11.3 Evacuation, Dehydration & Refrigerant Charging Procedures

Alabama HVAC Contractor License Exam

Track your progress as you read

Finished sections get a check mark.

1 Alabama HACR Laws, Rules & Licensing

1.1 Alabama HACR Board Authority, Licensing Pathways & Experience Requirements 1.2 Contractor Bonding, Insurance, Fees & Annual Renewal 1.3 Permits, Local Jurisdictions, Inspections & Disciplinary Actions

2 Contractor Business, Contracts, Estimating & Alabama Lien Law

2.1 Business Organization, Risk Management & Project Administration 2.2 Construction Contracts, Change Orders & Warranties 2.3 Alabama Mechanics' Lien Law & Financial Management 2.4 Construction Estimating, Markup & Bid Preparation 2.5 Project Management, Scheduling & Field Supervision 2.6 Risk Management, Contractor Insurance & Surety Bonds

3 Safety Standards, OSHA & EPA Section 608

3.1 OSHA Construction Safety (29 CFR 1926) for HVAC Contractors 3.2 EPA Section 608 Refrigerant Regulations & Recovery Requirements 3.3 Refrigerant Management, Leak Repair Rules & A2L Transition

4 General Technical Knowledge & Thermodynamics

4.1 Principles of Heat Transfer, Temperature & Pressure 4.2 The Mechanical Refrigeration Cycle & Refrigerant Properties 4.3 Psychrometrics & Air Properties for Humid Climates 4.4 Basic Electricity, Ohm's Law & Electrical Power for HVAC

5 Piping Systems, Refrigerant Lines & Fuel Gas Piping

5.1 Refrigerant Piping Sizing, Materials & Installation 5.2 Fuel Gas Piping Sizing & Installation (IRC Chapter 24) 5.3 Condensate Drain Systems & Trapping

6 System Sizing & ACCA Manual J Load Calculations

6.1 ACCA Manual J Fundamentals & Design Conditions 6.2 Envelope Loads: Conduction, Radiation & Fenestration 6.3 Infiltration, Ventilation & Internal Heat Gains

7 Duct System Design & ACCA Manual D

7.1 Airflow Principles, Static Pressure & Fan Performance 7.2 ACCA Manual D Duct Sizing & Friction Rate 7.3 Duct Materials, Installation Standards & Air Distribution

8 Heating & Cooling Equipment Operation

8.1 Heat Pump Systems & Supplemental Heating 8.2 Gas Furnaces & Combustion Systems 8.3 Air Conditioning Units, Compressors & Metering Devices

9 Mechanical Codes, Electrical Applications & Maintenance Diagnostics

9.1 Combustion Air & Venting Systems (IRC Chapter 24) 9.2 Electrical Applications for HVAC (NFPA 70 / NEC Article 440) 9.3 Preventative Maintenance, Troubleshooting & Plan Reading

10 Employment Law, Payroll Taxes & Contractor Finance

10.1 Federal & Alabama Labor Laws for HVAC Employers 10.2 Payroll, Employment Taxes & Worker Classification 10.3 Job Costing, Break-Even Analysis & Cash Flow Forecasting

11 Preventative Maintenance, Service Procedures & Commissioning

11.1 Preventative Maintenance Programs & Service Agreements 11.2 Filter, Coil & Drain Maintenance for Alabama's Humid Climate 11.3 Evacuation, Dehydration & Refrigerant Charging Procedures 11.4 Airflow Verification, Static Pressure Testing & Commissioning

12 Electrical Applications & Construction Documents

12.1 Electric Motors, Compressors & Motor Protection 12.2 Transformers, Control Circuits & Low-Voltage Wiring 12.3 Branch Circuits, Conductors, Grounding & Disconnects 12.4 Construction Documents, Specifications & Submittals

11.3 Evacuation, Dehydration & Refrigerant Charging Procedures

Key Takeaways Explain This Topic AI

The industry standard evacuation target is 500 microns, at which water boils near minus 12 degrees Fahrenheit so residual moisture flashes to vapor and is pumped out.

A decay test distinguishes the two failure modes: a vacuum that rises and then stabilizes indicates remaining moisture, while one that rises continuously indicates a leak or an open valve.

Systems with a fixed metering device are charged by superheat; systems with a thermostatic or electronic expansion valve are charged by subcooling.

Dry nitrogen must flow through the tubing during brazing to prevent cupric oxide scale that later plugs the metering device and filter drier.

Pressure testing is performed with dry nitrogen and a regulator; oxygen, acetylene, and compressed air are never used, and refrigerant may not be vented as a leak-search gas.

Last updated: September 2026

11.3 Evacuation, Dehydration & Refrigerant Charging Procedures

Important

The three enemies inside a sealed system are moisture , non-condensables , and particulate . Moisture combines with refrigerant and oil to form acids and freezes at the metering device. Non-condensable air occupies condenser surface and raises head pressure. Particulate - usually cupric oxide from brazing without nitrogen - plugs screens and driers. Every procedure in this section exists to keep one of the three out.

Step 1: Braze With Flowing Nitrogen

When copper is heated above roughly 800 degrees Fahrenheit in the presence of air, the inside surface forms a black, flaky cupric oxide scale. It breaks loose in service and plugs the filter drier, the screen, and the metering device.

Set a nitrogen regulator to roughly 2 to 3 psig and let a slow, steady flow pass through the tubing during heating and while the joint cools.

Purge with nitrogen before applying heat so the line is not full of air when the torch is lit.

Never braze on a pressurized system, and never braze with refrigerant in the line - heated refrigerant can decompose into hydrogen fluoride and phosgene.

Remove or heat-shield Schrader cores, service valve seats, and TXV power heads.

Step 2: Pressure Test With Dry Nitrogen

Use dry nitrogen through a regulator - never a full cylinder pressure, and never oxygen or acetylene, which react violently with oil.

Test to the pressure specified by the manufacturer or the applicable code for the system, hold, and watch for decay corrected for ambient temperature change. A 10-degree ambient swing moves the gauge on its own.

Do not use refrigerant as a trace gas and vent it. Knowingly venting is a violation of the Clean Air Act venting prohibition regardless of the refrigerant class.

  • Step 3: Deep Evacuation
  • Why 500 Microns

Atmospheric pressure is about 760,000 microns . As absolute pressure falls, the boiling point of water falls with it:

  • Absolute pressure Water boils at
  • 760,000 microns (atmospheric) 212 F
  • 25,000 microns about 80 F
  • 4,600 microns 32 F
  • 1,000 microns about 1 F
  • 500 microns about -12 F

At 500 microns any liquid water left in the system is far above its boiling point at that pressure, so it flashes to vapor and the pump removes it. Pulling only to 1,000 or 2,000 microns leaves liquid water behind in a system that will never get colder than about 35 degrees at the evaporator.

Setup That Actually Reaches 500 Microns

Two-stage vacuum pump with clean oil. Change the oil after every job; contaminated oil raises the pump's blank-off pressure.

Large-diameter, short hoses. A quarter-inch charging hose is a straw. Use 3/8-inch or 1/2-inch evacuation hoses, as short as practical.

Remove the Schrader cores with core removal tools. A Schrader core alone can double evacuation time.

Evacuate from both the high and low sides so the vacuum is not drawn through a closed metering device.

Place the micron gauge at the system , as far from the pump as possible. A gauge at the pump reads the pump, not the system.

Replace the liquid line filter drier before evacuating; a drier installed after evacuation defeats the purpose.

Triple Evacuation

On a wet system - a burnout, a long open line set, or a flooded unit - break the vacuum twice with dry nitrogen. Pull to about 1,500 microns, break to a few psig with nitrogen, repeat, then pull the final vacuum to below 500 microns. The nitrogen sweeps water vapor that a single pull-down leaves clinging to the oil.

Step 4: Read the Decay Test

Isolate the system from the pump with a valve at the manifold - not by shutting the pump off - and watch the micron gauge.

  • Behavior Interpretation Action
  • Holds below 500 microns System is tight and dry Charge

Rises, then levels off at a stable value Remaining moisture boiling off Continue evacuating; consider triple evacuation

Rises continuously without leveling Leak or an open valve or core Stop; pressure test with nitrogen and find it

  • Step 5: Charge Correctly
  • Weigh In

The most accurate method whenever the factory charge and the line set length are known. Start from the nameplate charge, then add or subtract for line set length per the manufacturer's per-foot adjustment. Weigh-in is required on any system evacuated to a vacuum, and it is the only defensible method on a fixed-orifice system at low outdoor ambient.

Charge a Fixed Metering Device by Superheat

A piston or capillary tube does not regulate superheat, so the charge sets it. Total Superheat = Suction Line Temperature at the Condenser − Saturation Temperature at Suction Pressure \text{Total Superheat} = \text{Suction Line Temperature at the Condenser} - \text{Saturation Temperature at Suction Pressure} Total Superheat = Suction Line Temperature at the Condenser − Saturation Temperature at Suction Pressure

The target comes from the manufacturer's charging chart, entered with outdoor dry-bulb temperature and indoor return-air wet-bulb temperature . A high indoor wet bulb and a low outdoor dry bulb call for a high target superheat; a low indoor wet bulb and a high outdoor dry bulb call for a low one.

Worked example : R-410A, suction pressure 118 psig, saturation temperature 40 F, suction line temperature 55 F. Total superheat is 15 F. If the chart calls for 10 F at the measured conditions, the system is undercharged and refrigerant is added until superheat falls to target.

Charge a TXV or EEV System by Subcooling

An expansion valve maintains its own evaporator superheat, so superheat tells you almost nothing about charge. Subcooling does. Subcooling = Saturation Temperature at Discharge Pressure − Liquid Line Temperature \text{Subcooling} = \text{Saturation Temperature at Discharge Pressure} - \text{Liquid Line Temperature} Subcooling = Saturation Temperature at Discharge Pressure − Liquid Line Temperature

Most manufacturers target roughly 8 F to 12 F of liquid subcooling; always use the value on the data plate or in the installation instructions.

Worked example : R-410A, discharge pressure 335 psig, saturation temperature 104 F, liquid line temperature 89 F. Subcooling is 15 F against a 10 F target - the system is overcharged , and refrigerant must be recovered, never vented, until subcooling reaches target.

Warning

Do not diagnose charge on a system with an airflow problem. Low airflow across the evaporator lowers suction pressure and mimics an undercharge. Verify the filter, coil, blower wheel, and total external static pressure before touching the gauges, or you will chase an airflow fault by adding refrigerant and end up with a flooded compressor.