Study guide

Fee Allocation Across Project Phases

ARE 5.0 Project Management PjM

Track your progress as you read

Finished sections get a check mark.

1 Exam Orientation

About the ARE 5.0 Project Management Exam Study Strategies & Case Study Mastery

2 Resources and Team Capacity

Staffing Plans & Project Team Assembly Financial Multipliers & Billing Rates Staff Utilization & Chargeable Ratios Consultant Selection & Fee Budgeting

3 Work Plans and Schedules

Project Work Plan Fundamentals Critical Path Method (CPM) & Network Logic Gantt Charts & Milestone Tracking Schedule Contingencies & External Constraints

4 Fee Planning and Communication

Fee Allocation Across Project Phases Earned Value Management (EVM) for Architects Project Communications & Documentation Protocols

5 Owner–Architect Services

AIA B101 Structure & Initial Information Standard of Care, Indemnification & Liability Architect's Basic Services (Article 3) Supplemental vs. Additional Services (Article 4)

6 Consultant Agreements and Integration

AIA C401 Architect-Consultant Agreement Integrating Owner-Retained Consultants

7 Construction Agreements

A101: Price, Time, and Payment Terms AIA A201 General Conditions for Project Managers Construction Manager Contracts: CMa vs. CMc

8 Compensation, Disputes, and Termination

Dispute Resolution Mechanisms & Claims Architectural Compensation & Reimbursables Termination, Suspension & Instruments of Service

9 Delivery Structures and Document Controls

Comparative Project Delivery Methods Bridged Design-Build & Public-Private Partnerships Document Controls by Delivery Method

10 Collaborative Delivery and Procurement

Integrated Project Delivery & Lean Construction Procurement, Bidding & Negotiation

11 Budget Monitoring and Scope Changes

Cost Estimating & Designing to Budget Managing Scope Creep & Construction Changes

12 Construction Administration and Approvals

Submittals, RFIs, Payments & Project Closeout Agency Approvals and Permit Workflow

13 Quality Reviews and Compliance

Quality Assurance vs. Quality Control Peer Reviews & Code Compliance Tracking

14 Coordinated Documents and Models

Interdisciplinary Coordination & Redicheck Specifications & CSI MasterFormat Organization BIM Management & Level of Development (LOD) Clash Detection & Model Coordination

15 Risk, Design Objectives, and Learning

Project Risk Identification & Risk Register Maintaining Design Objectives Through Delivery Knowledge Management & Post-Occupancy Evaluation

Fee Allocation Across Project Phases

Key Takeaways Explain This Topic AI

Phase percentages are negotiated and project-specific; AIA does not prescribe 15/20/40/5/20.

Subtract included consultant and expense obligations before allocating internal production effort.

Distinguish net fee before reserve from the production allowance after reserve.

Front-loaded delivery can require more early effort while later contracted review duties remain.

Last updated: October 2026

Fee Allocation Across Project Phases

Quick Answer: In traditional Design-Bid-Build practice, an illustrative work plan distributes architectural fees across the five standard AIA phases as 15% Schematic Design (SD), 20% Design Development (DD), 40% Construction Documents (CD), 5% Bidding & Negotiation, and 20% Construction Administration (CA) . Before distributing fees to phases, the project manager must calculate the Internal Production Allowance by deducting engineering consultant pass-through fees (illustratively 20%–35%) and carving out an internal firm contingency reserve (5%–10%) . Discrepancies between top-down client fee caps and bottom-up Work Breakdown Structure (WBS) labor estimates must be reconciled prior to contract signing by adjusting scope, reallocating staff seniority, or negotiating additional services.

The Traditional Five-Phase Architectural Fee Structure

Under standard Owner-Architect agreements, such as AIA Document B101-2017, architectural basic services are structured across five sequential phases. AIA does not prescribe phase percentages or universal firm fee benchmarks. The distribution below is an illustrative planning assumption; develop the actual allocation from scope, staffing, delivery method, review needs, and contracted services. Total Architectural Fee (100%)

  • ├── Schematic Design (SD): 15%
  • ├── Design Development (DD): 20%
  • ├── Construction Documents (CD): 40%
  • ├── Procurement / Bidding: 5%
  • └── Construction Administration (CA): 20%
  • 1. Schematic Design (SD) — 15% of Basic Services Fee

Scope & Objectives: The design team explores conceptual spatial configurations, massing options, site circulation, code classifications, and relationship diagrams based on the Owner's program. The architect prepares preliminary single-line drawings, outline narratives, and an initial Estimate of the Cost of the Work under AIA B101 § 3.2.6.

Labor Profile: Highly weighted toward senior design staff (Principals and Senior Project Designers) exploring broad aesthetic and conceptual directions. Total drafting hours are moderate, but billing rates are high.

Management Imperative: Obtaining documented owner approval of the Schematic Design documents and updated cost estimate is mandatory before initiating DD. Unresolved conceptual changes permitted to drift into later phases cause catastrophic rework.

2. Design Development (DD) — 20% of Basic Services Fee

Scope & Objectives: Refines and fixes the architectural concept. Building systems are finalized, including primary structural framing layouts, mechanical/electrical/plumbing (MEP) distribution strategies, exterior envelope wall assemblies, major material selections, and outline specifications. The architect submits an updated cost estimate under AIA B101 § 3.3.2.

Labor Profile: Balanced between senior technical leaders (Project Architect) and production staff (Job Captain, staff designers), with increasing involvement from consulting structural, civil, and MEP engineers.

Management Imperative: DD is the "decision freezing" phase. All primary technical systems and dimensions must be established. Overallocating effort here is preferable to underallocating; uncoordinated engineering systems discovered in Construction Documents require expensive redrafting.

3. Construction Documents (CD) — 40% of Basic Services Fee

Scope & Objectives: Represents the single largest expenditure of architectural labor. The team generates fully detailed, dimensioned, and annotated construction drawings and comprehensive MasterFormat specifications (the Project Manual) necessary for regulatory permitting, bidding, and construction.

Labor Profile: Production-intensive. Dominated by Job Captains, BIM modelers, and technical specification writers, supervised by the Project Architect performing continuous interdisciplinary quality cross-checks.

Management Imperative: The PM must guard against "over-detailing" or expanding scope beyond the contract narrative. Detailed deliverables checklists and strict adherence to the Work Breakdown Structure (WBS) prevent fee burn during this phase.

4. Procurement / Bidding & Negotiation — 5% of Basic Services Fee

Scope & Objectives: The architect assists the owner in distributing bidding documents to prospective contractors, conducting pre-bid conferences, answering bidder Requests for Information (RFIs), issuing Addenda, and evaluating bid proposals or negotiating contract terms.

Labor Profile: Brief calendar window (illustratively 3 to 6 weeks) requiring targeted involvement by the Project Architect and Project Manager.

Management Imperative: Maintaining an accurate Addenda log is vital. Because this phase carries only 5% of the fee, poorly coordinated CD sets that generate hundreds of bidder RFIs can exhaust the bidding budget in days.

5. Construction Administration (CA) — 20% of Basic Services Fee

Scope & Objectives: Under AIA B101 § 3.6, the architect acts as the owner's representative to observe construction progress, evaluate quality, review contractor submittals and shop drawings, process RFIs, review and certify Applications for Payment (AIA G702/G703), prepare Change Orders (AIA G701), conduct punch list inspections, and issue the Certificate of Substantial Completion (AIA G704).

Labor Profile: Sustained, long-duration phase spanning months or years. Involves the Project Architect and field representatives conducting regular site visits and managing submittal logs.

Management Imperative: CA fees must be metered carefully across the anticipated construction duration. If construction is delayed through no fault of the architect, basic CA fees will be depleted, requiring the architect to invoke Additional Services under AIA B101 § 4.2 for extended contract administration.

Fee Allocation Adjustments by Project Delivery Method

While the 15/20/40/5/20 breakdown is an illustrative Design-Bid-Build scenario, alternative delivery methods shift the timing and intensity of architectural effort, requiring significant reallocation of the fee curve:

Project Delivery Method SD (%) DD (%) CD (%) Bidding (%) CA (%) Primary Operational Rationale

Design-Bid-Build (DBB) 15% 20% 40% 5% 20% Sequential baseline; maximum effort concentrated in fully completed CD set prior to competitive bidding.

Construction Manager as Constructor (CMAR / CMc) 18% 25% 32% 5% 20% Early CM involvement shifts detailing forward; DD expanded to 25% to support early Guaranteed Maximum Price (GMP) pricing and constructability reviews.

Design-Build (DB) 20% 25% 30% 5% 20% Architect is teamed with or employed by builder; early trade subcontractor coordination front-loads design decisions into SD and DD.

Fast-Track (Multiple Bid Packages) 15% 20% 35% 10% 20% Multiple procurement packages (e.g., foundation, structural steel, core/shell, interiors) expand bidding and procurement coordination overhead.

Integrated Project Delivery (IPD) 25% 30% 20% 5% 20% Follows the MacLeamy Curve; massive front-loading of multi-party collaborative design in early phases dramatically reduces CD drafting and CA field RFIs.

The MacLeamy Curve and Front-Loading Fees

In progressive delivery methods such as Integrated Project Delivery (IPD) or collaborative CMAR, the fee distribution mirrors the MacLeamy Curve . This principle illustrates that the ability to impact cost and functional performance is highest during early design (SD and DD), while the financial cost of making design changes rises exponentially as the project advances into Construction Documents and Construction. Shifting fee and personnel into earlier phases reduces costly change orders, RFIs, and schedule extensions during construction.

Deriving the Internal Production Allowance & Internal Contingency Reserve

Net professional-service fee is measured before the internal reserve. In the worked example, it is $375,000; allocating a $25,000 reserve leaves a $350,000 production allowance. The reserve does not reduce earned net revenue. Included expense obligations must be removed consistently; do not subtract expenses billed separately from a professional-service-only fee.

An architectural project manager must never allocate the full gross contract fee directly to architectural production. Doing so ignores mandatory consultant pass-through costs and exposes the firm to severe financial vulnerability when unexpected complications arise.

Deducting Consultant Pass-Through Fees

For this planning scenario, assume architect-retained consulting engineers (structural, civil, mechanical, electrical, plumbing, and fire protection) account for 20% to 35% of the gross architectural contract fee. These funds do not belong to the architectural firm; they are contractual pass-through obligations governed by agreements such as AIA Document C401-2017.

Establishing the Internal Firm Project Contingency Reserve

For this scenario, the firm chooses an internal project contingency of 5% to 10% from the architectural fee prior to distributing funds across phase labor budgets. This internal contingency serves critical operational purposes:

Absorbs Minor Scope Drift: Covers minor client design adjustments that do not rise to the contractual threshold of formal Additional Services.

Buffers Against Internal Rework: Mitigates the financial impact of technical coordination hurdles, detailing revisions, or software/BIM modeling snags.

Guards QA/QC Peer Reviews: Ensures funds remain available at the conclusion of CD for independent senior quality reviews without depleting phase production hours.

Step-by-Step Mathematical Calculation of Internal Production Allowance

The Internal Production Allowance represents the true revenue available for direct architectural labor and overhead/profit: Gross Contract Fee − Consultant Fees − Reimbursables − Internal Project Contingency = Internal Production Allowance \text{Gross Contract Fee} - \text{Consultant Fees} - \text{Reimbursables} - \text{Internal Project Contingency} = \text{Internal Production Allowance} Gross Contract Fee − Consultant Fees − Reimbursables − Internal Project Contingency = Internal Production Allowance Phase Labor Budget = Internal Production Allowance × Phase Allocation Percentage \text{Phase Labor Budget} = \text{Internal Production Allowance} \times \text{Phase Allocation Percentage} Phase Labor Budget = Internal Production Allowance × Phase Allocation Percentage Planned Phase Labor Hours = Phase Labor Budget Blended Hourly Billing Rate \text{Planned Phase Labor Hours} = \frac{\text{Phase Labor Budget}}{\text{Blended Hourly Billing Rate}} Planned Phase Labor Hours = Blended Hourly Billing Rate Phase Labor Budget ​

Top-Down vs. Bottom-Up Fee Budgeting Reconciliation

A central duty of the Project Manager during project kickoff is reconciling two fundamentally opposing fee estimation methodologies:

1. Top-Down Fee Budgeting

Top-down budgeting is market-driven or client-driven. It begins with the total fee stipulated in the client's Request for Proposals (RFP), calculated as a fixed lump sum or as a percentage of the estimated Construction Cost (e.g., 7.0% of a $10,000,000 construction budget = $700,000 gross fee). The PM divides this fixed top-down number across phases and attempts to fit staff into the resulting financial boxes.

2. Bottom-Up Fee Budgeting

Bottom-up budgeting is production-driven. Working from the Work Breakdown Structure (WBS), the PM and Project Architect itemize every required drawing sheet, specification section, coordination meeting, and administrative task. They estimate the precise labor hours required by each staff role (e.g., 40 hours of Job Captain drafting, 16 hours of PA detailing) and multiply these hours by the firm's standard billing rates or Direct Personnel Expense (DPE) multipliers: Bottom-Up Fee = ∑ ( Planned Hours per Role × Hourly Billing Rate ) \text{Bottom-Up Fee} = \sum (\text{Planned Hours per Role} \times \text{Hourly Billing Rate}) Bottom-Up Fee = ∑ ( Planned Hours per Role × Hourly Billing Rate )

The Reconciliation Process: Resolving Gaps

In professional practice, the bottom-up estimate can exceed the top-down fee allowance. If a firm signs a contract based on an unadjusted top-down cap without reconciling it against bottom-up reality, the project carries an unresolved risk of overrunning its fee. The PM must execute one or more of the following reconciliation strategies:

Adjust Staff Seniority Mix: Reallocate production tasks from senior architects ($160–$200/hr) to intermediate or junior designers ($90–$110/hr), preserving appropriate senior design, coordination, oversight, and review involvement to reduce the blended hourly rate.

Negotiate Scope and Deliverables: Review the project scope narrative with the client. Remove non-essential deliverables (such as physical study models, photorealistic marketing renderings, or multiple distinct schematic design options) and categorize them as Additional Services.

Streamline Drawing Production: Leverage standard firm detail libraries, modular components, and automated BIM scheduling tools to reduce budgeted production hours per sheet.

Negotiate an Adjusted Fee Cap: Present the granular bottom-up WBS to the client during contract negotiation to demonstrate why the proposed top-down fee is inadequate to support the requested scope of services.

Comprehensive Worked Case Study: Full Project Fee Breakdown

Consider an architectural firm negotiating a stipulated lump-sum agreement of $500,000 for a new community library under a traditional Design-Bid-Build delivery model. The firm plans a 25% consultant allowance, reserves an internal project contingency of 5%, and utilizes a blended team billing rate of $125 per hour .

Initial Fee Deduction Analysis

  • Financial Component Calculation Dollar Amount Status
  • Gross Contract Fee Total contract value $500,000 Contractual Base
  • Consultant Fees (25%) $500,000 × 0.25 (Structural, MEP, Civil) -$125,000 Pass-Through Liability
  • Internal Contingency (5%) $500,000 × 0.05 -$25,000 Reserved Risk Pool
  • Internal Production Allowance $500,000 - $125,000 - $25,000 $350,000 Available Direct Architectural Labor
  • Phase-by-Phase Labor Budget & Staff Hour Distribution Table

Applying the traditional Design-Bid-Build fee percentages to the $350,000 Internal Production Allowance yields the following operational labor allocation across the project lifecycle:

  • Phase Scenario % Phase Production Allowance Planned Hours (@ $125/hr) Phase Duration Average Weekly Hours
  • Schematic Design (SD) 15% $52,500 420 hrs 8 weeks 52.5 hrs/wk
  • Design Development (DD) 20% $70,000 560 hrs 10 weeks 56.0 hrs/wk
  • Construction Documents (CD) 40% $140,000 1,120 hrs 16 weeks 70.0 hrs/wk
  • Bidding & Negotiation 5% $17,500 140 hrs 4 weeks 35.0 hrs/wk
  • Construction Administration (CA) 20% $70,000 560 hrs 52 weeks 10.8 hrs/wk
  • Total Basic Services 100% $350,000 2,800 hrs 90 weeks —

Reference: AIA B101 compensation blanks and phase percentages .