Dispute Resolution Mechanisms & Claims

ARE 5.0 Project Management PjM

Track your progress as you read

Finished sections get a check mark.

1 Exam Orientation

About the ARE 5.0 Project Management Exam Study Strategies & Case Study Mastery

2 Resources and Team Capacity

Staffing Plans & Project Team Assembly Financial Multipliers & Billing Rates Staff Utilization & Chargeable Ratios Consultant Selection & Fee Budgeting

3 Work Plans and Schedules

Project Work Plan Fundamentals Critical Path Method (CPM) & Network Logic Gantt Charts & Milestone Tracking Schedule Contingencies & External Constraints

4 Fee Planning and Communication

Fee Allocation Across Project Phases Earned Value Management (EVM) for Architects Project Communications & Documentation Protocols

5 Owner–Architect Services

AIA B101 Structure & Initial Information Standard of Care, Indemnification & Liability Architect's Basic Services (Article 3) Supplemental vs. Additional Services (Article 4)

6 Consultant Agreements and Integration

AIA C401 Architect-Consultant Agreement Integrating Owner-Retained Consultants

7 Construction Agreements

A101: Price, Time, and Payment Terms AIA A201 General Conditions for Project Managers Construction Manager Contracts: CMa vs. CMc

8 Compensation, Disputes, and Termination

Dispute Resolution Mechanisms & Claims Architectural Compensation & Reimbursables Termination, Suspension & Instruments of Service

9 Delivery Structures and Document Controls

Comparative Project Delivery Methods Bridged Design-Build & Public-Private Partnerships Document Controls by Delivery Method

10 Collaborative Delivery and Procurement

Integrated Project Delivery & Lean Construction Procurement, Bidding & Negotiation

11 Budget Monitoring and Scope Changes

Cost Estimating & Designing to Budget Managing Scope Creep & Construction Changes

12 Construction Administration and Approvals

Submittals, RFIs, Payments & Project Closeout Agency Approvals and Permit Workflow

13 Quality Reviews and Compliance

Quality Assurance vs. Quality Control Peer Reviews & Code Compliance Tracking

14 Coordinated Documents and Models

Interdisciplinary Coordination & Redicheck Specifications & CSI MasterFormat Organization BIM Management & Level of Development (LOD) Clash Detection & Model Coordination

15 Risk, Design Objectives, and Learning

Project Risk Identification & Risk Register Maintaining Design Objectives Through Delivery Knowledge Management & Post-Occupancy Evaluation

Dispute Resolution Mechanisms & Claims

Key Takeaways Explain This Topic AI

A201’s 21-day claim notice applies to the specified period; concealed conditions have a separate prompt-notice rule.

The IDM takes preliminary action within ten days, without a universal 30-day final-decision deadline.

The 2017 receipt-based mediation demand and response periods are each 30 days under § 15.2.6.1.

Mediation, arbitration, litigation, and joinder have different functions and depend on the selected agreements.

Last updated: October 2026

Claims and dispute resolution

A project disagreement is not necessarily a formal claim. First identify the issue, relevant agreement, affected parties, and requested relief. A contractor's RFI asks for information or interpretation; a claim asserts a contractual right to money, time, or another remedy. The architect should preserve a clear record and apply the correct process without confusing a design clarification with authorization for additional compensation.

Establish the claim's basis

A useful claim record identifies the triggering event, contract provision, requested adjustment, notice date, supporting costs, schedule effects, and prior decisions. Under A201, the party making a claim bears the responsibility to substantiate it. An invoice alone does not demonstrate entitlement. For a delay, identify the affected activities and their relationship to the current critical path, not just the number of days a crew was idle.

Suppose the owner delays an equipment decision and the contractor requests ten extra days. Review when the information was contractually needed, when it arrived, which activities were prevented, whether float remained, and whether another delay overlapped. The fact that the owner caused a delay does not by itself calculate either the time extension or monetary relief. Preserve the schedule update and notices used in the evaluation.

Notice periods and exceptions

A201–2017 § 15.1.3.1 applies a 21-day notice requirement to claims arising before or during the one-year correction period: measure from the event or first recognition of the condition, whichever is later. Claims discovered after that correction period are handled differently under § 15.1.3.2. Do not teach the 21-day period as a universal rule for every later claim.

Concealed or unknown conditions have a separate provision, § 3.7.4: provide prompt notice before disturbing the conditions, no later than 14 days after first observation. The architect investigates and recommends an adjustment when the contractual criteria are satisfied. Claims for additional cost under § 15.1.5 generally require notice before the work involved, with specified exceptions. Additional-time provisions are in § 15.1.6. Always read the applicable clause instead of applying a familiar deadline from a different issue.

Notice delivery also matters. A201 treats claim notices differently from ordinary project emails. Verify the prescribed recipient and delivery method in the executed agreement. A technically well-supported claim can still encounter a procedural dispute if notice requirements were ignored. The legal consequences depend on the actual contract and applicable law; a manager should not announce automatic forfeiture merely from a simplified study rule.

Initial decision maker

The architect is the default initial decision maker unless another person is named. This role concerns specified owner–contractor claims, not automatically every dispute among all consultants and project participants. The IDM applies the agreement impartially and considers supporting information. Particular exclusions and later-arising claims must be checked in Article 15.

Within ten days of receiving a claim, the IDM takes the prescribed preliminary action, such as requesting data, rejecting or approving the claim, suggesting compromise, or advising that it cannot resolve the matter. This does not create a universal obligation to issue a final decision within 30 days. The 30-day period without an initial decision can permit proceeding to mediation under the applicable clause.

When an initial decision is issued, read the receipt-based deadlines carefully. Under § 15.2.6.1, a party can demand mediation within 30 days after receiving the decision, and the other party then has 30 days after receiving that demand to file. These are distinct triggers. Mixing the 2007 edition's deadlines with the 2017 edition can change the outcome of an exam scenario.

Mediation and binding procedures

Mediation uses a neutral facilitator to help the parties reach a settlement; the mediator does not ordinarily impose the result. A201 requires mediation as a condition precedent to binding dispute resolution within its terms. A mediation request and a binding-procedure demand may be filed concurrently, but the agreement prescribes the mediation-first stay. “Mediation required” does not mean that all other filing must wait, especially where rights or limitations periods need preservation.

Arbitration produces a binding determination under the selected arbitration rules, while litigation proceeds in court. Arbitration may be private, but confidentiality, cost, speed, appeal limits, and discovery depend on the rules and circumstances. It is not guaranteed to be cheaper or confidential in every case. Determine the selected binding method from the agreement rather than assuming arbitration is always required by AIA forms.

B101 governs owner–architect disputes, and C401 addresses architect–consultant disputes. The architect is not the judge of an owner's claim against the architect under the A201 IDM role. Coordination between dispute provisions is valuable, but each agreement still matters.

Consolidation, continued work, and resolution

Related proceedings may be consolidated or additional parties joined only under the applicable contractual conditions and rules. Do not assume that the architect can automatically force every consultant into any owner–contractor proceeding. Review common issues, existing agreements, consent provisions, and the selected forum. Preserve relevant records so a consistent factual history is available regardless of forum.

A201 generally requires continued contractor performance and owner payments in accordance with the contract pending a claim, subject to stated exceptions and termination or suspension rights. An unresolved claim alone is not blanket authorization to abandon the project. Keep undisputed issues moving while preserving the dispute record.

For a management response, separate immediate safety or design clarification from the entitlement decision. Log the dispute, give required notices, gather contemporaneous cost and schedule evidence, obtain the applicable initial decision, and follow the selected escalation process. A practical early meeting can narrow issues, but it does not replace required notice or a written settlement. Record the final adjustment in the appropriate agreement or construction instrument and update the baseline.

Reference: AIA A201 2017 changes and claims .

Distinguish the dispute steps

  • Step Purpose
  • Notice and records Preserve the applicable contractual process and facts
  • Initial decision when applicable Obtain the designated decision-maker’s review
  • Mediation Seek a facilitated voluntary resolution
  • Selected binding process Resolve the dispute through the agreed forum