Study guide

3.3 Commercial / Non-Dwelling Demand Factors

Arkansas Journeyman Electrician Exam Study Guide 2026

Track your progress as you read

Finished sections get a check mark.

1 Introduction & Arkansas Exam Overview

1.1 Current Exam Facts 1.2 Arkansas Licensing Pathway & Board Process 1.3 Open-Book Rules & Allowed References 1.4 NEC 2023 Navigation & Lookup Strategy

2 Electrical Theory & Trade Calculations

2.1 Ohm's Law, Power, and Basic Circuits 2.2 Series, Parallel, and Combination Circuits 2.3 Voltage Drop Calculations 2.4 Box Fill Calculations (314.16)

3 Load Calculations (Article 220)

3.1 Standard Dwelling Unit Load Calculations 3.2 Optional Dwelling & Multifamily Demand 3.3 Commercial / Non-Dwelling Demand Factors 3.4 Ampacity Adjustment & Correction (310.15)

4 Grounding Electrode Systems

4.1 Grounding Electrode Types & Installation 4.2 Grounding Electrode Conductor Sizing (250.66) 4.3 Main Bonding Jumper & Service Bonding

5 Equipment Grounding & Bonding

5.1 Equipment Grounding Conductors (250.122) 5.2 Bonding Raceways, Enclosures & Equipment 5.3 Separately Derived Systems Grounding

6 Services & Service Equipment

6.1 Service Entrance Conductors & Clearances 6.2 Service Disconnecting Means 6.3 Service Equipment & Working Space 6.4 Grounding Connections at the Service

7 Feeders & Overcurrent Protection

7.1 Feeder Conductor Sizing 7.2 Overcurrent Device Selection (Art 240) 7.3 Feeder and Branch-Circuit Tap Rules 7.4 Continuous Loads & OCPD Sizing

8 Branch Circuits, GFCI & AFCI

8.1 Branch-Circuit Ratings & Required Circuits 8.2 Dwelling Receptacle Placement & Kitchen/Bath Circuits 8.3 GFCI Protection Requirements 8.4 AFCI Protection Requirements

9 Metal Raceways

9.1 EMT Installation & Supports 9.2 RMC and IMC 9.3 Flexible Metal & Liquidtight Flexible Metal Conduit

10 Nonmetallic Raceways & Enclosures

10.1 PVC and ENT 10.2 Conduit Fill (Chapter 9 Tables) 10.3 Boxes, Conduit Bodies & Fill 10.4 Cabinets, Cutout Boxes & Meter Enclosures

11 Conductor Ampacity & Selection

11.1 Ampacity Table 310.16 Application 11.2 Termination Temperature Limitations 11.3 Conductor Insulation Types & Uses 11.4 Parallel Conductors

12 Cable Assemblies & Terminations

12.1 NM, MC, and AC Cable Assemblies 12.2 Conductor Identification & Color Coding 12.3 Splices, Taps & Terminations

13 Motors (Article 430)

13.1 Motor Nameplate Data & FLC Tables 13.2 Motor Branch-Circuit Conductors 13.3 Motor Overload Protection 13.4 Motor Short-Circuit / Ground-Fault Protection

14 Motor Controls & Transformers

14.1 Motor Disconnects & Controllers 14.2 Motor Control Circuits 14.3 Transformers (Article 450) for Journeymen

15 Utilization & General-Use Equipment

15.1 Luminaires & Lighting (Art 410) 15.2 Receptacles & Switches (Arts 406/404) 15.3 Appliances & Fixed Electric Space-Heating 15.4 Panelboards (Art 408)

16 Special Occupancies

16.1 Hazardous (Classified) Locations Overview 16.2 Health Care, Assembly & Temporary Installations 16.3 Swimming Pools, Spas & Similar Installations

17 Special Equipment Highlights

17.1 Signs & Outline Lighting 17.2 Elevators & Electric Vehicle Power Transfer 17.3 Emergency & Standby Systems Basics

18 Low-Voltage, Alarms & Communications

18.1 Class 1, 2, and 3 Circuits (Art 725) 18.2 Fire Alarm Systems (Art 760) 18.3 Communications Circuits Overview (Art 800+)

19 Electrical Safety

19.1 Working Space & Dedicated Equipment Space (110.26) 19.2 Lockout/Tagout & Safe Work Practices 19.3 Arc-Flash Awareness for the Exam

20 Exam Strategy & Test Day

20.1 Mixed Calculation Lab 20.2 Timed Code Lookup Drills 20.3 Test-Day Checklist, Scoring & Retakes

3.3 Commercial / Non-Dwelling Demand Factors

Key Takeaways Explain This Topic AI

Non-dwelling general lighting uses the unit loads in Table 220.42(A) and demand factors in Table 220.45 for the occupancy type

Receptacle loads for non-dwellings follow 220.14 and feeder demand rules such as 220.47 — do not use dwelling 220.52 laundry/SA adders

Kitchen equipment other than dwelling units may use Table 220.56 demand factors for three or more pieces of equipment

Continuous loads are calculated at 125% for feeder/service conductor and OCPD sizing interactions (210.19 / 215.2 / 230.42 as applicable)

Show-window, sign, and other special loads have specific Article 220 / Chapter 2 rules — calculate each load type under its own section before summing

Last updated: August 2026

Commercial Loads on a Journeyman Outline

Arkansas Prov’s calculation items are not limited to houses. Expect store lighting, office receptacles, restaurant kitchen equipment, and continuous loads on feeders. The skill is the same: identify occupancy → open the correct Table 220.42(A) unit load → apply Table 220.45 demand if allowed → add other loads under their own sections → apply 125% where continuous .

Do not import dwelling-only shortcuts (two 1500 VA small-appliance circuits, laundry 1500 VA, Table 220.55 household range column) into a retail or office problem unless the stem truly describes dwelling units.

General Lighting — Table 220.42(A) and Table 220.45

NEC 2023 bases many non-dwelling lighting calculations on Table 220.42(A), General Lighting Loads by Non-Dwelling Occupancy . That table lists unit loads in VA/ft² (or other stated units) by occupancy type — banks, offices, stores, restaurants, schools, warehouses, etc. Your exam workflow:

Find the occupancy in Table 220.42(A) .

Multiply unit load × floor area (using the Code’s area rules).

Apply Table 220.45 demand factors for that occupancy when the table provides a demand factor row for it.

Dwelling vs non-dwelling reminder: Dwellings use 220.41 (3 VA/ft²) plus dwelling demand rows. Stores/offices use Table 220.42(A) values — which are often higher VA/ft² than 3.

Illustrative store example (verify unit load in your Code book): Suppose Table 220.42(A) lists 1.9 VA/ft² for a given store occupancy (look up the exact published value). A 5000 ft² sales area → 5000 × 1.9 = 9500 VA connected lighting load before demand. If Table 220.45 allows a demand factor for that occupancy (some occupancies are 100% of the calculated lighting load), apply only what the table prints.

Offices / banks: Many non-dwelling occupancies take 100% of the general lighting load in Table 220.45 (no 35% dwelling-style reduction). That is why commercial lighting demand often stays near the full VA/ft² product — read the table row; do not assume dwelling 35%.

Receptacle Loads — Other Than Dwelling Units

For non-dwelling receptacles, start in 220.14 for branch-circuit load values (for example, receptacle outlets calculated at not less than 180 VA per strap/yoke where that rule applies) and use feeder/service demand provisions such as 220.47 Receptacle Loads — Other Than Dwelling Units (demand factors in Table 220.47 , or Table 220.45 where that section permits) when totaling multioutlet receptacle loads for feeders. In the 2020 NEC this same rule was numbered 220.44 — use the 2023 number on an Arkansas Prov form.

Typical feeder pattern (confirm exact breakpoints in 220.47 / related text):

Sum receptacle VA (number of receptacles × 180 VA, or other method the section allows for multioutlet assemblies).

Apply the published demand factors to that receptacle total (commonly a first portion at 100% and a remainder at a reduced percentage — open 220.47 rather than guessing).

Worked sketch: 100 general-purpose receptacles × 180 VA = 18,000 VA . If the applicable demand rule takes the first 10 kVA at 100% and the remainder at 50% (verify in your NEC edition’s 220.47), demand = 10,000 + (8000 × 0.50) = 14,000 VA . Wrong answers often leave all 18,000 VA at 100% or illegally apply dwelling Table 220.45 35% factors to receptacles.

Multioutlet assemblies, show windows, and fixed multioutlet strips have special calculation notes in 220.14 — if the stem mentions a show window, look up the VA per linear foot rule instead of counting receptacles.

Kitchen Equipment — Other Than Dwelling Unit(s) (220.56)

Commercial cooking and kitchen equipment is not Table 220.55 household ranging. Use 220.56 and Table 220.56 :

For three or more appliances fastened in place and used for cooking, food prep, or similar kitchen loads in other-than-dwelling occupancies, Table 220.56 demand factors may apply to the total connected load .

Demand factors in Table 220.56 decrease as the number of units increases (look up 3 units vs 6 vs 10+).

Example: Six kitchen appliances, connected total 48 kW . If Table 220.56 lists 65% for 6 units (confirm in table), demand = 48 × 0.65 = 31.2 kW . If only two appliances are present, you generally cannot take Table 220.56 demand — use the section’s rules for fewer than three (typically 100% of nameplate unless another section applies).

Restaurant questions may also reference 220.88 optional methods for new restaurants — if the stem cites 220.88, open Part IV; otherwise stay with 220.56 + lighting/receptacle rules.

Continuous Loads and the 125% Factor

A continuous load is one where the maximum current is expected to continue for 3 hours or more . Lighting in many commercial occupancies is treated as continuous. For branch-circuit conductors, feeders, and services, related rules in 210.19(A) , 215.2 , and 230.42 generally require sizing to not less than 125% of the continuous load plus 100% of the noncontinuous load (with listed exceptions).

Exam assembly pattern:

Calculate continuous VA (often lighting).

Calculate noncontinuous VA (some receptacles, certain equipment).

Feeder VA for sizing ≈ 1.25 × continuous + 1.00 × noncontinuous .

Convert to amperes; select conductors/OCPD per Articles 210/215/230/240 and ampacity rules.

Example: Continuous lighting demand 20,000 VA + noncontinuous receptacle demand 8,000 VA on a 208Y/120 V feeder. Sizing load = 1.25 × 20,000 + 8,000 = 33,000 VA . Amperes for a three-phase feeder: I = 33000 ÷ (208 × 1.732) ≈ 91.6 A — then apply conductor ampacity and OCPD selection (often a follow-up).

Do not multiply already-demanded loads by 125% and also apply an illegal second demand factor. Apply demand factors first as Article 220 directs, then apply continuous-load multipliers for conductor/OCPD sizing when the question asks for that.

Other Commercial Adders You Should Tab

  • Load type Where to look Exam note
  • Motors 220.50 / Art. 430 Largest motor 25% adder on feeders
  • Fixed electric space heating 220.51 Often 100% of connected load
  • Noncoincident loads 220.60 Largest of noncoincident
  • Neutral 220.61 Reductions only as stated
  • Signs Art. 600 + 220 references Separate calculated load
  • Track lighting 220.43 VA per foot / luminaire rules

Build commercial feeders as a checklist sum , not a single blended percentage.

Full Commercial Mini-Calc (Exam Style)

Occupancy: small retail, 4000 ft². Assume Table 220.42(A) unit lighting load 1.9 VA/ft² (verify), lighting continuous, Table 220.45 demand 100% for this occupancy. Receptacles: 40 × 180 VA = 7200 VA; apply 220.47 demand as 100% of first 10 kVA + 50% of remainder → here all 7200 at 100% = 7200 VA noncontinuous for this sketch. One 3-phase motor with calculated load contribution 3000 VA; add 25% of largest motor = 750 VA.

  • Lighting connected/demand = 4000 × 1.9 = 7600 VA (continuous)
  • Receptacles demand = 7200 VA (treat as noncontinuous in this sketch)
  • Motor + 25% = 3000 + 750 = 3750 VA
  • Conductor sizing VA ≈ 1.25 × 7600 + 7200 + 3750 = 9500 + 7200 + 3750 = 20,450 VA

Prov may ask only for the lighting VA, only for whether 125% applies, or only for the receptacle demand step. Calculate the asked quantity; do not volunteer extra arithmetic that invites rounding traps.

  • Timed Lookup Order for Commercial Items
  • Occupancy → Table 220.42(A)
  • Lighting demand → Table 220.45
  • Receptacles → 220.14 + 220.47
  • Kitchen → 220.56 / Table 220.56
  • Continuous? → 125% on the continuous portion for sizing questions
  • Motors / HVAC / neutrals → dedicated sections

If a distractor uses 3 VA/ft² on a store, it confused 220.41 dwelling rules with commercial unit loads.