10.2 Conduit Fill (Chapter 9 Tables)

Arkansas Journeyman Electrician Exam Study Guide 2026

Track your progress as you read

Finished sections get a check mark.

1 Introduction & Arkansas Exam Overview

1.1 Current Exam Facts 1.2 Arkansas Licensing Pathway & Board Process 1.3 Open-Book Rules & Allowed References 1.4 NEC 2023 Navigation & Lookup Strategy

2 Electrical Theory & Trade Calculations

2.1 Ohm's Law, Power, and Basic Circuits 2.2 Series, Parallel, and Combination Circuits 2.3 Voltage Drop Calculations 2.4 Box Fill Calculations (314.16)

3 Load Calculations (Article 220)

3.1 Standard Dwelling Unit Load Calculations 3.2 Optional Dwelling & Multifamily Demand 3.3 Commercial / Non-Dwelling Demand Factors 3.4 Ampacity Adjustment & Correction (310.15)

4 Grounding Electrode Systems

4.1 Grounding Electrode Types & Installation 4.2 Grounding Electrode Conductor Sizing (250.66) 4.3 Main Bonding Jumper & Service Bonding

5 Equipment Grounding & Bonding

5.1 Equipment Grounding Conductors (250.122) 5.2 Bonding Raceways, Enclosures & Equipment 5.3 Separately Derived Systems Grounding

6 Services & Service Equipment

6.1 Service Entrance Conductors & Clearances 6.2 Service Disconnecting Means 6.3 Service Equipment & Working Space 6.4 Grounding Connections at the Service

7 Feeders & Overcurrent Protection

7.1 Feeder Conductor Sizing 7.2 Overcurrent Device Selection (Art 240) 7.3 Feeder and Branch-Circuit Tap Rules 7.4 Continuous Loads & OCPD Sizing

8 Branch Circuits, GFCI & AFCI

8.1 Branch-Circuit Ratings & Required Circuits 8.2 Dwelling Receptacle Placement & Kitchen/Bath Circuits 8.3 GFCI Protection Requirements 8.4 AFCI Protection Requirements

9 Metal Raceways

9.1 EMT Installation & Supports 9.2 RMC and IMC 9.3 Flexible Metal & Liquidtight Flexible Metal Conduit

10 Nonmetallic Raceways & Enclosures

10.1 PVC and ENT 10.2 Conduit Fill (Chapter 9 Tables) 10.3 Boxes, Conduit Bodies & Fill 10.4 Cabinets, Cutout Boxes & Meter Enclosures

11 Conductor Ampacity & Selection

11.1 Ampacity Table 310.16 Application 11.2 Termination Temperature Limitations 11.3 Conductor Insulation Types & Uses 11.4 Parallel Conductors

12 Cable Assemblies & Terminations

12.1 NM, MC, and AC Cable Assemblies 12.2 Conductor Identification & Color Coding 12.3 Splices, Taps & Terminations

13 Motors (Article 430)

13.1 Motor Nameplate Data & FLC Tables 13.2 Motor Branch-Circuit Conductors 13.3 Motor Overload Protection 13.4 Motor Short-Circuit / Ground-Fault Protection

14 Motor Controls & Transformers

14.1 Motor Disconnects & Controllers 14.2 Motor Control Circuits 14.3 Transformers (Article 450) for Journeymen

15 Utilization & General-Use Equipment

15.1 Luminaires & Lighting (Art 410) 15.2 Receptacles & Switches (Arts 406/404) 15.3 Appliances & Fixed Electric Space-Heating 15.4 Panelboards (Art 408)

16 Special Occupancies

16.1 Hazardous (Classified) Locations Overview 16.2 Health Care, Assembly & Temporary Installations 16.3 Swimming Pools, Spas & Similar Installations

17 Special Equipment Highlights

17.1 Signs & Outline Lighting 17.2 Elevators & Electric Vehicle Power Transfer 17.3 Emergency & Standby Systems Basics

18 Low-Voltage, Alarms & Communications

18.1 Class 1, 2, and 3 Circuits (Art 725) 18.2 Fire Alarm Systems (Art 760) 18.3 Communications Circuits Overview (Art 800+)

19 Electrical Safety

19.1 Working Space & Dedicated Equipment Space (110.26) 19.2 Lockout/Tagout & Safe Work Practices 19.3 Arc-Flash Awareness for the Exam

20 Exam Strategy & Test Day

20.1 Mixed Calculation Lab 20.2 Timed Code Lookup Drills 20.3 Test-Day Checklist, Scoring & Retakes

10.2 Conduit Fill (Chapter 9 Tables)

Key Takeaways Explain This Topic AI

Chapter 9, Table 1 sets percent fill: one conductor 53%, two conductors 31%, more than two conductors 40% (nipples ≤ 24 in may use 60% per Note 4)

Use Table 4 for raceway internal area, Table 5 (and 5A) for conductor approximate areas, then compare total conductor area to allowable fill area

Annex C gives precomputed maximum same-size conductor counts—use it only when all conductors are the same size and type; mixed sizes require Tables 4 and 5

Fill calculations are separate from ampacity adjustment (310.15)—passing fill does not automatically satisfy derating

Trade size is not outside diameter math: always open Table 4 for the actual wiring method (EMT, PVC, RMC, etc.) because internal areas differ

Last updated: August 2026

10.2 Conduit Fill (Chapter 9 Tables)

Quick Answer: Conduit fill is a Chapter 9 math problem, not a raceway-article guess. Table 1 sets the percent: 53% for one conductor, 31% for two, 40% for over two (and 60% for nipples 24 in or less per Note 4). Multiply the raceway’s internal area from Table 4 by that percent; sum conductor areas from Table 5 ; the sum must be ≤ allowable fill. Use Annex C only when every conductor is the same size and type.

Arkansas Prov’s Raceways and Enclosures items frequently hide a fill question inside an otherwise ordinary PVC or EMT stem. You win by following the same workflow every time: identify the raceway type and trade size → open the correct Table 4 column → apply Table 1 percent → total the conductors from Table 5 (or Annex C when eligible).

Why fill exists (and what it is not)

Fill limits protect conductors from damage during pulls and leave space for heat. They do not :

Replace ampacity adjustment when more than three current-carrying conductors share a raceway ( 310.15 ).

Replace temperature correction for ambient conditions.

Tell you the minimum trade size for voltage-drop reasons.

A run can meet Chapter 9 fill and still fail ampacity rules—or pass ampacity with room to spare on fill. Prov may ask either skill; read the stem for “maximum number of conductors,” “minimum trade size,” or “is this fill acceptable?”

Table 1 — percent of cross section

  • Number of conductors Maximum fill
  • 1 53%
  • 2 31%
  • Over 2 40%
  • Nipple ≤ 24 in between enclosures (Note 4) 60%

Notes matter. Note 1 clarifies that the percentages apply to complete conduit systems. Note 2 addresses conduit bodies (see also Article 314 ). Note 4’s 60% nipple rule is a favorite exam twist: a short conduit nipple between two boxes can be filled more densely than a long home-run.

Equipment grounding conductors count in fill. Neutrals count. “Empty” spare raceways still have a fill limit when you add conductors later—size for the conductors you install now per the question.

  • Tables 4 and 5 — the area method
  • Table 4 (raceway)

Table 4 lists approximate internal diameter and total area plus columns for 40%, 53%, 31%, and 60% already computed for many wiring methods (EMT, IMC, RMC, PVC Schedule 40, PVC Schedule 80, ENT, FMC, LFMC, LFNC, etc.). Always pick the row for the actual method. Trade size 1 EMT does not have the same internal area as trade size 1 Schedule 80 PVC.

Table 5 (conductors)

Table 5 gives approximate areas for insulated conductors by AWG/kcmil and insulation type (THHN/THWN-2, XHHW, RHW, etc.). Table 5A covers compact conductors. Use the insulation type stated in the stem; defaulting to THHN when the problem says RHW will wrong-size the fill.

Workflow

List every conductor (hots, neutral, EGC, travelers, etc.) with size and type.

Look up each approximate area in Table 5 (or 5A).

Sum the areas.

From Table 1 , choose 53%, 31%, 40%, or nipple 60%.

From Table 4 , find the raceway’s total internal area (or the preprinted percent column).

Allowable fill area = total internal area × percent (or read the Table 4 percent column directly).

If sum ≤ allowable, the trade size works; if not, try the next larger trade size.

Annex C — same-size shortcut

Annex C tables list the maximum number of identical conductors of a given type that fit in each raceway trade size at the Table 1 percentages. Use Annex C when:

  • All conductors are the same AWG/kcmil, and
  • All have the same insulation type covered by that Annex C table, and

You are counting complete conductors (including EGCs of that same size).

Do not use Annex C for mixed sizes (for example, three 3/0 hots plus one 6 AWG EGC). Mixed fills require the Table 4 + Table 5 area method. Exam writers love mixing a large feeder with a small EGC to catch Annex C abuse.

  • Worked examples
  • Example 1 — Annex C eligible

Given: How many 12 AWG THHN copper conductors (including EGCs of the same size) may be installed in ½ in EMT?

Approach: All conductors same size/type → Annex C for EMT, 12 AWG THHN, over two conductors (40% column). Read the maximum count directly. (Typical published values put many 12 AWG THHN in ½ in EMT—confirm the exact Annex C number in your 2023 NEC rather than memorizing.)

Exam tip: If the stem asks “maximum number” and every wire is identical, Annex C is faster than summing Table 5 rows.

Example 2 — Mixed sizes (area method)

Given: Three 3/0 AWG THHN copper phase conductors, one 3/0 AWG THHN neutral, and one 4 AWG THHN EGC in PVC Schedule 40. What minimum trade size?

Approach:

From Table 5 , find area of 3/0 THHN; multiply by 4 for the four 3/0 conductors.

Add area of 4 AWG THHN from Table 5 .

Total conductor area = sum.

Over two conductors → 40% fill ( Table 1 ).

Open Table 4 for PVC Schedule 40 (not EMT, not Schedule 80).

Find the smallest trade size whose 40% column (or total area × 0.40) is ≥ the conductor sum.

This is the classic feeder-plus-EGC fill problem. Using Annex C for “3/0 only” and ignoring the 4 AWG EGC underfills the math and can pick an undersized conduit.

Example 3 — Nipple exception

Given: A 18 in conduit nipple between a panel and a wireway will contain many control conductors. May fill exceed 40%?

Approach: Nipple length ≤ 24 in → Chapter 9, Table 1, Note 4 permits 60% fill. Use Table 4’s 60% column for that raceway. Ampacity adjustment may still apply if the nipple is long enough relative to Article 310 notes—but for pure fill percentage, 60% is the Table 1 answer.

Example 4 — One conductor

Given: A single 500 kcmil THHN in RMC for a tap. What percent fill limit?

Approach: One conductor → 53% ( Table 1 ). Compare the conductor’s Table 5 area to 53% of the RMC Table 4 area. Do not apply the 40% rule to a lone conductor.

Example 5 — Two conductors

Given: Two parallel 250 kcmil conductors in one conduit (unusual but testable). Percent fill?

Approach: Exactly two conductors → 31% , which is the most restrictive percentage. Two large conductors often force a surprisingly large raceway.

Method-specific Table 4 traps

  • Stem raceway Open this Table 4 section
  • EMT Electrical Metallic Tubing
  • RMC Rigid Metal Conduit
  • IMC Intermediate Metal Conduit
  • PVC Sch 40 Rigid PVC Schedule 40
  • PVC Sch 80 Rigid PVC Schedule 80 (smaller internal area!)
  • ENT Electrical Nonmetallic Tubing
  • LFMC / LFNC Matching flexible liquidtight tables

Schedule 80 PVC has a thicker wall and less internal area than Schedule 40 of the same trade size. A fill that barely fits Schedule 40 may fail Schedule 80—Prov will switch schedules to test whether you opened the right rows.

Fill vs ampacity adjustment (keep them separate)

  • Question type Tool
  • Will the conductors physically fit? Chapter 9 Tables 1, 4, 5 / Annex C
  • What ampacity after bundling? 310.15 adjustment factors
  • What ampacity after hot ambient? 310.15 correction factors
  • What OCPD rating? Article 240 + conductor ampacity

If nine current-carrying 12 AWG THHN fit by Annex C in a conduit, you still adjust ampacity for more than three current-carrying conductors. Fill success ≠ ampacity success.

Timed open-book tips

Flag Chapter 9, Table 1 (with Notes), Table 4 , Table 5 , and Annex C tabs. On every fill stem: (1) Count conductors and note sizes/types. (2) Same size? Try Annex C. Mixed? Table 5 sum. (3) Apply correct Table 1 percent (watch nipples and the two-conductor 31% case). (4) Match Table 4 to the exact wiring method and schedule. That four-step loop is how you convert Raceways items into reliable points on a timed Arkansas Prov open-book exam.