Study guide
6.3 Service Equipment & Working Space
Arkansas Journeyman Electrician Exam Study Guide 2026
Track your progress as you read
Finished sections get a check mark.
1 Introduction & Arkansas Exam Overview
1.1 Current Exam Facts 1.2 Arkansas Licensing Pathway & Board Process 1.3 Open-Book Rules & Allowed References 1.4 NEC 2023 Navigation & Lookup Strategy
2 Electrical Theory & Trade Calculations
2.1 Ohm's Law, Power, and Basic Circuits 2.2 Series, Parallel, and Combination Circuits 2.3 Voltage Drop Calculations 2.4 Box Fill Calculations (314.16)
3 Load Calculations (Article 220)
3.1 Standard Dwelling Unit Load Calculations 3.2 Optional Dwelling & Multifamily Demand 3.3 Commercial / Non-Dwelling Demand Factors 3.4 Ampacity Adjustment & Correction (310.15)
4 Grounding Electrode Systems
4.1 Grounding Electrode Types & Installation 4.2 Grounding Electrode Conductor Sizing (250.66) 4.3 Main Bonding Jumper & Service Bonding
5 Equipment Grounding & Bonding
5.1 Equipment Grounding Conductors (250.122) 5.2 Bonding Raceways, Enclosures & Equipment 5.3 Separately Derived Systems Grounding
6 Services & Service Equipment
6.1 Service Entrance Conductors & Clearances 6.2 Service Disconnecting Means 6.3 Service Equipment & Working Space 6.4 Grounding Connections at the Service
7 Feeders & Overcurrent Protection
7.1 Feeder Conductor Sizing 7.2 Overcurrent Device Selection (Art 240) 7.3 Feeder and Branch-Circuit Tap Rules 7.4 Continuous Loads & OCPD Sizing
8 Branch Circuits, GFCI & AFCI
8.1 Branch-Circuit Ratings & Required Circuits 8.2 Dwelling Receptacle Placement & Kitchen/Bath Circuits 8.3 GFCI Protection Requirements 8.4 AFCI Protection Requirements
9 Metal Raceways
9.1 EMT Installation & Supports 9.2 RMC and IMC 9.3 Flexible Metal & Liquidtight Flexible Metal Conduit
10 Nonmetallic Raceways & Enclosures
10.1 PVC and ENT 10.2 Conduit Fill (Chapter 9 Tables) 10.3 Boxes, Conduit Bodies & Fill 10.4 Cabinets, Cutout Boxes & Meter Enclosures
11 Conductor Ampacity & Selection
11.1 Ampacity Table 310.16 Application 11.2 Termination Temperature Limitations 11.3 Conductor Insulation Types & Uses 11.4 Parallel Conductors
12 Cable Assemblies & Terminations
12.1 NM, MC, and AC Cable Assemblies 12.2 Conductor Identification & Color Coding 12.3 Splices, Taps & Terminations
13 Motors (Article 430)
13.1 Motor Nameplate Data & FLC Tables 13.2 Motor Branch-Circuit Conductors 13.3 Motor Overload Protection 13.4 Motor Short-Circuit / Ground-Fault Protection
14 Motor Controls & Transformers
14.1 Motor Disconnects & Controllers 14.2 Motor Control Circuits 14.3 Transformers (Article 450) for Journeymen
15 Utilization & General-Use Equipment
15.1 Luminaires & Lighting (Art 410) 15.2 Receptacles & Switches (Arts 406/404) 15.3 Appliances & Fixed Electric Space-Heating 15.4 Panelboards (Art 408)
16 Special Occupancies
16.1 Hazardous (Classified) Locations Overview 16.2 Health Care, Assembly & Temporary Installations 16.3 Swimming Pools, Spas & Similar Installations
17 Special Equipment Highlights
17.1 Signs & Outline Lighting 17.2 Elevators & Electric Vehicle Power Transfer 17.3 Emergency & Standby Systems Basics
18 Low-Voltage, Alarms & Communications
18.1 Class 1, 2, and 3 Circuits (Art 725) 18.2 Fire Alarm Systems (Art 760) 18.3 Communications Circuits Overview (Art 800+)
19 Electrical Safety
19.1 Working Space & Dedicated Equipment Space (110.26) 19.2 Lockout/Tagout & Safe Work Practices 19.3 Arc-Flash Awareness for the Exam
20 Exam Strategy & Test Day
20.1 Mixed Calculation Lab 20.2 Timed Code Lookup Drills 20.3 Test-Day Checklist, Scoring & Retakes
6.3 Service Equipment & Working Space
Key Takeaways Explain This Topic AI
NEC 110.26 requires sufficient access and working space about electrical equipment that may need examination, adjustment, servicing, or maintenance while energized
Table 110.26(A)(1) sets minimum clear depth by voltage to ground and Condition 1/2/3; on the 0–150 V to ground row (a 120/240 V service) all three Conditions require 3 ft, while 151–600 V steps 3 ft / 3½ ft / 4 ft
Working space width must be at least 30 in or the width of the equipment, whichever is greater (110.26(A)(2)); headroom generally not less than 6½ ft (110.26(A)(3))
Dedicated equipment space above service equipment (110.26(E)) is separate from working-space depth — protect the zone for raceways/cables entering the equipment
Illumination of working spaces (110.26(D)) and keeping the working space clear of storage are frequent Prov/safety crossover items
Last updated: August 2026
Working Space Is a Service Topic on Prov
Article 230 tells you what service equipment is and where disconnects go. 110.26 tells you whether a human can safely stand in front of that equipment. Arkansas’s outline includes both Services/OCP (8) and Safety (3) — working-space items can be scored under either framing. For service gear (meter-main combinations, service disconnect enclosures, service panelboards), treat 110.26 as mandatory companion reading to Article 230.
Scope — 110.26 Opening Paragraph
Working space is required about electrical equipment likely to require examination, adjustment, servicing, or maintenance while energized . Service equipment clearly qualifies. The space is for operation and maintenance access , not for storage of paint, lumber, or water heaters.
If a stem says materials are stored in front of a service panel, the violation is 110.26 clearance/access — not an ampacity table problem.
Depth of Working Space — Table 110.26(A)(1)
110.26(A)(1) sends you to Table 110.26(A)(1) . Depth depends on the nominal voltage to ground and on the Condition (1, 2, or 3) that describes what faces the worker across the space. §19.1 drills the Condition definitions and the full table under the Safety outline block; this section applies them to service equipment .
High-frequency dwelling/service fact: a 120/240 V single-phase service is 120 V to ground , so it is read on the 0–150 V row — and on that row all three Conditions require 3 ft . A meter-main mounted on a garage wall directly across an aisle from a grounded concrete wall is Condition 2 thinking, but the required depth is still 3 ft . Depth only grows when voltage to ground grows.
A 480Y/277 V service is 277 V to ground , which lands on the 151–600 V row: 3 ft (Condition 1), 3½ ft (Condition 2), and 4 ft (Condition 3). That is the row where an aisle between two open switchboard sections becomes a 4 ft measurement, not a 3 ft one.
Exam workflow for service stems:
Convert the service description to volts to ground (120/240 V → 120 V; 208Y/120 V → 120 V; 480Y/277 V → 277 V).
Classify Condition 1/2/3 from what faces the worker.
Read the one cell in Table 110.26(A)(1) — remembering that on the 0–150 V row the Condition does not change the answer.
Width of Working Space — 110.26(A)(2)
The width of the working space in front of the electrical equipment must be the width of the equipment or 30 inches , whichever is greater . In all cases, the working space must permit at least a 90-degree opening of equipment doors or hinged panels.
Traps:
A 20-inch-wide panel still needs 30 inches of working-space width.
A 36-inch-wide switchboard needs at least 36 inches of width (equipment width governs when larger than 30 inches).
Depth from Table 110.26(A)(1) and width from 110.26(A)(2) are different measurements — do not answer a width question with a depth number.
Height (Headroom) — 110.26(A)(3)
The height of the working space must be clear and extend from the grade, floor, or platform to a height of 6½ feet (6 ft 6 in) or the height of the equipment, whichever is greater. Limited exceptions exist for service equipment or panelboards in existing dwelling units that do not exceed 200 A — open the exception text when the stem screams “existing dwelling.”
Prov favorite: minimum headroom 6 feet 6 inches for equipment rated 1000 V or less (unless the equipment is taller).
Entrance to Working Space — 110.26(C)
For large equipment (generally 1200 A or more and over 6 ft wide), 110.26(C)(2) requires special entrance/egress arrangements (doors at each end, or the exception paths). Smaller service equipment in dwellings usually does not trigger the large-equipment dual-entrance rule — but commercial service gear might. If the stem gives 1200 A and width over 6 ft , open 110.26(C) .
Personnel doors within 25 ft of the working space edge for large equipment may need to open in the direction of egress and be equipped with listed panic hardware under the conditions in 110.26(C)(3) .
Illumination — 110.26(D)
110.26(D) requires illumination for working spaces about service equipment, switchboards, switchgear, panelboards, or motor control centers installed indoors. Additional lighting outlet controls and automatic control limitations appear in the section — for exam purposes, know that working spaces need lighting , and control of that lighting generally must not place you in darkness while standing in the working space in a way the section prohibits.
Dedicated Equipment Space — 110.26(E)
Do not confuse working space (in front) with dedicated equipment space (typically above and in the footprint of the equipment).
For indoor installations, 110.26(E)(1) generally requires a dedicated space equal to the width and depth of the equipment extending from the floor to a height of 6 ft above the equipment or to the structural ceiling, whichever is lower. Foreign systems (ducts, pipes) are restricted in that zone unless protection/foreign-system rules in the section are met. Outdoor installations have related dedicated-space rules in 110.26(E)(2) .
Teaching distinction:
- Rule Protects
- 110.26(A) working space Person standing in front of live parts
110.26(E) dedicated equipment space Zone for conduits/cables/busways entering equipment; keeps foreign systems out
A sprinkler pipe dripping into the top of a service panel can be a dedicated-space problem even if the aisle in front meets Table 110.26(A)(1).
Guarding, Enclosures, and Service Equipment Marking
Service equipment must be enclosed or guarded per Article 230 Part V and general 110.27 guarding rules. Combine:
- 230.66 suitability marking for service equipment
- 110.21 / equipment labeling for ratings and warnings
- Working-space compliance so the marked disconnect can actually be operated
On exam day, if the stem mentions both “clearance in front of the service disconnect” and “pipes above the panel,” you may need both 110.26(A) and 110.26(E).
Practical Service-Equipment Layout Checks
Use this field/exam checklist:
Is the disconnect location legal under 230.70 ?
Can a worker stand in Condition-correct depth per Table 110.26(A)(1) ?
Is width ≥ 30 in / equipment width?
Is headroom ≥ 6½ ft (or equipment height)?
Is the space used for storage? (Should be no.)
Is indoor working space illuminated per 110.26(D) ?
Is dedicated space above clear per 110.26(E) ?
Timed Open-Book Tips for §6.3
Permanent-tab 110.26 and Table 110.26(A)(1) next to Article 230 .
Always convert the stem to volts to ground before opening the table.
Width answers are usually 30 inches ; depth answers are usually 3 / 3.5 / 4 feet depending on condition/voltage — do not swap units.