckets

Bucket What it contains Common pricing source

Material Equipment, duct, fittings, refrigerant, controls, fasteners, sealants Current supplier quotes; hold quotes in writing

Labor Installer and helper hours from labor units Historic productivity, then published labor units

Labor burden Employer payroll taxes, workers compensation, liability, benefits Computed as a percentage of base wage

Equipment Lift rental, crane, brake, vacuum pump, recovery machine, truck cost Rental rate or internal ownership rate

Subcontracts Electrical, crane, structural, drywall patch, crane rigging Written sub quotes with scope attached

Everything else - office rent, estimator salary, dispatcher, advertising, insurance on the building, owner salary - is overhead and is recovered by markup, not by burying it in a labor rate.

Step 3: Labor Units and Labor Burden

A labor unit is the number of installer hours a task historically takes. Once the hours are known, the cost is hours x fully burdened hourly rate.

Labor burden is the difference between what an employee is paid and what the employee costs. For a $25.00/hour Alabama installer, a representative burden build-up looks like this:

  • Burden component Rate applied Cost per hour
  • Social Security and Medicare (FICA employer share) 7.65% $1.91
  • Federal unemployment (FUTA, net of state credit) 0.6% on the first $7,000 $0.02
  • Alabama unemployment (SUTA, $8,000 wage base) example 2.7% of the $8,000 base $0.10
  • Workers compensation (HVAC class code) example 6.2% of payroll $1.55
  • General liability allocated to payroll example 2.1% of payroll $0.52
  • Health insurance, paid time off, training, uniforms fixed dollars per hour $4.00
  • Fully burdened cost $33.10 per hour (a 32.4% burden)

A contractor who bids labor at the $25.00 base wage loses $8.10 every hour worked and will not see it until the year-end financial statement.

Step 4: Markup Is Not Margin

This is the arithmetic the exam tests. Markup % = Price − Cost Cost Margin % = Price − Cost Price \text{Markup \%} = \frac{\text{Price} - \text{Cost}}{\text{Cost}} \qquad \text{Margin \%} = \frac{\text{Price} - \text{Cost}}{\text{Price}} Markup % = Cost Price − Cost ​ Margin % = Price Price − Cost ​

Markup is measured against cost ; margin is measured against the selling price . Because price is always larger than cost, the margin percentage is always the smaller of the two numbers.

  • Applied markup Selling price on $10,000 cost Resulting gross margin
  • 10% $11,000 9.1%
  • 20% $12,000 16.7%
  • 25% $12,500 20.0%
  • 43% $14,300 30.1%
  • 50% $15,000 33.3%

To price from a target margin , do not multiply - divide: Price = Total Cost 1 − Target Margin \text{Price} = \frac{\text{Total Cost}}{1 - \text{Target Margin}} Price = 1 − Target Margin Total Cost ​

A contractor who wants a 30% gross margin on $10,000 of cost must sell at $10,000 / 0.70 = $14,286 , which is a 42.9% markup. Adding "30%" to cost yields $13,000 and a 23.1% margin - a $1,286 shortfall on one job.

Step 5: Overhead Recovery, Contingency and the Final Price

Overhead recovery is normally expressed as a percentage of direct cost or of revenue. If annual overhead is $240,000 and expected annual revenue is $1,200,000, overhead is 20% of revenue and every bid must carry it.

Contingency covers identified but unquantified risk - unknown attic access, asbestos-wrapped duct, hidden framing. It is not a substitute for a complete takeoff.

Escalation protects long-lead equipment quotes. Written supplier quotes should state a firm-price period, and the proposal should mirror it.

Bid errors : a mathematical mistake discovered before award can often be withdrawn; after award, the contractor is generally bound. Double-check extensions and unit conversions before the bid is delivered.

Step 6: Match the Estimate to the Contract Type

  • Contract type Who carries cost overrun risk Best used when
  • Lump sum (stipulated sum) Contractor Scope is fully defined by drawings and specs
  • Unit price Shared - owner pays for actual quantities Quantities are uncertain but unit work is repetitive
  • Cost plus a fee Owner Scope cannot be defined at signing, emergency work
  • Guaranteed maximum price (GMP) Contractor above the cap, owner below Owner wants open books but a ceiling
  • Time and material (T&M) Owner Service, diagnostics, and small repairs
  • Worked Example: Residential Changeout

A 3-ton gas furnace and coil changeout in Hoover:

Material : equipment $3,400, line set and fittings $260, plenum and transitions $180, thermostat $140, permit $85 = $4,065

  • Labor : two technicians, 12 hours each = 24 hours at $33.10 fully burdened = $794.40
  • Equipment : recovery machine, vacuum pump, brake allocation = $60
  • Subcontract : none
  • Total direct cost = $4,919.40

The company needs a 35% gross margin: Price = $ 4 , 919.40 1 − 0.35 = $ 4 , 919.40 0.65 = $ 7 , 568.31 \text{Price} = \frac{\$4,919.40}{1 - 0.35} = \frac{\$4,919.40}{0.65} = \$7,568.31 Price = 1 − 0.35 $4 , 919.40 ​ = 0.65 $4 , 919.40 ​ = $7 , 568.31

Rounded to $7,570 , that is a 53.8% markup on cost and a 35.0% gross margin on price. Selling at cost plus 35% would have produced $6,641 and only a 25.9% margin.