Study guide
1.2 Eligibility, PSI Delivery, Fees, Scheduling & Rescheduling
Architect Registration Examination ARE 5.0
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: ARE 5.0 Structure, Delivery & Scoring
1.1 The Six Divisions: Items, Durations, Sections & Objectives 1.2 Eligibility, PSI Delivery, Fees, Scheduling & Rescheduling 1.3 Cut Scores, Score Reports, Provisional Feedback & Retakes
2 Chapter 2: Licensure Path, Item Types & Test-Day Strategy
2.1 Education Standard, AXP Hours, Settings & Reporting Rules 2.2 The NCARB Record, Score Validity Policy & Reciprocity 2.3 Item Types, Case Studies, Exam Tools, Breaks & Pacing
3 Chapter 3: Practice Management — Firm Resources, Conduct & the Work Environment
3.1 Assessing Practice Resources: Staffing, Development & Capital Investment 3.2 Regulating the Work Environment: FLSA, Antidiscrimination Law, OSHA & ADA Title III 3.3 Ethical Standards, the NCARB Rules of Conduct & the Standard of Care 3.4 Business Structures, Firm Ownership Rules & Practice-Wide Methodologies
4 Chapter 4: Practice Management — Firm Finances & Financial Health
4.1 Utilization, Overhead, Break-Even & Net Multiplier 4.2 Liquidity, Solvency & Reading Firm Financials Strategically 4.3 Accrual vs. Cash Accounting & the Architectural Balance Sheet 4.4 The Income Statement, Net Operating Revenue & Cash Flow Management
5 Chapter 5: Practice Management — Risk, Insurance & Business Development
5.1 Risk Management & the Firm’s Insurance Portfolio 5.2 Contractual Risk Allocation, Intellectual Property & Dispute Resolution 5.3 Client Requests, Compensation Methods, Project Delivery & Project Risk
6 Chapter 6: Project Management — Team, Resources & Consultants
6.1 Assembling the Project Team: Roles, Authority & Selection Criteria 6.2 Allocating & Managing Project Resources: Hours, Rates & Leveling 6.3 Consultant Selection, Qualifications-Based Selection & Scope Boundaries 6.4 AIA C401: Flow-Through, Consultant Standard of Care, Insurance & Payment
7 Chapter 7: Project Management — Work Planning, Scheduling & Budget Control
7.1 The Project Work Plan & Phase Fee Allocation 7.2 Work Breakdown Structures, Scheduling Methods & Dependency Logic 7.3 Critical Path Calculations, Float & Schedule Compression 7.4 Project Communication: Paths, Instruments, Meetings & the Record 7.5 Monitoring the Project Budget with Earned Value Management 7.6 Scope Creep, Additional Services & Written Authorization
8 Chapter 8: Project Management — Contracts, Approvals & Quality Control
8.1 AIA B101: Initial Information, Standard of Care & Basic Services 8.2 B101: Owner Duties, Cost of the Work, Copyright, Termination & Compensation 8.3 The Owner-Contractor Agreement & A201 Contractor Responsibilities 8.4 A201: Architect Administration, Changes, Claims & Separate Contractors 8.5 Regulatory Compliance, Authorities Having Jurisdiction & Project Approvals 8.6 Documenting a Project for the Specified Delivery Method 8.7 Quality Assurance, Quality Control, Constructability & the Record
9 Chapter 9: Programming & Analysis — Site & Environmental Conditions
9.1 Climate Classification, Solar Geometry & Passive Site Opportunities 9.2 Microclimate, Wind, Topography, Grading & Site Hydrology 9.3 Environmental Due Diligence: CERCLA Liability & Phase I / Phase II Assessments 9.4 Soil Mechanics, Geotechnical Investigation & Foundation Selection 9.5 Vehicular Circulation, Access Management, Parking & Emergency Access
10 Chapter 10: Programming & Analysis — Zoning, Codes & Site Infrastructure
10.1 Pedestrian Circulation, Site Utilities & Contextual Constraints 10.2 Zoning Authority, Euclidean and Form-Based Codes & Bulk Standards 10.3 Non-Conforming Uses, Variances, Easements & Parking Feasibility 10.4 IBC Occupancy Classification, Mixed Occupancy & Incidental Uses 10.5 IBC Construction Types, Fire-Resistance Ratings & Compartmentation
11 Chapter 11: Programming & Analysis — Building Programming & Feasibility
11.1 Programming Methodology, Net vs. Gross Area & Building Efficiency 11.2 Adjacency Matrices, Bubble Diagrams, Blocking & Stacking 11.3 Evaluating an Existing Building Against a Program 11.4 Reviewing Project Budget & Schedule Feasibility Against Scope 11.5 Identifying Building & Structural System Alternatives at Programming
12 Chapter 12: Project Planning & Design — Siting, Configuration, Codes & Life Safety
12.1 Building Siting, Neighborhood Context, Zoning Application & Configuration 12.2 IBC Allowable Area: Tabular Area, Frontage & Sprinkler Increases 12.3 Building Height, Story Limits, Mixed Occupancy & Unlimited Area Buildings 12.4 Means of Egress Components & Occupant Load Calculation 12.5 Exit Count, Remoteness, Egress Capacity, Travel Distance & Dead Ends 12.6 Accessible Routes, Slopes, Protruding Objects & Ramp Design 12.7 Door Clearances, Operating Hardware & Accessible Toilet Room Geometry
13 Chapter 13: Project Planning & Design — Structural & Mechanical Systems
13.1 Selecting Structural Systems: Steel, Concrete, Wood & Masonry 13.2 Lateral Force-Resisting Systems, Wind Loads & Seismic Design 13.3 Thermal Comfort, ASHRAE Standard 55 & Psychrometrics 13.4 HVAC System Typologies, Spatial Allocation & Central Plant Equipment 13.5 Potable Water Supply, Drainage, Waste & Vent Systems 13.6 Electrical Distribution, Emergency Power, Lighting & Daylighting 13.7 Fire Suppression, Standpipes, Conveying, Security & Communications
14 Chapter 14: Project Planning & Design — Envelope, Materials & Cost
14.1 Envelope Thermodynamics, Heat Transfer & Fenestration Performance 14.2 Thermal Bridging, Continuous Insulation & Thermal Mass 14.3 Passive Solar Heating, Natural Ventilation & Daylighting Architecture 14.4 Material Selection Criteria, Fire Performance & Vapor Permeance 14.5 Life Cycle Assessment, Embodied Carbon & Material Transparency 14.6 Galvanic Compatibility, Thermal Movement & Masonry Durability 14.7 Cost Estimating by Phase & Contingency Planning 14.8 Life-Cycle Cost Analysis, Present Value & Value Engineering
15 Chapter 15: Project Development & Documentation — Roofing, Waterproofing & Wall Assemblies
15.1 Low-Slope Roofing Systems, Membranes & Drainage Geometry 15.2 Flashing, Parapets, Copings & Roof Penetration Detailing 15.3 Steep-Slope Roofing & Below-Grade Waterproofing 15.4 Enclosure Control Layers & Rain Screen Cladding Systems 15.5 Vapor Retarders, Permeance Classes & Dew Point Control
16 Chapter 16: Project Development & Documentation — Connections, Coordination & Interiors
16.1 Structural Steel Connections & Base Plate Detailing 16.2 Concrete Reinforcing, Cover & Building Movement Joints 16.3 Sizing Structural, Mechanical, Electrical & Plumbing Components 16.4 Ceiling Plenum Coordination, Clash Detection & Level of Development 16.5 Vertical Chases, Shaft Walls, Through-Penetration Firestopping & Rated Joints 16.6 Interior Partition Framing, Head-of-Wall Details & Rated Gypsum Assemblies 16.7 Sound Isolation, STC, NRC & Reverberation Time 16.8 Door and Frame Construction & Fire Door Assemblies Under NFPA 80 16.9 Hardware Functions, Fire-Protection vs. Fire-Resistance Glazing
17 Chapter 17: Project Development & Documentation — Drawings, Specifications & Estimates
17.1 The National CAD Standard, Sheet Modules & Title Blocks 17.2 Drawing Cross-Referencing, Coordination & Revision Control 17.3 Documenting Site Features: Survey, Civil, Grading, Utilities & Landscape 17.4 The Project Manual & CSI MasterFormat Divisions 17.5 Section Numbering & the CSI Three-Part SectionFormat 17.6 Specification Methods & Document Precedence 17.7 Quantity Takeoff Estimating, General Conditions, Overhead & Alternates
18 Chapter 18: Construction & Evaluation — Procurement, Bidding & Preconstruction
18.1 Procurement Methods & AIA A701 Instructions to Bidders 18.2 Addenda Mechanics & Surety Bonds 18.3 The Preconstruction Conference & Administrative Protocols 18.4 Submittal Schedules, Long-Lead Items, Permits & Special Inspections 18.5 Bid Opening, Bidder Qualification & Discrepancy Rules 18.6 Alternates, Allowances, Unit Prices & Contract Award
19 Chapter 19: Construction & Evaluation — Observation & Contract Administration
19.1 The Architect’s Site Observation Role & the Means and Methods Firewall 19.2 Rejecting Non-Conforming Work, Special Inspections & Field Reports 19.3 Submittal Workflow, Review Responsibility & Action Stamps 19.4 Delegated Design, Design-Assist & Deferred Submittals 19.5 Requests for Information & Architect’s Supplemental Instructions 19.6 Change Orders, Construction Change Directives & Instrument Comparison
20 Chapter 20: Construction & Evaluation — Payment, Closeout & Evaluation
20.1 The Schedule of Values & the Application and Certificate for Payment 20.2 Stored Materials, Retainage, Certification Duties & Withholding 20.3 Substantial Completion & the Punch List Protocol 20.4 The Certificate of Substantial Completion & Its Legal Consequences 20.5 Final Completion, Final Payment & the Closeout Package 20.6 Warranty Administration, the Eleven-Month Walk-Through & Post-Occupancy Evaluation
1.2 Eligibility, PSI Delivery, Fees, Scheduling & Rescheduling
Key Takeaways Explain This Topic AI
Each ARE division costs $263, and all six divisions cost $1,578; the NCARB Record costs $105 to open and $105 per year to renew.
Exam eligibility is granted by your jurisdiction board (or NCARB Exam Eligibility Services) after you accept the ARE Candidate Agreement.
ARE 5.0 is delivered by PSI at test centers and through the PSI Proctoring Platform; personal calculators are prohibited in both modes.
You may reschedule up to 48 hours before an in-person appointment and 24 hours before an online appointment, and cancel up to one hour before for a fee.
NCARB refunds no exam, rescheduling, or cancellation fees, and a no-show forfeits the entire $263 test fee.
Last updated: September 2026
Passing the ARE is partly an administrative exercise. Eligibility flows through your NCARB Record, appointments are booked with PSI, and the fee, reschedule, and cancellation rules have real money attached to them.
Establishing and Maintaining Eligibility
You cannot buy an ARE seat on impulse. The sequence is fixed:
Establish an NCARB Record at my.ncarb.org.
Open the Exams tab and click Request Eligibility , selecting the jurisdiction where you intend to be licensed.
Accept the ARE Candidate Agreement , which legally binds you to keep exam content confidential.
Your board of architecture grants eligibility if you meet that jurisdiction's requirements — or NCARB grants it directly if your board participates in NCARB's Exam Eligibility Services.
Verify that the first and last name in your NCARB Record exactly matches your government photo ID before scheduling. A mismatch will cost you the appointment and the fee.
Because eligibility is granted by the jurisdiction, education and experience prerequisites vary. Some boards allow you to begin testing early in the Architectural Experience Program (AXP); others require AXP completion first.
Two Delivery Modes, One Vendor
NCARB delivers ARE 5.0 through PSI , in two modalities that use the same content, the same clock, and the same security standards:
PSI test center. A proctored workstation at a physical site. Staff handle identity verification and security screening, and you are insulated from your own bandwidth and power problems. During a break you must remain inside the test center — leaving may cancel your exam with no refund.
PSI Proctoring Platform (online). Remote delivery from a private room you control. You supply the hardware, the bandwidth, and a space that stays clear and quiet for the full appointment. A technical failure or an interruption in your space is your risk, not the proctor's.
Whichever you choose, run the PSI test run before exam day if you are testing online. Discovering a camera or firewall problem at the start of a 5-hour PPD appointment is an avoidable disaster.
Fees
- Item Fee
- ARE division (each) $263
- All six divisions $1,578
- NCARB Record application (licensure candidate) $105
- NCARB Record annual renewal $105
- Score verification of a failed division $100
- Exam review through your board $300 to NCARB, plus any board fee
Source: NCARB fee schedule and ARE 5.0 Guidelines (June 2026).
Budget the Record renewal for every year you are testing , not just the first. A candidate who takes three years to finish pays $1,578 in seat fees plus roughly $315 in Record fees, before any retakes. Every failed division adds another $263.
An exam seat you purchase in advance is valid for one year . Payment is made inside your NCARB Record with Visa, MasterCard, or American Express; third-party payment is available only when buying seats in advance, not at the end of scheduling. NCARB does not refund exam, rescheduling, or cancellation fees.
Rescheduling and Cancellation
The reschedule window is tied to the delivery mode:
In-person appointment: reschedule up to 48 hours before your appointment.
Online-proctored appointment: reschedule up to 24 hours before your appointment.
Cancellation: you may cancel up to one hour before the appointment time for a fee. You receive a replacement exam seat that expires one year from the transaction date.
Reschedule and cancellation fees are set on NCARB's published fee schedule and have been revised more than once; confirm the current amounts on NCARB's fees page before you move an appointment, because the charge depends on how much notice you give. If you fail to appear , you are marked absent and the entire test fee is forfeited.
One useful mechanic: if you need to retake a division after failing, or your appointment is canceled, the rescheduling count resets for the next attempt.
Identification and Security
Bring a valid, unexpired, government-issued photo ID whose first and last name match your NCARB Record exactly. Expect security screening at check-in and re-admittance screening every time you come back from a break. Personal calculators are prohibited in both modalities — the exam supplies an on-screen calculator, and using your own can void your scores.
Exam Tip: The 48-hour and 24-hour reschedule cutoffs are hard. Inside that window there is no reschedule — only a cancellation (with a fee, up to one hour before) or a no-show that forfeits the full $263. If you know a week out that you are not ready, move the appointment then, not the night before.