Study guide

1.4 Trade Math II: Fractions, Offsets, Areas & Heat Calculations

Alabama Journeyman Plumber Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Alabama Law, General Regulations, Trade Math, Tools & Safety

1.1 Alabama Exam Format, Licensing Law & Board Rules 1.2 IPC Chapter 3 General Regulations: Protection, Sleeves, Trenching & Structural Safety 1.3 Trade Math I: Pressure, Head, Fall, Volume & Expansion 1.4 Trade Math II: Fractions, Offsets, Areas & Heat Calculations 1.5 Plumbing Tools: Layout, Cutting, Joining, Threading & Test Equipment 1.6 Jobsite Safety: Trenches, Ladders, Confined Spaces, Hot Work & PPE

2 Chapter 2: Plumbing Fixtures, Fittings & Clearances

2.1 Minimum Plumbing Facilities, Fixture Clearances & Accessibility 2.2 Fixture Materials, Prohibited Fixtures, Overflows, Waste Outlets & Fixture Setting 2.3 Flushing Devices, Water Conservation & Temperature-Limiting Controls

3 Chapter 3: Water Supply, Distribution, Backflow & Water Heaters

3.1 Water Service & Distribution Sizing: WSFU, Demand, Pressure & Friction 3.2 Water Piping Materials, Joints, Valves, Supports & Disinfection 3.3 Cross-Connection Control & Backflow Prevention (IPC 608 & 312.10) 3.4 Water Heaters: Installation, Relief Valves, Pans & Thermal Expansion

4 Chapter 4: Sanitary Drainage Systems & DWV Sizing

4.1 Drainage Fixture Units & Sizing Branches, Stacks and Building Drains 4.2 Drainage Slopes, Building Drain & Sewer Rules, Offsets and Backwater Valves 4.3 DWV Materials, Fittings, Joints, Supports & Underground Installation 4.4 Indirect Waste, Special Waste, Sumps and Sewage Ejectors

5 Chapter 5: Traps, Cleanouts, Interceptors & Separators

5.1 Fixture Traps, Trap Seals, Prohibited Traps & Trap Seal Protection 5.2 Cleanouts: Required Locations, Size, Arrangement, Clearance & Access 5.3 Grease Interceptors, Oil Separators & Other Interceptors (IPC 1003)

6 Chapter 6: Vents and Venting Methods

6.1 Vent Purpose, Vent Stacks, Connections, Terminals & Vent Sizing 6.2 Fixture Vents, Individual Vents, Common Vents & Wet Venting 6.3 Circuit Vents, Combination Waste & Vent, Island, Waste Stack & Single-Stack Venting 6.4 Air Admittance Valves: Standards, Where Permitted, Location & Prohibitions

7 Chapter 7: Plan Reading, Sizing Practice, Testing & Fuel Gas

7.1 Reading Plumbing Drawings, Isometrics, Symbols & Schedules 7.2 Plan-Based Sizing Practice: Branches, Stacks, Building Drain, Vents & Water 7.3 Inspections and Tests: DWV, Water, Sewers, Storm, Shower Pans & Backflow 7.4 Fuel Gas Basics, Combustion Air, Venting & Alabama Gas Fitting Scope

8 Chapter 8: Roof Drain & Storm Drainage Systems

8.1 Roof Drains, Rainfall Rates & Storm Drain Sizing (IPC 1101–1106) 8.2 Secondary (Emergency) Roof Drainage, Scuppers, Controlled Flow, Subsoil Drains & Storm Sumps

1.4 Trade Math II: Fractions, Offsets, Areas & Heat Calculations

Key Takeaways Explain This Topic AI

For a simple offset, travel equals set times 1.414 for 45-degree fittings, 1.155 for 60-degree, 2.613 for 22-1/2-degree and 5.126 for 11-1/4-degree fittings.

In a rolling offset, the true offset is the square root of roll squared plus rise squared, so a 9-inch roll with a 12-inch rise gives a 15-inch true offset.

Circle area is 0.7854 times diameter squared, so doubling a pipe's diameter gives four times the flow area.

Heat added to water in Btu equals gallons times 8.34 times the temperature rise in degrees Fahrenheit.

Slopes of 1/4, 1/8 and 1/16 inch per foot equal grades of about 2.08%, 1.04% and 0.52%.

Last updated: October 2026

Why this section matters

The second half of the Trade Math blueprint covers piping geometry and quick conversions. These are the skills a journeyman uses to cut a 45-degree offset, compare pipe capacities, or check a water heater's recovery. Every method below works with a four-function calculator. Where a square root is needed, the numbers are chosen to come out even, or you can estimate.

Fractions, decimals and feet

Rulers read in sixteenths, but calculators work in decimals.

  • Fraction Decimal Fraction Decimal
  • 1/16 0.0625 9/16 0.5625
  • 1/8 0.125 5/8 0.625
  • 3/16 0.1875 11/16 0.6875
  • 1/4 0.25 3/4 0.75
  • 5/16 0.3125 13/16 0.8125
  • 3/8 0.375 7/8 0.875
  • 7/16 0.4375 15/16 0.9375
  • 1/2 0.5 1 1.0

Decimal inches to sixteenths: multiply the decimal part by 16 and round. For example, 0.45 × 16 = 7.2 0.45 \times 16 = 7.2 0.45 × 16 = 7.2 , which rounds to 7/16.

Inches to decimal feet: divide by 12. So 8 inches is 0.67 foot, and 15 inches is 1.25 feet.

Percent grade: divide the slope in inches per foot by 12, then multiply by 100. That gives about 2.08% for 1/4 inch per foot, 1.04% for 1/8 and 0.52% for 1/16.

Areas, circumference and capacity ratios A = 0.7854 × d 2 C = 3.1416 × d A = 0.7854 \times d^2 \qquad C = 3.1416 \times d A = 0.7854 × d 2 C = 3.1416 × d

A pipe's flow area grows with the square of its diameter:

A 4-inch pipe has ( 4 ÷ 2 ) 2 = 4 (4 \div 2)^2 = 4 ( 4 ÷ 2 ) 2 = 4 times the area of a 2-inch pipe.

A 3-inch pipe has ( 3 ÷ 1.5 ) 2 = 4 (3 \div 1.5)^2 = 4 ( 3 ÷ 1.5 ) 2 = 4 times the area of a 1-1/2-inch pipe.

It takes four 2-inch pipes to equal the area of one 4-inch pipe, not two.

Circumference shows up in storm drainage too. IPC 1106.5 and 1108.3 require a scupper to be at least as wide as the circumference of the roof drain it replaces. For a 4-inch drain, that is 3.1416 × 4 ≈ 12.6 3.1416 \times 4 \approx 12.6 3.1416 × 4 ≈ 12.6 inches (see section 8.2).

Water velocity in a pipe: v ( ft/s ) ≈ 0.4085 × Q ( gpm ) ÷ d 2 v\ (\text{ft/s}) \approx 0.4085 \times Q\ (\text{gpm}) \div d^2 v ( ft/s ) ≈ 0.4085 × Q ( gpm ) ÷ d 2 , with d d d the inside diameter in inches. For example, 20 gpm through a 1-inch pipe moves at about 8.2 feet per second.

Simple offsets

An offset moves a pipe line sideways and returns it to a parallel path with two equal fittings. Three measurements describe it:

Set (offset): the distance between the centerlines of the two parallel runs.

Travel: the center-to-center length of the angled piece.

Run (advance): the distance gained along the original direction while making the offset. Travel = Set × travel multiplier Run = Set × run multiplier \text{Travel} = \text{Set} \times \text{travel multiplier} \qquad \text{Run} = \text{Set} \times \text{run multiplier} Travel = Set × travel multiplier Run = Set × run multiplier

  • Fitting angle Travel multiplier Run multiplier
  • 60° 1.155 0.577
  • 45° 1.414 1.000
  • 30° 2.000 1.732
  • 22-1/2° 2.613 2.414
  • 11-1/4° 5.126 5.027
  • 5-5/8° 10.20 10.15

These multipliers are trigonometry. The travel multiplier is 1 ÷ sin ⁡ ( angle ) 1 \div \sin(\text{angle}) 1 ÷ sin ( angle ) and the run multiplier is 1 ÷ tan ⁡ ( angle ) 1 \div \tan(\text{angle}) 1 ÷ tan ( angle ) .

Example. A 45-degree offset needs an 18-inch set. Travel is 18 × 1.414 = 25.45 18 \times 1.414 = 25.45 18 × 1.414 = 25.45 inches. Since 0.45 × 16 = 7.2 0.45 \times 16 = 7.2 0.45 × 16 = 7.2 , that is about 25-7/16 inches center to center. Run equals set, 18 inches.

From center-to-center to cut length

Fittings take up length. The take-off of a fitting is its center-to-end dimension minus the depth the pipe goes into the socket. Use the manufacturer's dimension sheet, because take-offs vary by material and pattern. Cut length = Center-to-center − take-off of fitting 1 − take-off of fitting 2 \text{Cut length} = \text{Center-to-center} - \text{take-off of fitting 1} - \text{take-off of fitting 2} Cut length = Center-to-center − take-off of fitting 1 − take-off of fitting 2

Measurement terms used on drawings and in the math text:

Center to center: between fitting centerlines.

End to end: the overall pipe length.

End to center: from a pipe end to the centerline of a fitting.

Face to face: between the faces of fittings or flanges.

Rolling offsets

A rolling offset moves the pipe both sideways ( roll ) and up or down ( rise ) at once. Solve it in two steps:

True offset = roll 2 + rise 2 = \sqrt{\text{roll}^2 + \text{rise}^2} = roll 2 + rise 2 ​ (the Pythagorean theorem).

Travel = = = true offset × the multiplier for the fitting angle.

Example. Roll 9 inches, rise 12 inches. True offset = 81 + 144 = 225 = 15 = \sqrt{81 + 144} = \sqrt{225} = 15 = 81 + 144 ​ = 225 ​ = 15 inches. With 45-degree fittings, travel = 15 × 1.414 = 21.2 = 15 \times 1.414 = 21.2 = 15 × 1.414 = 21.2 inches.

Remember the 3-4-5 right triangle and its multiples (6-8-10, 9-12-15, 12-16-20). Plumbers use it to square a layout without a calculator.

Temperatures and heat ° F = ( ° C × 1.8 ) + 32 ° C = ( ° F − 32 ) ÷ 1.8 °F = (°C \times 1.8) + 32 \qquad °C = (°F - 32) \div 1.8 ° F = ( ° C × 1.8 ) + 32 ° C = ( ° F − 32 ) ÷ 1.8

Useful pairs: 49°C = 120°F (the IPC 412.3 shower limit), 43°C = 110°F (the 607.1.2 tempered water limit), 60°C = 140°F, and 99°C = 210°F (the 504.5 relief temperature).

Btu formula. One Btu raises 1 pound of water by 1°F. Btu = gallons × 8.34 × Δ T \text{Btu} = \text{gallons} \times 8.34 \times \Delta T Btu = gallons × 8.34 × Δ T

Recovery example. A gas water heater has a 40,000 Btu/h input at 76% efficiency, so its output is 40,000 × 0.76 = 30,400 40{,}000 \times 0.76 = 30{,}400 40 , 000 × 0.76 = 30 , 400 Btu/h. Raising incoming 50°F water to 140°F is a 90°F rise. Recovery is 30,400 ÷ ( 8.34 × 90 ) = 30,400 ÷ 750.6 ≈ 40.5 30{,}400 \div (8.34 \times 90) = 30{,}400 \div 750.6 \approx 40.5 30 , 400 ÷ ( 8.34 × 90 ) = 30 , 400 ÷ 750.6 ≈ 40.5 gallons per hour.

Other conversions

  • Convert Factor
  • Cubic feet to gallons × 7.48
  • Cubic inches to gallons ÷ 231
  • Cubic inches in a cubic foot 1,728
  • Inches of water column to psi × 0.036 (so 7 in w.c. ≈ 0.25 psi)
  • Psi to feet of head × 2.31
  • Natural gas Btu/h to cubic feet per hour ÷ about 1,000
  • Exam traps

Wrong multiplier: 1.414 is for 45° fittings. A 60° offset uses 1.155, and 22-1/2° uses 2.613.

Adding roll and rise: the true offset of a rolling offset is the square root of the sum of the squares, not the sum.

Diameter vs. area: doubling the diameter quadruples the area.

Btu problems: use the heater's output (input × efficiency), not its nameplate input, for recovery.