Study guide

Creating Inspection and Test Plans (ITPs)

AMPP CIP Level 2 Certified Coatings Inspector

Track your progress as you read

Finished sections get a check mark.

1 Introduction & Exam Overview

CIP Level 2 Exam Facts and Format Prerequisites, Certification Path, and Renewal July 2026 Blueprint and Study Strategy

2 Safety

Process Safety: Equipment and Job-Site Hazards Safety Issues for Specialized Coatings and Prep Methods Environmental Safety Regulations and Regulatory Layers Containment, Waste, VOC, Silica, and Hexavalent Chromium

3 Inspection Planning

Evaluating and Applying Client Written Expectations Purpose and Cost Justification of Inspection Creating Inspection and Test Plans (ITPs) Supporting Job Specifications

4 Inspection Activities & Standards

De Facto, National, and International Standards CIP Level 2 Scope vs Level 1 Responsibilities Verifying Level 1 Work and Applying NACE/AMPP Standards

5 Corrosion Causes

Corrosion Types: General, Localized, Crevice, Flow-Assisted Corrosion Cell and Electrochemical Processes Galvanic Corrosion and Dissimilar Metals

6 Corrosion Effect & Control

Substrate Corrosion Rates, Influencing Factors, and Mitigation Cathodic Protection Systems and Effects on Coatings

7 Environmental Conditions & Inspection

Environmental Requirements and Inspection Concerns Humidity Effects on Corrosion Rates and Coating Risk Dehumidification Systems: Desiccant, Refrigerant, and Heaters Enclosures, Air Movement, and Advanced Environmental Instrumentation

8 Surface Preparation Methods

Prep Methods for Nonferrous, Wood, Concrete, and Polymeric Substrates Surface Contaminants and Acid Cleaning Pickling, Passivation, and Rinse Verification Waterjetting Methods and Removable Materials

9 Surface Prep Equipment & Standards

Concrete Surface Preparation and Standards Abrasive Types, Mixes, and Inspection Considerations Centrifugal Blast Cleaning and Portable/Remote Systems Waterjetting and Centrifugal Blast Standards AB-1/2/3 Media Standards and Special Substrates

10 Coating Application Equipment

Thermal, Electrostatic, and Polyester Spray Applications Plural-Component Systems and Specialty Coating Application Convertible vs Non-Convertible Curing and Polymerization

11 Specialty Coatings & Products

Powder Coatings and Specialized Coating Types Thick-Barrier Linings: Installation and Use Coal-Tar Enamel, Asphalt, and Tape Coatings Maintenance Coating Considerations

12 Pipeline Coatings & Hot-Dip Galvanizing

Hot-Dip Galvanizing Application Process Fusion-Bonded Epoxy (FBE) Pipeline Coating Multi-Layer Polyolefin (3LPE/3LPP) Pipeline Coatings Pipeline Field Joints and Mainline Repair Products Pipeline Coating Importance and Integrity Failure Consequences Concrete on Pipelines and Concrete Coating Standards Concrete Coating Requirements and Cure Verification

13 Coating Inspection: Assessing

Coating Surveys of Existing Systems Coating Defects, Failures, and Detection Criteria Differentiating Adhesion Testing Methods HDG Defects; Nonferrous and Concrete Coating Inspection

14 Coating Inspection: Verification

Instrument Inspections: Verification vs Calibration Concrete Coating Thickness and Destructive Tests Eddy Current and Ultrasonic DFT Methods Cathodic Disbondment and Specialized Lab Testing

15 Documentation

Level 1 Report Review and Failure Documentation for Level 3 Documenting Specialty Coatings and Developing Reports Electronic Reporting, Data Storage, and Retention Maintenance Coating Surveys and Standards Bodies Product Data Sheets and Hot-Dip Galvanizing Standards

16 Communications & Teamwork

Certified Inspector Role and CIP Level 2 Limits Owner, Contractor, and Inspector Responsibilities Pre-Job Conference and Coating Condition Assessment Surveyor Defensive Behavior and Conflict Resolution Communication

17 Ethics

Attestation and Ethics of the AMPP-Certified Inspector Addressing and Analyzing Ethical Dilemmas Positive Suggestions That Improve Job Flow and Quality

Creating Inspection and Test Plans (ITPs)

Key Takeaways Explain This Topic AI

An inspection and test plan (ITP)—also called an inspection plan or test plan—is the controlling matrix of activities, standard/spec references, acceptance criteria, hold/witness/review points, responsible parties, and records for the coating job.

Hold points stop work until authorized verification; witness points require notification and optional observation; review points are document or record checks without stopping production in the field.

A complete ITP sequences surface preparation → coating application → cure verification → final inspection/acceptance so each gate uses the right criteria and records.

CIP Level 2 builds or critically reviews ITPs; CIP Level 1 primarily executes the hold and witness points written into an already-approved plan.

Every ITP line should answer: what is checked, to which standard or spec clause, what passes, who signs, and which form or attachment becomes the quality record.

Last updated: August 2026

Creating Inspection and Test Plans (ITPs)

Quick Answer: An inspection and test plan (ITP) —also called an inspection plan or test plan —is the living matrix that tells the project what to inspect, to which standard/spec , what passes , who must be present , and which record is filed . CIP Level 2 creates or reviews ITPs; CIP Level 1 mainly executes the hold and witness points already written into the approved plan.

Inspection Plan, Test Plan, and ITP Terminology

On the CIP Level 2 exam and in industry practice you will see three near-synonyms:

  • Inspection plan — emphasizes when and how visual and instrumental inspections occur
  • Test plan — emphasizes quantitative tests (DFT, adhesion, holiday, soluble salts, cure)
  • Inspection and test plan (ITP) — the combined document used on most industrial coating projects

Treat them as the same deliverable unless a client procedure splits “inspection” from “laboratory testing.” What matters is content: a sequenced list of quality activities with acceptance criteria and sign-off authority. If a bid package says “submit ITP for approval 14 days before mobilization,” that is your inspection plan / test plan package—not a verbal agreement at the gate.

Structure of an ITP

A usable ITP is a table (often with a cover sheet for revision control). Minimum columns:

  • Column Purpose
  • Activity / step What work or verification is occurring (e.g., “verify blast cleanliness”)
  • Standard / spec reference Project spec clause, AMPP/NACE/SSPC/ISO/ASTM number, or PDS section
  • Acceptance criteria Pass/fail numbers or visual grades (e.g., SSPC-SP 10; 3–4 mil profile; DFT per SSPC-PA 2)
  • Inspection point type Hold (H), Witness (W), Review (R)—sometimes Surveillance (S)
  • Responsible party Applicator QC, third-party inspector, owner QA, NDE tech, manufacturer
  • Records / forms DIR line item, profile log, DFT spreadsheet, holiday report, photo ID
  • Timing / frequency Each area, each shift, each lot, percent of joints, before next coat

Optional but valuable columns: equipment list (gauge models), calibration reference, environmental limits, and cross-references to method statements. Every row should stand alone: a new Level 1 inspector should be able to execute the row without guessing.

Cover Sheet and Revision Control

The ITP is a controlled document. The cover sheet typically lists project name, coating systems, revision number and date, approvers (contractor QC, owner QA, inspector), and a revision history. Field copies must match the approved revision. Handwritten “temporary” hold-point deletions on a printout are not a valid ITP change—those require a formal revision or a written client directive linked to the revision log.

Hold Points vs Witness Points vs Review Points

These three inspection-point types are core Level 2 vocabulary:

Type Code (typical) Work may proceed if inspector is absent? Primary use

Hold point H No — work stops until authorized sign-off Critical irreversible steps (prep grade before prime; holiday test before immersion fill; final acceptance)

Witness point W Yes , if required notice was given and the ITP allows proceeding Observation of process (mixing, stripe coat technique, equipment setup)

Review point R Yes — documents are checked later or in parallel Batch certificates, calibration certificates, DIR packages, cure logs

Hold points protect the owner from irreversible progress over a defective condition. Witness points balance oversight with schedule when presence is valuable but absence after notice should not freeze the job. Review points catch paperwork and certification gaps without standing on the scaffold for every record. Mislabeling a true hold as a witness is a common contractor pressure tactic; Level 2 inspectors defend the classification based on consequence of failure, not schedule convenience.

Some owners add surveillance (random observation without formal notification). If used, define it in the ITP so “we thought you would just show up” is not the notification system.

Sequencing: Prep → Application → Cure → Final

A coherent inspection plan follows the physical work flow. Do not cluster all testing at the end.

1. Surface Preparation Phase

Typical ITP activities:

  • Pre-blast condition and grease/oil removal verification
  • Abrasive cleanliness / chloride on media when specified
  • Ambient and substrate checks before blast (when required)
  • Cleanliness grade vs specified SP/ISO grade (hold)
  • Profile measurement per ASTM D4417 or project method (hold or witness)
  • Soluble salt / dust / water-break tests as specified (often hold on immersion steel)
  • 2. Application Phase
  • Material identity, batch numbers, mix ratio, induction and pot life
  • Stripe coat verification on welds and edges
  • Ambient conditions and dew-point margin during spray
  • Wet-film thickness checks during application
  • Intercoat cleanliness and recoat-window compliance before next coat
  • Dry-film thickness per SSPC-PA 2 or project sampling plan after each coat or as specified
  • 3. Cure Phase
  • Cure schedule vs PDS temperature/time tables
  • Hardness, MEK rub, or other cure tests when specified
  • Recoat or service-entry restrictions
  • 4. Final Inspection and Acceptance
  • Final DFT survey and visual defect survey
  • Holiday/discontinuity testing where required (often hold for linings)
  • Adhesion testing sample plan when specified (destructive—plan locations)
  • Punch list, NCR closeout, and final acceptance package

If the ITP jumps from “blast” to “final DFT” with no ambient, WFT, or intercoat rows, it is incomplete—even if the cover looks professional.

Example ITP Excerpt (Immersion Tank Lining)

Step Activity Reference Acceptance criteria Point Responsible Record

1 Pre-clean / degrease Project Spec §3.1; SSPC-SP 1 No visible oil/grease; water-break free if specified W Applicator QC + Inspector DIR + photos

2 Abrasive blast to near-white Spec §3.2; SSPC-SP 10 / NACE No. 2 Visual match to standard photos; no mill scale H Inspector DIR cleanliness log

3 Profile measurement ASTM D4417 Method C (or as specified) 2.5–4.0 mils (example range—use project numbers) H Inspector Profile log

4 Soluble salts Spec §3.4; Bresle method as specified ≤ project max µg/cm² H Inspector Salt test form

5 Primer application & WFT PDS + Spec §4 WFT within calculated range; stripe coat complete W Applicator QC; Inspector witnesses Batch + WFT log

6 DFT after primer SSPC-PA 2; Spec §5 Meets PA 2 sampling and min/max H Inspector DFT sheet

7 Intermediate / finish coats Spec + PDS recoat window Within recoat window; DFT cumulative OK H/W as listed Inspector DFT + ambient log

8 Cure verification PDS cure table Min time/temp met before holiday test R Applicator QC; Inspector reviews Cure log

9 Holiday detection Spec §6; NACE SP0188 or project method No holidays at set voltage; repairs retested H Inspector Holiday report

10 Final acceptance package Contract QA procedure All H points signed; NCRs closed H / R Owner QA + Inspector Final dossier

Use project-specific numbers from the actual specification—never invent acceptance criteria that contradict the client’s documents. The table above is a teaching skeleton, not a universal tank standard.

CIP Level 2 Role: Build and Review, Not Only Execute

  • Role CIP Level 1 (typical) CIP Level 2 (exam expectation)
  • ITP creation Rarely authors the full ITP Can draft or co-author ITP content from spec + standards
  • ITP review Follows approved points Critiques missing hold points, wrong standards, weak criteria

Field execution Performs measurements at H/W points Also verifies Level 1 work quality and documentation completeness

Change control Reports conflicts upward Recommends ITP revisions when scope, product, or risk changes

Level 2 review questions to ask of any proposed ITP:

Does every irreversible step have an appropriate hold or strong witness ?

Are acceptance criteria measurable and tied to a standard/spec/PDS ?

Is sequencing logical through prep → application → cure → final ?

Are records named so the final dossier can be assembled without hunting?

Are responsibilities realistic (who actually has the instrument and authority)?

Do immersion, buried, or high-criticality areas get denser testing than mild atmospheric steel?

If the answer to any of these is no, Level 2 documents the gap and proposes a revision before production—not after a failure.

Practical Tips for Creating ITPs

Start from the coating system schedule and walk the process in time order.

Pull test methods from the project specification first; use PDS limits where the spec points to the manufacturer.

Align DFT rules with SSPC-PA 2 (or the project’s stated alternative) so sampling is not improvised.

Pair each instrumented test with a calibration review point so gauges are defensible.

Keep language objective: “Verify DFT per SSPC-PA 2,” not “Ensure good thickness.”

After owner approval, train Level 1 staff on the live revision and place controlled copies at the job shack.

A strong ITP is the difference between inspection as a random presence and inspection as a planned quality system. CIP Level 2 owns that planning skill.