Study guide
6.1 Assembling the Project Team: Roles, Authority & Selection Criteria
Architect Registration Examination ARE 5.0
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: ARE 5.0 Structure, Delivery & Scoring
1.1 The Six Divisions: Items, Durations, Sections & Objectives 1.2 Eligibility, PSI Delivery, Fees, Scheduling & Rescheduling 1.3 Cut Scores, Score Reports, Provisional Feedback & Retakes
2 Chapter 2: Licensure Path, Item Types & Test-Day Strategy
2.1 Education Standard, AXP Hours, Settings & Reporting Rules 2.2 The NCARB Record, Score Validity Policy & Reciprocity 2.3 Item Types, Case Studies, Exam Tools, Breaks & Pacing
3 Chapter 3: Practice Management — Firm Resources, Conduct & the Work Environment
3.1 Assessing Practice Resources: Staffing, Development & Capital Investment 3.2 Regulating the Work Environment: FLSA, Antidiscrimination Law, OSHA & ADA Title III 3.3 Ethical Standards, the NCARB Rules of Conduct & the Standard of Care 3.4 Business Structures, Firm Ownership Rules & Practice-Wide Methodologies
4 Chapter 4: Practice Management — Firm Finances & Financial Health
4.1 Utilization, Overhead, Break-Even & Net Multiplier 4.2 Liquidity, Solvency & Reading Firm Financials Strategically 4.3 Accrual vs. Cash Accounting & the Architectural Balance Sheet 4.4 The Income Statement, Net Operating Revenue & Cash Flow Management
5 Chapter 5: Practice Management — Risk, Insurance & Business Development
5.1 Risk Management & the Firm’s Insurance Portfolio 5.2 Contractual Risk Allocation, Intellectual Property & Dispute Resolution 5.3 Client Requests, Compensation Methods, Project Delivery & Project Risk
6 Chapter 6: Project Management — Team, Resources & Consultants
6.1 Assembling the Project Team: Roles, Authority & Selection Criteria 6.2 Allocating & Managing Project Resources: Hours, Rates & Leveling 6.3 Consultant Selection, Qualifications-Based Selection & Scope Boundaries 6.4 AIA C401: Flow-Through, Consultant Standard of Care, Insurance & Payment
7 Chapter 7: Project Management — Work Planning, Scheduling & Budget Control
7.1 The Project Work Plan & Phase Fee Allocation 7.2 Work Breakdown Structures, Scheduling Methods & Dependency Logic 7.3 Critical Path Calculations, Float & Schedule Compression 7.4 Project Communication: Paths, Instruments, Meetings & the Record 7.5 Monitoring the Project Budget with Earned Value Management 7.6 Scope Creep, Additional Services & Written Authorization
8 Chapter 8: Project Management — Contracts, Approvals & Quality Control
8.1 AIA B101: Initial Information, Standard of Care & Basic Services 8.2 B101: Owner Duties, Cost of the Work, Copyright, Termination & Compensation 8.3 The Owner-Contractor Agreement & A201 Contractor Responsibilities 8.4 A201: Architect Administration, Changes, Claims & Separate Contractors 8.5 Regulatory Compliance, Authorities Having Jurisdiction & Project Approvals 8.6 Documenting a Project for the Specified Delivery Method 8.7 Quality Assurance, Quality Control, Constructability & the Record
9 Chapter 9: Programming & Analysis — Site & Environmental Conditions
9.1 Climate Classification, Solar Geometry & Passive Site Opportunities 9.2 Microclimate, Wind, Topography, Grading & Site Hydrology 9.3 Environmental Due Diligence: CERCLA Liability & Phase I / Phase II Assessments 9.4 Soil Mechanics, Geotechnical Investigation & Foundation Selection 9.5 Vehicular Circulation, Access Management, Parking & Emergency Access
10 Chapter 10: Programming & Analysis — Zoning, Codes & Site Infrastructure
10.1 Pedestrian Circulation, Site Utilities & Contextual Constraints 10.2 Zoning Authority, Euclidean and Form-Based Codes & Bulk Standards 10.3 Non-Conforming Uses, Variances, Easements & Parking Feasibility 10.4 IBC Occupancy Classification, Mixed Occupancy & Incidental Uses 10.5 IBC Construction Types, Fire-Resistance Ratings & Compartmentation
11 Chapter 11: Programming & Analysis — Building Programming & Feasibility
11.1 Programming Methodology, Net vs. Gross Area & Building Efficiency 11.2 Adjacency Matrices, Bubble Diagrams, Blocking & Stacking 11.3 Evaluating an Existing Building Against a Program 11.4 Reviewing Project Budget & Schedule Feasibility Against Scope 11.5 Identifying Building & Structural System Alternatives at Programming
12 Chapter 12: Project Planning & Design — Siting, Configuration, Codes & Life Safety
12.1 Building Siting, Neighborhood Context, Zoning Application & Configuration 12.2 IBC Allowable Area: Tabular Area, Frontage & Sprinkler Increases 12.3 Building Height, Story Limits, Mixed Occupancy & Unlimited Area Buildings 12.4 Means of Egress Components & Occupant Load Calculation 12.5 Exit Count, Remoteness, Egress Capacity, Travel Distance & Dead Ends 12.6 Accessible Routes, Slopes, Protruding Objects & Ramp Design 12.7 Door Clearances, Operating Hardware & Accessible Toilet Room Geometry
13 Chapter 13: Project Planning & Design — Structural & Mechanical Systems
13.1 Selecting Structural Systems: Steel, Concrete, Wood & Masonry 13.2 Lateral Force-Resisting Systems, Wind Loads & Seismic Design 13.3 Thermal Comfort, ASHRAE Standard 55 & Psychrometrics 13.4 HVAC System Typologies, Spatial Allocation & Central Plant Equipment 13.5 Potable Water Supply, Drainage, Waste & Vent Systems 13.6 Electrical Distribution, Emergency Power, Lighting & Daylighting 13.7 Fire Suppression, Standpipes, Conveying, Security & Communications
14 Chapter 14: Project Planning & Design — Envelope, Materials & Cost
14.1 Envelope Thermodynamics, Heat Transfer & Fenestration Performance 14.2 Thermal Bridging, Continuous Insulation & Thermal Mass 14.3 Passive Solar Heating, Natural Ventilation & Daylighting Architecture 14.4 Material Selection Criteria, Fire Performance & Vapor Permeance 14.5 Life Cycle Assessment, Embodied Carbon & Material Transparency 14.6 Galvanic Compatibility, Thermal Movement & Masonry Durability 14.7 Cost Estimating by Phase & Contingency Planning 14.8 Life-Cycle Cost Analysis, Present Value & Value Engineering
15 Chapter 15: Project Development & Documentation — Roofing, Waterproofing & Wall Assemblies
15.1 Low-Slope Roofing Systems, Membranes & Drainage Geometry 15.2 Flashing, Parapets, Copings & Roof Penetration Detailing 15.3 Steep-Slope Roofing & Below-Grade Waterproofing 15.4 Enclosure Control Layers & Rain Screen Cladding Systems 15.5 Vapor Retarders, Permeance Classes & Dew Point Control
16 Chapter 16: Project Development & Documentation — Connections, Coordination & Interiors
16.1 Structural Steel Connections & Base Plate Detailing 16.2 Concrete Reinforcing, Cover & Building Movement Joints 16.3 Sizing Structural, Mechanical, Electrical & Plumbing Components 16.4 Ceiling Plenum Coordination, Clash Detection & Level of Development 16.5 Vertical Chases, Shaft Walls, Through-Penetration Firestopping & Rated Joints 16.6 Interior Partition Framing, Head-of-Wall Details & Rated Gypsum Assemblies 16.7 Sound Isolation, STC, NRC & Reverberation Time 16.8 Door and Frame Construction & Fire Door Assemblies Under NFPA 80 16.9 Hardware Functions, Fire-Protection vs. Fire-Resistance Glazing
17 Chapter 17: Project Development & Documentation — Drawings, Specifications & Estimates
17.1 The National CAD Standard, Sheet Modules & Title Blocks 17.2 Drawing Cross-Referencing, Coordination & Revision Control 17.3 Documenting Site Features: Survey, Civil, Grading, Utilities & Landscape 17.4 The Project Manual & CSI MasterFormat Divisions 17.5 Section Numbering & the CSI Three-Part SectionFormat 17.6 Specification Methods & Document Precedence 17.7 Quantity Takeoff Estimating, General Conditions, Overhead & Alternates
18 Chapter 18: Construction & Evaluation — Procurement, Bidding & Preconstruction
18.1 Procurement Methods & AIA A701 Instructions to Bidders 18.2 Addenda Mechanics & Surety Bonds 18.3 The Preconstruction Conference & Administrative Protocols 18.4 Submittal Schedules, Long-Lead Items, Permits & Special Inspections 18.5 Bid Opening, Bidder Qualification & Discrepancy Rules 18.6 Alternates, Allowances, Unit Prices & Contract Award
19 Chapter 19: Construction & Evaluation — Observation & Contract Administration
19.1 The Architect’s Site Observation Role & the Means and Methods Firewall 19.2 Rejecting Non-Conforming Work, Special Inspections & Field Reports 19.3 Submittal Workflow, Review Responsibility & Action Stamps 19.4 Delegated Design, Design-Assist & Deferred Submittals 19.5 Requests for Information & Architect’s Supplemental Instructions 19.6 Change Orders, Construction Change Directives & Instrument Comparison
20 Chapter 20: Construction & Evaluation — Payment, Closeout & Evaluation
20.1 The Schedule of Values & the Application and Certificate for Payment 20.2 Stored Materials, Retainage, Certification Duties & Withholding 20.3 Substantial Completion & the Punch List Protocol 20.4 The Certificate of Substantial Completion & Its Legal Consequences 20.5 Final Completion, Final Payment & the Closeout Package 20.6 Warranty Administration, the Eleven-Month Walk-Through & Post-Occupancy Evaluation
6.1 Assembling the Project Team: Roles, Authority & Selection Criteria
Key Takeaways Explain This Topic AI
The principal-in-charge holds contractual authority and the client relationship; the project manager controls work plan, budget, and schedule.
The project architect owns technical detailing and code compliance, while BIM and production staff own modeling, sheet assembly, and clash detection.
Team selection criteria are project-driven: building type experience, delivery method experience, jurisdiction familiarity, schedule availability, and cost level.
Exactly one person must hold responsible control over sealed technical submissions — a licensure requirement, not an organizational choice.
Staff continuity from construction documents into construction administration materially reduces RFI volume during construction.
Last updated: September 2026
Introduction to Architectural Project Resourcing
In architectural practice, project management serves as the critical operational bridge connecting design intent, business profitability, and contractual compliance. While firm-wide leadership establishes overarching strategic goals, individual project success hinges on assembling an appropriately skilled project team, actively forecasting labor resources, balancing workload demands, and rigorously managing external consulting engineers. According to The Architect's Handbook of Professional Practice (AHPP) published by the American Institute of Architects (AIA), the Project Management (PjM) division of the ARE 5.0 tests a candidate's ability to orchestrate human capital, optimize billable labor across project phases, and coordinate interdisciplinary teams under standard AIA contractual agreements.
Project Team Organization & Core Roles
An architectural project team is a matrix organization structured to address contractual accountability, project management, technical design, and digital production. Clear delineation of roles is vital to prevent scope gaps, internal friction, and project delays:
Project Role Primary Contractual & Administrative Duties Key Production & Technical Focus Standard Billing Multiplier Impact
Principal-in-Charge (PIC) Contract negotiation, fee agreements, executive client relations, firm legal risk management, dispute escalation High-level design critique, milestone QA/QC reviews, signing and sealing prime contract instruments Low utilization (40%–50%); highest hourly billing rate
Project Manager (PM) Project work planning, fee budgeting, schedule baseline tracking, consultant coordination, client billing, scope management Directing project team workflow, monitoring earned value, managing client meetings and official correspondence Moderate-high utilization (60%–75%); mid-to-high billing rate
Project Architect (PA) Code research, local zoning compliance, technical constructability reviews, specifications coordination Directing document production (CD set), coordinating engineering systems, detailing assemblies, CA field visits High utilization (75%–85%); mid-level billing rate
BIM / Technical Staff Adhering to office BIM/CAD standards, clash detection protocols, model health maintenance 3D model authoring, 2D detail generation, sheet layout, drafting redlines, submittal processing assistance Highest utilization (80%–90%+); entry/junior billing rate
1. Principal-in-Charge (PIC)
The Principal-in-Charge is a partner, shareholder, or owner in the firm who retains ultimate executive and legal accountability for the commission. The PIC signs the prime Owner-Architect Agreement (e.g., AIA Document B101), authorizes billing rates and contract fees, allocates firm capital, and acts as the senior executive escalation point. The PIC does not manage daily task assignments but provides quality assurance reviews at major phase milestones.
2. Project Manager (PM)
The Project Manager leads the execution of the commission from initial kickoff through project closeout. The PM develops and maintains the Project Work Plan (PWP), establishes project schedules, monitors fee budgets, tracks staff hours, prepares monthly client invoices, and manages multi-disciplinary consultant contracts (AIA Document C401). Crucially, the PM is the primary operational liaison to the owner's representative, facilitating communication and securing written authorization for scope changes.
3. Project Architect (PA)
The Project Architect oversees the architectural design documentation and technical integration. The PA researches building codes, life safety regulations, accessibility standards, and municipal ordinances. The PA leads the development of the drawing set and Project Manual (specifications), guides constructability detailing, resolves technical collisions with mechanical, electrical, plumbing (MEP), and structural systems, and conducts on-site field observations during Construction Administration.
4. BIM Specialists & Technical Production Staff
Technical staff—including architectural designers, intern architects, and BIM modelers—generate the graphic models, drawings, and schedules in building information modeling (BIM) platforms such as Autodesk Revit. They execute redlines, construct 3D parametric families, maintain model integrity, run automated clash detection in coordination software (e.g., Navisworks), and organize drawing sheets under the United States National CAD Standard (NCS) and Uniform Drawing System (UDS).
Skill Mapping & Workload Balancing
Staff allocation requires skill mapping —matching specific staff proficiencies and experience levels to project phases. For instance, conceptual and schematic design requires design-oriented staff with strong client presentation skills, whereas the construction documents phase demands rigorous technical detailers and specification writers. Workload balancing ensures that no single team member is overburdened while others experience billable downtime, maintaining overall studio morale and billable efficiency.
Criteria for Assembling the Team
Objective 1.1 is about selection , and the criteria are project-driven rather than availability-driven:
Criterion What it asks Why it decides the assignment
Project type experience Has this person delivered this building type? Healthcare, laboratory, aviation, and high-rise work carry regulatory regimes that do not transfer
Delivery method experience Has this person worked under CM at Risk, design-build, or IPD? Document sequencing and pricing milestones differ by method
Jurisdiction familiarity Does this person know the AHJ and the local amendments? Local amendments and review culture drive permit schedule
Availability across the schedule Is this person free when the project needs them, not just today? A person committed elsewhere in month four is not available
Cost level versus fee plan Does this person's rate fit the budgeted blended rate? Over-qualified staffing silently consumes the fee
Continuity Will this person stay through construction administration? Turnover between CDs and CA is a primary source of RFIs
Two structural rules apply to every team:
One person must hold contractual authority — the principal-in-charge who signs, commits, and owns the client relationship. Diffusing that authority produces conflicting direction to the client.
One person must hold responsible control over the sealed technical submissions. That is a licensure requirement, not an organizational preference.