5.3 Client Requests, Compensation Methods, Project Delivery & Project Risk

Architect Registration Examination ARE 5.0

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: ARE 5.0 Structure, Delivery & Scoring

1.1 The Six Divisions: Items, Durations, Sections & Objectives 1.2 Eligibility, PSI Delivery, Fees, Scheduling & Rescheduling 1.3 Cut Scores, Score Reports, Provisional Feedback & Retakes

2 Chapter 2: Licensure Path, Item Types & Test-Day Strategy

2.1 Education Standard, AXP Hours, Settings & Reporting Rules 2.2 The NCARB Record, Score Validity Policy & Reciprocity 2.3 Item Types, Case Studies, Exam Tools, Breaks & Pacing

3 Chapter 3: Practice Management — Firm Resources, Conduct & the Work Environment

3.1 Assessing Practice Resources: Staffing, Development & Capital Investment 3.2 Regulating the Work Environment: FLSA, Antidiscrimination Law, OSHA & ADA Title III 3.3 Ethical Standards, the NCARB Rules of Conduct & the Standard of Care 3.4 Business Structures, Firm Ownership Rules & Practice-Wide Methodologies

4 Chapter 4: Practice Management — Firm Finances & Financial Health

4.1 Utilization, Overhead, Break-Even & Net Multiplier 4.2 Liquidity, Solvency & Reading Firm Financials Strategically 4.3 Accrual vs. Cash Accounting & the Architectural Balance Sheet 4.4 The Income Statement, Net Operating Revenue & Cash Flow Management

5 Chapter 5: Practice Management — Risk, Insurance & Business Development

5.1 Risk Management & the Firm’s Insurance Portfolio 5.2 Contractual Risk Allocation, Intellectual Property & Dispute Resolution 5.3 Client Requests, Compensation Methods, Project Delivery & Project Risk

6 Chapter 6: Project Management — Team, Resources & Consultants

6.1 Assembling the Project Team: Roles, Authority & Selection Criteria 6.2 Allocating & Managing Project Resources: Hours, Rates & Leveling 6.3 Consultant Selection, Qualifications-Based Selection & Scope Boundaries 6.4 AIA C401: Flow-Through, Consultant Standard of Care, Insurance & Payment

7 Chapter 7: Project Management — Work Planning, Scheduling & Budget Control

7.1 The Project Work Plan & Phase Fee Allocation 7.2 Work Breakdown Structures, Scheduling Methods & Dependency Logic 7.3 Critical Path Calculations, Float & Schedule Compression 7.4 Project Communication: Paths, Instruments, Meetings & the Record 7.5 Monitoring the Project Budget with Earned Value Management 7.6 Scope Creep, Additional Services & Written Authorization

8 Chapter 8: Project Management — Contracts, Approvals & Quality Control

8.1 AIA B101: Initial Information, Standard of Care & Basic Services 8.2 B101: Owner Duties, Cost of the Work, Copyright, Termination & Compensation 8.3 The Owner-Contractor Agreement & A201 Contractor Responsibilities 8.4 A201: Architect Administration, Changes, Claims & Separate Contractors 8.5 Regulatory Compliance, Authorities Having Jurisdiction & Project Approvals 8.6 Documenting a Project for the Specified Delivery Method 8.7 Quality Assurance, Quality Control, Constructability & the Record

9 Chapter 9: Programming & Analysis — Site & Environmental Conditions

9.1 Climate Classification, Solar Geometry & Passive Site Opportunities 9.2 Microclimate, Wind, Topography, Grading & Site Hydrology 9.3 Environmental Due Diligence: CERCLA Liability & Phase I / Phase II Assessments 9.4 Soil Mechanics, Geotechnical Investigation & Foundation Selection 9.5 Vehicular Circulation, Access Management, Parking & Emergency Access

10 Chapter 10: Programming & Analysis — Zoning, Codes & Site Infrastructure

10.1 Pedestrian Circulation, Site Utilities & Contextual Constraints 10.2 Zoning Authority, Euclidean and Form-Based Codes & Bulk Standards 10.3 Non-Conforming Uses, Variances, Easements & Parking Feasibility 10.4 IBC Occupancy Classification, Mixed Occupancy & Incidental Uses 10.5 IBC Construction Types, Fire-Resistance Ratings & Compartmentation

11 Chapter 11: Programming & Analysis — Building Programming & Feasibility

11.1 Programming Methodology, Net vs. Gross Area & Building Efficiency 11.2 Adjacency Matrices, Bubble Diagrams, Blocking & Stacking 11.3 Evaluating an Existing Building Against a Program 11.4 Reviewing Project Budget & Schedule Feasibility Against Scope 11.5 Identifying Building & Structural System Alternatives at Programming

12 Chapter 12: Project Planning & Design — Siting, Configuration, Codes & Life Safety

12.1 Building Siting, Neighborhood Context, Zoning Application & Configuration 12.2 IBC Allowable Area: Tabular Area, Frontage & Sprinkler Increases 12.3 Building Height, Story Limits, Mixed Occupancy & Unlimited Area Buildings 12.4 Means of Egress Components & Occupant Load Calculation 12.5 Exit Count, Remoteness, Egress Capacity, Travel Distance & Dead Ends 12.6 Accessible Routes, Slopes, Protruding Objects & Ramp Design 12.7 Door Clearances, Operating Hardware & Accessible Toilet Room Geometry

13 Chapter 13: Project Planning & Design — Structural & Mechanical Systems

13.1 Selecting Structural Systems: Steel, Concrete, Wood & Masonry 13.2 Lateral Force-Resisting Systems, Wind Loads & Seismic Design 13.3 Thermal Comfort, ASHRAE Standard 55 & Psychrometrics 13.4 HVAC System Typologies, Spatial Allocation & Central Plant Equipment 13.5 Potable Water Supply, Drainage, Waste & Vent Systems 13.6 Electrical Distribution, Emergency Power, Lighting & Daylighting 13.7 Fire Suppression, Standpipes, Conveying, Security & Communications

14 Chapter 14: Project Planning & Design — Envelope, Materials & Cost

14.1 Envelope Thermodynamics, Heat Transfer & Fenestration Performance 14.2 Thermal Bridging, Continuous Insulation & Thermal Mass 14.3 Passive Solar Heating, Natural Ventilation & Daylighting Architecture 14.4 Material Selection Criteria, Fire Performance & Vapor Permeance 14.5 Life Cycle Assessment, Embodied Carbon & Material Transparency 14.6 Galvanic Compatibility, Thermal Movement & Masonry Durability 14.7 Cost Estimating by Phase & Contingency Planning 14.8 Life-Cycle Cost Analysis, Present Value & Value Engineering

15 Chapter 15: Project Development & Documentation — Roofing, Waterproofing & Wall Assemblies

15.1 Low-Slope Roofing Systems, Membranes & Drainage Geometry 15.2 Flashing, Parapets, Copings & Roof Penetration Detailing 15.3 Steep-Slope Roofing & Below-Grade Waterproofing 15.4 Enclosure Control Layers & Rain Screen Cladding Systems 15.5 Vapor Retarders, Permeance Classes & Dew Point Control

16 Chapter 16: Project Development & Documentation — Connections, Coordination & Interiors

16.1 Structural Steel Connections & Base Plate Detailing 16.2 Concrete Reinforcing, Cover & Building Movement Joints 16.3 Sizing Structural, Mechanical, Electrical & Plumbing Components 16.4 Ceiling Plenum Coordination, Clash Detection & Level of Development 16.5 Vertical Chases, Shaft Walls, Through-Penetration Firestopping & Rated Joints 16.6 Interior Partition Framing, Head-of-Wall Details & Rated Gypsum Assemblies 16.7 Sound Isolation, STC, NRC & Reverberation Time 16.8 Door and Frame Construction & Fire Door Assemblies Under NFPA 80 16.9 Hardware Functions, Fire-Protection vs. Fire-Resistance Glazing

17 Chapter 17: Project Development & Documentation — Drawings, Specifications & Estimates

17.1 The National CAD Standard, Sheet Modules & Title Blocks 17.2 Drawing Cross-Referencing, Coordination & Revision Control 17.3 Documenting Site Features: Survey, Civil, Grading, Utilities & Landscape 17.4 The Project Manual & CSI MasterFormat Divisions 17.5 Section Numbering & the CSI Three-Part SectionFormat 17.6 Specification Methods & Document Precedence 17.7 Quantity Takeoff Estimating, General Conditions, Overhead & Alternates

18 Chapter 18: Construction & Evaluation — Procurement, Bidding & Preconstruction

18.1 Procurement Methods & AIA A701 Instructions to Bidders 18.2 Addenda Mechanics & Surety Bonds 18.3 The Preconstruction Conference & Administrative Protocols 18.4 Submittal Schedules, Long-Lead Items, Permits & Special Inspections 18.5 Bid Opening, Bidder Qualification & Discrepancy Rules 18.6 Alternates, Allowances, Unit Prices & Contract Award

19 Chapter 19: Construction & Evaluation — Observation & Contract Administration

19.1 The Architect’s Site Observation Role & the Means and Methods Firewall 19.2 Rejecting Non-Conforming Work, Special Inspections & Field Reports 19.3 Submittal Workflow, Review Responsibility & Action Stamps 19.4 Delegated Design, Design-Assist & Deferred Submittals 19.5 Requests for Information & Architect’s Supplemental Instructions 19.6 Change Orders, Construction Change Directives & Instrument Comparison

20 Chapter 20: Construction & Evaluation — Payment, Closeout & Evaluation

20.1 The Schedule of Values & the Application and Certificate for Payment 20.2 Stored Materials, Retainage, Certification Duties & Withholding 20.3 Substantial Completion & the Punch List Protocol 20.4 The Certificate of Substantial Completion & Its Legal Consequences 20.5 Final Completion, Final Payment & the Closeout Package 20.6 Warranty Administration, the Eleven-Month Walk-Through & Post-Occupancy Evaluation

5.3 Client Requests, Compensation Methods, Project Delivery & Project Risk

Key Takeaways Explain This Topic AI

An incomplete client request — missing site, program, budget, schedule, or delivery method — must be completed before a fee can responsibly be quoted.

Stipulated sum places scope-growth risk on the architect; unlimited hourly places it on the owner; an hourly fee with an upper limit places it on the architect above the cap.

Design-bid-build fixes price only after design is complete, while CM at Risk sets a guaranteed maximum price during design and design-build fixes price earliest.

Under design-build the architect may contract with the design-builder rather than the owner, which removes the architect’s traditional role as impartial interpreter of the contract documents.

Contractual terms disqualify commissions more often than technical fit does, because uninsurable warranties, duties to defend, and uncapped indemnity are not covered by professional liability insurance.

Last updated: September 2026

Practice Management Section 3 looks at projects from the firm's side of the table: which commissions to pursue, how to respond to a client's request, what form of agreement and compensation to propose, how the project will be delivered, and what risk the project brings into the practice.

Responding to a Client Services Request

Before a fee is quoted, the architect has to evaluate the request itself.

Is the request complete? A request that omits the site, the program area, the budget, the schedule, or the delivery method cannot be priced. The correct first action is almost always to obtain the missing information, not to quote a defensive number.

What scope of services is actually needed? Basic services for one client may need to be supplemented with programming, existing-conditions documentation, civil engineering, cost estimating, commissioning, or record modeling. Each is priced separately.

Is there a conflict? The NCARB Rules of Conduct and the AIA Code both require disclosure of any actual or potential conflict of interest. A firm holding a financial interest in a competing development, or representing two bidders on the same site, must disclose and often must decline.

Is there a public interest conflict? Work that would require the architect to conceal a code violation, misrepresent a condition to an authority having jurisdiction, or design around a known safety hazard is refused, not negotiated.

The Go / No-Go Decision

Pursuit costs money — proposal preparation, interviews, and sometimes conceptual design are unbillable overhead. A disciplined go/no-go screen weighs:

  • Factor Favorable Unfavorable
  • Technical fit Firm has completed comparable project types First-of-type with no in-house expertise
  • Client Known, creditworthy, experienced No track record, litigation history, unfunded

Contract terms Standard agreement, standard of care preserved Owner form with warranties, uncapped indemnity, no LoL

  • Fee and schedule Supports the firm's target net multiplier Fee below break-even, compressed schedule
  • Capacity Staff available when the work lands Requires speculative hiring
  • Strategic value Opens a target market or client relationship Distracts from core practice
  • Compensation Methods

The form of compensation allocates risk between owner and architect.

Method How it works Where the risk sits

Stipulated (fixed) sum A lump sum for a defined scope Architect — any scope growth erodes profit unless authorized as an additional service

Percentage of the cost of the work Fee set as a percentage of construction cost Shared — fee tracks cost, but disputes arise when the owner reduces scope

  • Hourly, unlimited Rate per hour, no cap Owner
  • Hourly with an upper limit Rate per hour, capped Architect above the cap
  • Unit cost Fee per unit (per bed, per key, per square foot) Architect if units are redefined

Whatever the method, the agreement must define what triggers additional services , or scope growth becomes uncompensated work.

Project Delivery Methods

Delivery method determines who holds which contract, when price is fixed, and what the architect's construction-phase role is. Expect items that give you an owner's priority — lowest first cost, earliest completion, single point of responsibility — and ask which method fits.

Delivery method Contract structure Price certainty Owner priority it serves

Design-Bid-Build (DBB) Owner holds separate contracts with architect and contractor Fixed at bid, after design is complete Lowest first cost, open competition, fully documented scope

CM as Adviser (CMa) Owner holds architect, CM, and contractor(s); CM is a fee-based consultant Late Independent cost and schedule advice, multiple prime contracts

CM at Risk (CMAR) Owner holds architect and CM/GC; CM/GC delivers a guaranteed maximum price GMP set during design Early price certainty with preconstruction input

Design-Build (DB) Owner holds one contract with a design-build entity Early Single point of responsibility, speed

Integrated Project Delivery (IPD) Multi-party agreement among owner, architect, and contractor Collaborative, shared risk and reward Collaboration, shared incentives, waived claims among parties

Two consequences the exam returns to repeatedly:

Under design-build , the architect may be a subconsultant to the contractor. Privity runs to the design-builder, not the owner, and the architect's traditional role as the owner's impartial interpreter of the contract documents is compromised.

Under CM at Risk and IPD , design and construction overlap. Documents get issued for pricing at levels of completeness that design-bid-build never uses, which changes the firm's internal documentation and quality-control protocol.

Screening a Project for Risk

Objective 3.3 asks how a practice evaluates and mitigates the risk a prospective project brings. The recurring exposures:

  • Risk Mitigation
  • Project type outside firm experience Associate with an experienced firm, or decline

Owner-drafted agreement with warranties or guarantees Negotiate standard-of-care language; the exposure is uninsurable

Uncapped or broad-form indemnity, duty to defend Limit indemnity to the architect's negligence; strike the duty to defend

  • Condensed or fast-tracked schedule Price the coordination risk; document the compression in the agreement
  • Unfunded or thinly capitalized owner Require retainer, verify financing, shorten payment terms
  • Consequential damages exposure Preserve the mutual waiver of consequential damages

Exam Tip: When an item asks whether a firm should pursue a commission, the disqualifying facts are usually contractual, not technical. An uninsurable warranty clause, a duty to defend, or a missing limitation of liability outweighs an attractive fee — because the firm's professional liability policy will not respond to a liability it assumed by contract.

Joint Ventures (JVs) and Teaming Agreements

For large-scale, complex institutional or public projects, firms often associate through Joint Ventures or Teaming Agreements.

Joint Ventures (AIA C101)

A Joint Venture is a distinct legal entity (typically a partnership or LLC) formed by two or more independent firms under AIA C101 to pursue and execute a specific project.

Pass-Through Entity: Functions as a partnership for tax purposes, distributing profits and losses according to agreed ownership percentages.

Joint and Several Liability: Under standard prime contracts with the client, all joint venture partners are jointly and severally liable for 100% of the contract's performance. Even if the internal JV agreement allocates work 70/30, if one firm commits a catastrophic design error or defaults, the client can legally recover the entire 100% judgment from the other firm.

Teaming Agreements & Prime-Consultant Alternative

As a lower-risk alternative, firms frequently enter into a Teaming Agreement during proposal development, transitioning to a standard Prime-Consultant relationship. One firm acts as Prime Architect under AIA B101 and retains the associate firm as an independent consultant under AIA C401. This preserves contractual privity strictly between the owner and prime architect, insulating the consultant from direct owner claims and eliminating joint and several prime liability.