Study guide
1.4 AIA A701 Instructions to Bidders & Bidding Rules
ARE 5.0 Construction & Evaluation CE
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Preconstruction Roles, Project Delivery & Bidding
1.1 Project Delivery Methods & Construction Administration Roles 1.2 Architect's Preconstruction Responsibilities & AIA B101 CA Services 1.3 Pre-Bid Conferences, Site Visits & Document Distribution 1.4 AIA A701 Instructions to Bidders & Bidding Rules
2 Chapter 2: Contractor Selection, Bids, Alternates & Contracts
2.1 Contractor Qualification & Evaluation Criteria 2.2 Bid Evaluation, Bonds & Bidder Responsibility 2.3 Alternates, Allowances & Unit Prices 2.4 Owner-Contractor Agreements & Contract Documents Hierarchy
3 Chapter 3: Architect's Role on Site, Observation & Field Reports
3.1 Architect's Authority, Limitations & Standard of Care on Site 3.2 Conducting Site Visits & Field Documentation Protocols 3.3 AIA G711 Architect's Field Reports & Observation Tracking 3.4 Architect as Initial Decision Maker (IDM) & Neutral Interpretation
4 Chapter 4: Special Inspections, Codes, Life Safety & Environmental Hazards
4.1 IBC Chapter 17 Special Inspections, Testing Laboratories & Quality Assurance 4.2 Field Code Compliance, Accessibility Standards & Life Safety Rough-Ins 4.3 Hazardous Materials Discovery, Environmental Regulations & OSHA Safety Awareness 4.4 Sustainability Standards, Mock-Ups & Building Envelope Testing
5 Chapter 5: Conformance, Construction Progress & Work Remedies
5.1 Specification Conformance, Division 01 & Construction Tolerances 5.2 Construction Schedules, Critical Path Method (CPM) & Delay Analysis 5.3 Uncovering Work & Concealed / Unknown Subsurface Conditions 5.4 Non-Conforming Work: Rejection, Notice, Correction Period & Owner Acceptance
6 Chapter 6: Field Modifications: RFIs, ASIs, CCDs & Change Orders
6.1 Requests for Information (RFIs) & AIA G716 Administration 6.2 Architect's Supplemental Instructions (AIA G710) 6.3 Construction Change Directives (AIA G714) 6.4 Change Orders (AIA G701) & Contract Adjustments
7 Chapter 7: Submittals, Shop Drawings, Mock-ups & Delegated Design
7.1 Submittal Schedules & Contractor Review Protocols 7.2 Shop Drawings, Product Data, Samples & Action Stamps 7.3 Physical Mock-Ups, Testing Reports & Certificates of Conformance 7.4 Delegated Design Responsibilities & Professional Certifications
8 Chapter 8: Payment Applications, Schedule of Values & Retainage
8.1 Schedule of Values (SOV) Preparation & Review 8.2 AIA G702 & G703 Application and Certificate for Payment 8.3 Retainage Rules & Off-Site Stored Materials Verification 8.4 Seven-Day Review Timeline & Legal Effects of Certification
9 Chapter 9: Payment Withholding, Disputes, Claims & Termination
9.1 Legal Grounds for Withholding Payment Certification 9.2 Claims Procedures, 21-Day Notice & Damage Limitations 9.3 Dispute Resolution: IDM, Mediation, Arbitration & Litigation 9.4 Termination or Suspension of the Contract
10 Chapter 10: Substantial Completion, Punch Lists & Handover
10.1 Substantial Completion: Legal Definition & Triggers 10.2 Punch List Preparation & AIA G704 Certificate Administration 10.3 Partial Occupancy, Phased Handover & Facility Transition
11 Chapter 11: Final Completion, Liens, Warranties & Closeout
11.1 Closeout Submittals: O&M Manuals, Record Drawings & Attic Stock 11.2 Mechanics' Liens, AIA G706, G706A & G707 Consent of Surety 11.3 Final Inspection, Final Payment Issuance & Mutual Waiver of Claims
12 Chapter 12: Building Performance Evaluation & Post-Occupancy
12.1 Post-Occupancy Evaluation (POE) & Performance Metrics 12.2 Total Building Commissioning & Envelope Verification 12.3 Eleven-Month Warranty Walkthrough & Design Feedback Loops
1.4 AIA A701 Instructions to Bidders & Bidding Rules
Key Takeaways Explain This Topic AI
AIA Document A701-2018 governs the competitive bidding environment, establishing strict countdown deadlines: substitution requests must be received 10 days prior, interpretation requests 7 days prior, and Addenda issued no later than 4 days prior to bid opening.
Under Article 2, submitting a bid constitutes a legally binding representation that the bidder has examined the site, correlated observations with contract documents, and based their bid strictly on the specified materials without unauthorized qualifications.
Bid security (typically 5% to 10% in the form of a bid bond or certified check) protects the owner against the winning bidder's failure or refusal to enter into contract and provide required performance/payment bonds.
Public contracts mandate award to the lowest responsive (compliant with all bidding instructions) and responsible (demonstrating technical capability, financial solvency, and integrity) bidder.
Bids cannot be withdrawn after opening during the designated holding period (typically 30 to 90 days), subject to applicable provisions for clerical errors, owner financial evidence and jurisdictional rules.
Last updated: October 2026
Apply the actual procurement rules
Public procurement requirements vary by jurisdiction, funding source and solicitation. Read the stated receipt, attendance, responsiveness, award and protest rules. Examples in this section assume a competitive low-bid process with material requirements enforced as stated. Private negotiated work can use different selection criteria. AIA forms do not create a universal public procurement statute.
1.4 AIA A701 Instructions to Bidders & Bidding Rules
Competitive bidding relies on procedural fairness, strict deadlines, and transparent evaluation criteria. In standard architectural practice, these rules are governed by AIA Document A701-2018 ( Instructions to Bidders ). While A701 is not a contract between the owner and the contractor—it is an instructional instrument that forms part of the Bidding Documents —its provisions establish legally binding rules that control the procurement process until the construction contract (e.g., AIA Document A101-2017 ) is formally executed.
The Architecture of AIA Document A701-2018
AIA A701 is organized into eight articles that govern every operational step of the bidding phase:
- Article 1 : Definitions (Bidding Documents, Bid, Base Bid, Alternate, Unit Price)
- Article 2 : Bidder's Representations
- Article 3 : Bidding Documents (Copies, Interpretation, Substitutions, Addenda)
- Article 4 : Bidding Procedures (Form and Style, Bid Security, Submission, Modification/Withdrawal)
- Article 5 : Consideration of Bids (Opening, Rejection, Acceptance/Award)
- Article 6 : Post-Bid Information (Contractor's Qualification Statement, Subcontractor lists)
- Article 7 : Performance Bond and Payment Bond
- Article 8 : Enumeration of the Proposed Contract Documents
- Article 2: Bidders' Representations and Due Diligence
Submitting a bid makes six representations under A701-2018 § 2.1 :
Document understanding (§ 2.1.1): The bidder has read and understands the bidding documents.
Related work (§ 2.1.2): The bidder understands the relationship to other project portions being bid or built.
Compliance (§ 2.1.3): The bid complies with the bidding documents.
Site review (§ 2.1.4): The bidder has visited, reviewed local conditions and correlated observations with the proposed contract documents.
Specified basis (§ 2.1.5): The bid uses the required materials, equipment and systems without an undisclosed exception.
Liquidated damages (§ 2.1.6): The bidder understands any liquidated-damages provisions in the proposed agreement.
The Legal Impact of Article 2
An observable condition is a reason to investigate and request clarification before bidding. A bidder should report a visible drainage culvert that conflicts with the proposed foundation rather than assume free removal later. This due-diligence duty does not eliminate every differing-site-condition claim: compare the actual contract indications, reasonable observations, notice and resulting cost or time effects under A201 § 3.7.4.
Article 3: Interpretations, Substitutions, and Addenda Timelines
AIA A701 establishes a strict, time-sensitive countdown calendar that candidates should be able to apply, subject to project amendments:
1. Written Requests for Interpretation (§ 3.2)
Bidders must study the documents and promptly report any errors, inconsistencies, or ambiguities to the architect.
Bidders requiring clarification must submit a written request to the architect at least 7 days prior to the date for receipt of bids (A701 § 3.2.2).
The architect responds by issuing an Addendum to all plan holders.
2. Proposed Substitutions Prior to Bid Opening (§ 3.3)
Bidders who wish to base their pricing on an alternate material, equipment item, or system not explicitly named in the specifications must submit a formal Substitution Request :
10-Day Cutoff (§ 3.3.2.1) : The written request must be received by the architect at least 10 days prior to the date for receipt of bids.
Required Documentation (§ 3.3.2) : The request must include complete technical data, samples, performance testing results, side-by-side specification comparisons, and a statement of any schedule or cost impacts on other trades.
Architect's Sole Discretion (§ 3.3.3) : The burden of proof rests on the proposer. The architect's decision to approve or reject a proposed substitution is final.
Addendum Requirement (§ 3.3.4) : If approved, the architect does not notify the requesting bidder privately . Instead, the architect issues an Addendum to all prospective bidders, allowing every competitor to utilize the newly approved product.
3. Addenda Distribution Rules (§ 3.4)
4-Day Cutoff (§ 3.4.3) : Addenda must be issued no later than 4 days prior to the date for receipt of bids.
The 4-Day Rationale : Contractors assemble sub-bids from dozens of trades during the final 48 to 72 hours. Issuing technical changes less than 4 days before bid opening causes pricing errors, chaos, and missed bids.
The Exception : An Addendum withdrawing the request for bids or postponing the bid date may be issued at any time prior to the scheduled bid opening.
Receipt and acknowledgment: Verify that all Addenda have been received and acknowledge them as the Bid Form requires. Under the stated strict low-bid procedure, an omitted acknowledgment affecting price or scope is a material responsiveness issue; apply the governing procurement rules.
- Article 4: Bidding Procedures, Bid Security, and Irrevocability
- Form of Bid (§ 4.1)
Bids must be submitted on the official Bid Form provided in the Project Manual without alterations, unauthorized conditions, or qualifications. All blanks must be filled in with ink or typed, numbers stated in both words and figures (with words prevailing in the event of a discrepancy), and executed by a legally authorized officer.
Bid Security (§ 4.2)
Bid Security guarantees that the bidder, if awarded the contract, will execute the agreement and furnish required performance and payment bonds.
Acceptable Forms : Bid security may be a Bid Bond (typically AIA Document A310-2010 ) issued by an authorized surety, a certified check, or a cashier's check.
Percentage : Usually stipulated as 5% to 10% of the total bid sum (including accepted alternates).
Default remedy: Apply the actual security instrument and procurement law. Under A310-2010 , a selected bidder’s failure to execute the contract and furnish required bonds can trigger the cost difference for award to the next qualified bidder, capped by the bond’s penal amount. Do not assume every check, bond or jurisdiction uses an identical forfeiture remedy.
Submission and Late Bids (§ 4.3)
Submit bids in the paper or electronic form and location specified in the bidding instructions. Paper instructions may require a sealed, labeled envelope; A701-2018 also accommodates electronic delivery.
A bid received after the exact time and date designated for receipt will be returned unopened.
Apply the stated receipt method, deadline and governing procurement law. A701 supports electronic as well as paper submissions. Do not invent a private exception for a favored bidder; refer disputed timeliness or statutory exceptions to the procurement authority.
Modification or Withdrawal of Bids (§ 4.4)
Prior to Bid Opening (§ 4.4.1) : A bidder may modify or withdraw their bid at any time prior to the designated bid opening time, either in person or by written notice.
Post-Opening Holding Period (Article 4.4) : The bidding documents state the period during which the bidder must hold its price. Read that period together with the clerical-error process, owner-financing provisions and applicable law; a holding period is not an exception-free ban on withdrawal.
Clerical withdrawal (§ 4.4.3) : A701-2018 provides for withdrawal within two days after opening, or the jurisdiction's specified period, with evidence of the clerical error to the architect's reasonable satisfaction. The bid is withdrawn and not resubmitted. Distinguish that procedure from a discretionary price increase or an unsupported assertion that estimating judgment was poor.
Article 5: Bid Consideration, Responsiveness, and Responsibility
Under A701 Article 5 , the owner reserves the right to reject any or all bids, waive informalities or minor irregularities in a bid, and accept the bid that best serves the owner's interests.
For a public procurement whose published rules require low-bid award, evaluate the lowest responsive and responsible bidder . Other lawful procurements can use best-value or negotiated selection:
Disqualification Criteria
Non-Responsive : The submission fails to comply with the instructions in the Bidding Documents (e.g., missing bid bond, unacknowledged addendum affecting scope, qualified bid stating "subject to steel price fluctuations"). Material price or scope deficiencies generally cannot be privately cured after opening under strict low-bid rules; distinguish waivable minor irregularities under the governing law.
Non-Responsible : The contractor lacks the financial capability, technical competence, bonding capacity, or past track record to successfully perform the work. A contractor with an active felony indictment or an exhausted bonding line may be deemed non-responsible.
AIA A701 Critical Deadlines and Enforcement Rules
Timeline Milestone A701 Contract Provision Mandatory Procedural Action Legal Consequence of Non-Compliance
10 Days Prior to Bid Section 3.3.2.1 Submit proposed product substitutions in writing Late substitution requests rejected without technical evaluation
7 Days Prior to Bid Section 3.2.2 Submit written requests for interpretation / RFIs Architect is not obligated to answer late inquiries
4 Days Prior to Bid Section 3.4.3 Last day for architect to issue technical Addenda Addenda issued < 4 days prior requires postponing bid opening date
Bid Opening Deadline Article 4.3 and solicitation Deliver the specified paper or electronic bid to the designated recipient Apply the stated deadline and governing late-bid rules
Holding Period Article 4.4 and solicitation Hold the bid for the stated period Check clerical-error, financing and statutory exceptions before assessing security liability
Contract Award Section 5.3 Owner applies the stated lawful award criteria Unsuccessful bidders have bid security returned within agreed period