10.2 Addressing Conflict and the Thomas-Kilmann Model

APM Project Management Qualification PMQ

Track your progress as you read

Finished sections get a check mark.

1 Introduction & Exam Overview

1.1 Current Exam Facts 1.2 Exam Format & Question Types 1.3 How to Study for APM PMQ

2 Life Cycles

2.1 Linear Life Cycles and Why Work Is Phased 2.2 Iterative and Hybrid Life Cycles 2.3 Project Life Cycles and Extended Life Cycles 2.4 Choosing a Life Cycle: Context, Culture, Strengths and Limitations

3 Governance Arrangements

3.1 Functional, Matrix and Projectised Structures 3.2 Governance Frameworks, Policies and Delegated Responsibility 3.3 Life-Cycle Impact on Governance and Limits of Financial Authority 3.4 Project Roles and Responsibilities 3.5 Project Manager and Project Sponsor Through the Life Cycle 3.6 Linking Projects to Organisational Objectives

4 Sustainability

4.1 Sustainability Responsibilities, Principles and Impact 4.2 Monitoring and Reporting Sustainability Measures

5 Business Case

5.1 Business Case Fundamentals and Analysis Tools 5.2 The Business Case as Baseline and Reviewing Change

6 Procurement

6.1 Procurement Strategy: Purpose and Contents 6.2 Supplier Selection and Negotiation 6.3 Features of Different Contractual Relationships 6.4 Supplier Reimbursement Methods

7 Reviews & Assurance

7.1 Reviews, Decision Gates, Benefits Reviews and Audits 7.2 What Gets Reported and Informing Decisions 7.3 Why Activities Are Re-Planned After a Review 7.4 Project Assurance

8 Transition & Benefits Management

8.1 Transition Requirements and Business-as-Usual Readiness 8.2 Knowledge Transfer and Agreeing the Transition Plan 8.3 Benefits Management: Identification to Realisation 8.4 Aligning and Communicating Benefits

9 Stakeholder Engagement & Communication

9.1 Stakeholder Analysis, Influence and Engagement 9.2 The Communication Management Plan and Its Benefits 9.3 Managing Stakeholder Expectations 9.4 Communication Methods and Tailoring the Message 9.5 Factors That Help and Hinder Communication

10 Conflict Resolution

10.1 Sources and Impacts of Conflict 10.2 Addressing Conflict and the Thomas-Kilmann Model

11 Leadership

11.1 Leadership, Motivation and Team Performance 11.2 Changing Leadership Styles for the Situation 11.3 Coaching, Mentoring and Emotional Intelligence

12 Team Management

12.1 Team Development Stages and Models 12.2 Characteristics and Benefits of Effective Teams 12.3 Leading Virtual and Hybrid Teams

13 Diversity & Inclusion

13.1 Diversity Characteristics and the Equality Act 13.2 Incorporating Diversity and Diverse Thinking 13.3 Conscious and Unconscious Bias and Fair Treatment

14 Ethics, Compliance & Professionalism

14.1 Continuing Professional Development and Competence 14.2 Sources of Specialist Advice and Standards 14.3 The Legal and Regulatory Landscape

15 Requirements & Solutions

15.1 Establishing Scope Through Requirements Management 15.2 Managing Scope Through Configuration Management 15.3 Solutions Development and Prioritisation

16 Quality Management

16.1 Quality Planning, Indicators and the Business Case 16.2 Quality Control and Success Criteria

17 Integrated Planning

17.1 The Integrated Project Management Plan: Format and Contents 17.2 Why an Integrated Plan Matters

18 Schedule Management

18.1 Defining Scope and Breakdown Structures 18.2 Dependencies and What Drives the Schedule 18.3 Re-Estimating and Schedule Optimisation

19 Resource Management

19.1 Determining Resource Requirements and Availability 19.2 Organisational Breakdown Structure and RACI 19.3 Categorising and Allocating Resources 19.4 Resource Smoothing and Resource Levelling

20 Budgeting & Cost Control

20.1 Creating a Budget and Cost Types 20.2 Earned Value and Cost Forecasting 20.3 Monitoring and Reporting Financial Performance 20.4 Closing Down Project Finances

21 Risk & Issue Management

21.1 Benefits of Risk and Issue Management and Contingency Planning 21.2 The Risk and Issue Management Processes 21.3 Proactive and Reactive Risk Responses 21.4 Governance in Risk and Issue Management

22 Change Control

22.1 The Change Control Process and Its Stages 22.2 What a Change Request Must Capture 22.3 Assessing Options and the Impact of a Change 22.4 Recommending Decisions and Updating Plans

10.2 Addressing Conflict and the Thomas-Kilmann Model

Key Takeaways Explain This Topic AI

The Thomas-Kilmann model places five conflict modes on axes of assertiveness and cooperativeness: competing, collaborating, compromising, avoiding, and accommodating.

Collaborating produces the best joint outcome but costs the most time, so it fits high-stakes issues where a durable solution matters.

Competing is appropriate where safety, legality, or compliance is at stake and speed matters more than consensus.

Avoiding is a legitimate choice for trivial issues or when emotions need time to cool — but not for material risks.

No mode is universally right: the examinable skill is justifying the mode against the situation, stakes, time available, and relationship.

Last updated: August 2026

Outcome 11c asks you to know ways in which conflict can be addressed in different situations , and names the Thomas-Kilmann Conflict Mode Instrument explicitly. A named model in the syllabus means you should be able to name all five modes and, more importantly, say when each is appropriate — the marks sit in matching the mode to the situation, not in reciting the grid.

Ways conflict can be addressed

Addressing conflict is a process , not a single conversation. Practical steps for the project manager:

Recognise early — delayed attention often converts task conflict into relationship conflict.

Diagnose source and stakeholders — interests, power, urgency, and what "winning" means to each party.

Choose mode and forum — private 1:1, facilitated workshop, joint problem-solving, or formal escalation.

Separate people from problem where possible — reframe to interests and project objectives.

Generate options — expand the pie before dividing it (scope trade-offs, sequence change, extra resource, temporary workaround).

Agree decision and record — who decided what, why, and any residual risk.

Follow up — check behaviour and delivery after the agreement; repair trust if needed.

Escalate when authority, safety, ethics, or business-case impact exceeds the PM’s remit — with options, not only problems.

Other organisational mechanisms (mediation, commercial dispute procedures, HR processes, assurance reviews) sit alongside the interpersonal modes below when stakes or formality rise.

Thomas-Kilmann Conflict Mode Instrument (TKI)

The Thomas-Kilmann Conflict Mode Instrument describes five conflict-handling modes along two dimensions:

Assertiveness — extent to which you pursue your own concerns.

Cooperativeness — extent to which you pursue the other party’s concerns.

  • Mode Assertiveness Cooperativeness Essence
  • Competing High Low Pursue own position; win-lose
  • Collaborating High High Seek integrative solution that satisfies both
  • Compromising Medium Medium Partial satisfaction; split the difference
  • Avoiding Low Low Sidestep, postpone, or withdraw
  • Accommodating Low High Yield to the other party’s concerns

No mode is universally "best." PMQ marks reward fit to situation .

When-to-use table (examinable judgement)

Mode When it is often appropriate When it is often weak

Competing Quick decisive action needed; safety/compliance non-negotiable; unpopular but necessary decisions; defending against exploitation Complex multi-party problems needing buy-in; long-term partnership damage if overused

Collaborating Both stakes and relationships matter; learning needed; root causes complex; time available for joint design True zero-sum emergencies with no time; one party acting in bad faith

Compromising Moderate importance; time-limited; temporary settlement; parties of equal power; collaboration attempted and stalled Critical safety/quality where half-measures fail; chronic use that leaves root causes unsolved

Avoiding Issue trivial; need to cool emotions; no power to change outcome now; more information coming soon Chronic issues that grow; safety/ethics concerns; avoidance used to dodge accountability

Accommodating You are wrong or outranked on the point; preserving harmony more valuable than this issue; building credit for later; low personal stake Pattern of always yielding that creates resentment or bad decisions; critical project objectives sacrificed

Mode deep dives with project flavour

Competing. Useful when a sponsor or PM must stop unsafe work, enforce a regulatory hold, or protect a non-negotiable constraint. Tone still matters: firm on the decision, respectful of people. Over-competing creates fear and silence — risks stop being reported.

Collaborating. The gold standard when two stakeholders both hold legitimate needs (for example operations uptime vs release window). Process: share interests, invent options, use objective criteria (benefits, risk, cost of delay). Takes time and facilitation skill; often the best long-term mode for matrix conflicts.

Compromising. Each side gives something (for example half the features this release, half next; shared specialist 50/50 for two weeks). Fast and pragmatic, but repeated compromise can produce mediocre solutions nobody fully owns. Use as a bridge, then plan a better structural fix.

Avoiding. Legitimate for minor preference clashes or when a public argument would harm a sensitive negotiation. Dangerous when used for known critical-path blockers or ethical issues. If you avoid, state when you will return to the issue.

Accommodating. Yield on a reporting format the PMO prefers if it costs little and builds goodwill. Do not accommodate on safety, legal compliance, or knowingly false status reporting.

Worked scenarios (PMQ style)

Scenario A — schedule vs quality. Testing leads want two more weeks; marketing has booked a launch. Source: schedule/priority . Impact could be constructive if it forces a risk-based release decision. Mode: start with collaborating (minimum viable release criteria, phased launch, extra test resource options). If a legal non-compliance risk remains, compete to stop unsafe go-live and escalate to the sponsor/board.

Scenario B — two specialists, one design. Both designs are viable; personality heat is rising. Source: technical plus personality . Mode: collaborate with decision criteria (lifecycle cost, maintainability, risk); if time-boxed and still stuck, compromise on a pilot of one approach with a review gate; PM facilitates and records the decision.

Scenario C — supplier variation dispute. Source: commercial . Early hard competing on every point may destroy delivery relationship; pure accommodating may bust the budget. Use evidence-based negotiation: interests, contract facts, and where needed formal change control and escalation — modes shift by issue (collaborate on programme recovery; compete on clear contractual breach).

Scenario D — trivial tool preference. Team argue over which chat channel to use. Source: low-stakes style . Avoid prolonged debate or accommodate majority preference quickly; save collaborative energy for benefits-critical conflicts.

Putting conflict resolution together for exam answers

When a scenario shows friction:

Name sources (often more than one).

State positive and/or negative impacts if the conflict continues as-is.

Select a Thomas-Kilmann mode (or sequence of modes) and justify with stakes, time, relationships, and non-negotiables.

Describe process steps (diagnose, facilitate, options, decide, record, follow up).

Escalate with options when authority or business justification is at risk.

That chain matches how APM PMQ rewards applied conflict management rather than a single memorised "always collaborate" slogan.