7.5 Monitoring the Project Budget with Earned Value Management
Architect Registration Examination ARE 5.0
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: ARE 5.0 Structure, Delivery & Scoring
1.1 The Six Divisions: Items, Durations, Sections & Objectives 1.2 Eligibility, PSI Delivery, Fees, Scheduling & Rescheduling 1.3 Cut Scores, Score Reports, Provisional Feedback & Retakes
2 Chapter 2: Licensure Path, Item Types & Test-Day Strategy
2.1 Education Standard, AXP Hours, Settings & Reporting Rules 2.2 The NCARB Record, Score Validity Policy & Reciprocity 2.3 Item Types, Case Studies, Exam Tools, Breaks & Pacing
3 Chapter 3: Practice Management — Firm Resources, Conduct & the Work Environment
3.1 Assessing Practice Resources: Staffing, Development & Capital Investment 3.2 Regulating the Work Environment: FLSA, Antidiscrimination Law, OSHA & ADA Title III 3.3 Ethical Standards, the NCARB Rules of Conduct & the Standard of Care 3.4 Business Structures, Firm Ownership Rules & Practice-Wide Methodologies
4 Chapter 4: Practice Management — Firm Finances & Financial Health
4.1 Utilization, Overhead, Break-Even & Net Multiplier 4.2 Liquidity, Solvency & Reading Firm Financials Strategically 4.3 Accrual vs. Cash Accounting & the Architectural Balance Sheet 4.4 The Income Statement, Net Operating Revenue & Cash Flow Management
5 Chapter 5: Practice Management — Risk, Insurance & Business Development
5.1 Risk Management & the Firm’s Insurance Portfolio 5.2 Contractual Risk Allocation, Intellectual Property & Dispute Resolution 5.3 Client Requests, Compensation Methods, Project Delivery & Project Risk
6 Chapter 6: Project Management — Team, Resources & Consultants
6.1 Assembling the Project Team: Roles, Authority & Selection Criteria 6.2 Allocating & Managing Project Resources: Hours, Rates & Leveling 6.3 Consultant Selection, Qualifications-Based Selection & Scope Boundaries 6.4 AIA C401: Flow-Through, Consultant Standard of Care, Insurance & Payment
7 Chapter 7: Project Management — Work Planning, Scheduling & Budget Control
7.1 The Project Work Plan & Phase Fee Allocation 7.2 Work Breakdown Structures, Scheduling Methods & Dependency Logic 7.3 Critical Path Calculations, Float & Schedule Compression 7.4 Project Communication: Paths, Instruments, Meetings & the Record 7.5 Monitoring the Project Budget with Earned Value Management 7.6 Scope Creep, Additional Services & Written Authorization
8 Chapter 8: Project Management — Contracts, Approvals & Quality Control
8.1 AIA B101: Initial Information, Standard of Care & Basic Services 8.2 B101: Owner Duties, Cost of the Work, Copyright, Termination & Compensation 8.3 The Owner-Contractor Agreement & A201 Contractor Responsibilities 8.4 A201: Architect Administration, Changes, Claims & Separate Contractors 8.5 Regulatory Compliance, Authorities Having Jurisdiction & Project Approvals 8.6 Documenting a Project for the Specified Delivery Method 8.7 Quality Assurance, Quality Control, Constructability & the Record
9 Chapter 9: Programming & Analysis — Site & Environmental Conditions
9.1 Climate Classification, Solar Geometry & Passive Site Opportunities 9.2 Microclimate, Wind, Topography, Grading & Site Hydrology 9.3 Environmental Due Diligence: CERCLA Liability & Phase I / Phase II Assessments 9.4 Soil Mechanics, Geotechnical Investigation & Foundation Selection 9.5 Vehicular Circulation, Access Management, Parking & Emergency Access
10 Chapter 10: Programming & Analysis — Zoning, Codes & Site Infrastructure
10.1 Pedestrian Circulation, Site Utilities & Contextual Constraints 10.2 Zoning Authority, Euclidean and Form-Based Codes & Bulk Standards 10.3 Non-Conforming Uses, Variances, Easements & Parking Feasibility 10.4 IBC Occupancy Classification, Mixed Occupancy & Incidental Uses 10.5 IBC Construction Types, Fire-Resistance Ratings & Compartmentation
11 Chapter 11: Programming & Analysis — Building Programming & Feasibility
11.1 Programming Methodology, Net vs. Gross Area & Building Efficiency 11.2 Adjacency Matrices, Bubble Diagrams, Blocking & Stacking 11.3 Evaluating an Existing Building Against a Program 11.4 Reviewing Project Budget & Schedule Feasibility Against Scope 11.5 Identifying Building & Structural System Alternatives at Programming
12 Chapter 12: Project Planning & Design — Siting, Configuration, Codes & Life Safety
12.1 Building Siting, Neighborhood Context, Zoning Application & Configuration 12.2 IBC Allowable Area: Tabular Area, Frontage & Sprinkler Increases 12.3 Building Height, Story Limits, Mixed Occupancy & Unlimited Area Buildings 12.4 Means of Egress Components & Occupant Load Calculation 12.5 Exit Count, Remoteness, Egress Capacity, Travel Distance & Dead Ends 12.6 Accessible Routes, Slopes, Protruding Objects & Ramp Design 12.7 Door Clearances, Operating Hardware & Accessible Toilet Room Geometry
13 Chapter 13: Project Planning & Design — Structural & Mechanical Systems
13.1 Selecting Structural Systems: Steel, Concrete, Wood & Masonry 13.2 Lateral Force-Resisting Systems, Wind Loads & Seismic Design 13.3 Thermal Comfort, ASHRAE Standard 55 & Psychrometrics 13.4 HVAC System Typologies, Spatial Allocation & Central Plant Equipment 13.5 Potable Water Supply, Drainage, Waste & Vent Systems 13.6 Electrical Distribution, Emergency Power, Lighting & Daylighting 13.7 Fire Suppression, Standpipes, Conveying, Security & Communications
14 Chapter 14: Project Planning & Design — Envelope, Materials & Cost
14.1 Envelope Thermodynamics, Heat Transfer & Fenestration Performance 14.2 Thermal Bridging, Continuous Insulation & Thermal Mass 14.3 Passive Solar Heating, Natural Ventilation & Daylighting Architecture 14.4 Material Selection Criteria, Fire Performance & Vapor Permeance 14.5 Life Cycle Assessment, Embodied Carbon & Material Transparency 14.6 Galvanic Compatibility, Thermal Movement & Masonry Durability 14.7 Cost Estimating by Phase & Contingency Planning 14.8 Life-Cycle Cost Analysis, Present Value & Value Engineering
15 Chapter 15: Project Development & Documentation — Roofing, Waterproofing & Wall Assemblies
15.1 Low-Slope Roofing Systems, Membranes & Drainage Geometry 15.2 Flashing, Parapets, Copings & Roof Penetration Detailing 15.3 Steep-Slope Roofing & Below-Grade Waterproofing 15.4 Enclosure Control Layers & Rain Screen Cladding Systems 15.5 Vapor Retarders, Permeance Classes & Dew Point Control
16 Chapter 16: Project Development & Documentation — Connections, Coordination & Interiors
16.1 Structural Steel Connections & Base Plate Detailing 16.2 Concrete Reinforcing, Cover & Building Movement Joints 16.3 Sizing Structural, Mechanical, Electrical & Plumbing Components 16.4 Ceiling Plenum Coordination, Clash Detection & Level of Development 16.5 Vertical Chases, Shaft Walls, Through-Penetration Firestopping & Rated Joints 16.6 Interior Partition Framing, Head-of-Wall Details & Rated Gypsum Assemblies 16.7 Sound Isolation, STC, NRC & Reverberation Time 16.8 Door and Frame Construction & Fire Door Assemblies Under NFPA 80 16.9 Hardware Functions, Fire-Protection vs. Fire-Resistance Glazing
17 Chapter 17: Project Development & Documentation — Drawings, Specifications & Estimates
17.1 The National CAD Standard, Sheet Modules & Title Blocks 17.2 Drawing Cross-Referencing, Coordination & Revision Control 17.3 Documenting Site Features: Survey, Civil, Grading, Utilities & Landscape 17.4 The Project Manual & CSI MasterFormat Divisions 17.5 Section Numbering & the CSI Three-Part SectionFormat 17.6 Specification Methods & Document Precedence 17.7 Quantity Takeoff Estimating, General Conditions, Overhead & Alternates
18 Chapter 18: Construction & Evaluation — Procurement, Bidding & Preconstruction
18.1 Procurement Methods & AIA A701 Instructions to Bidders 18.2 Addenda Mechanics & Surety Bonds 18.3 The Preconstruction Conference & Administrative Protocols 18.4 Submittal Schedules, Long-Lead Items, Permits & Special Inspections 18.5 Bid Opening, Bidder Qualification & Discrepancy Rules 18.6 Alternates, Allowances, Unit Prices & Contract Award
19 Chapter 19: Construction & Evaluation — Observation & Contract Administration
19.1 The Architect’s Site Observation Role & the Means and Methods Firewall 19.2 Rejecting Non-Conforming Work, Special Inspections & Field Reports 19.3 Submittal Workflow, Review Responsibility & Action Stamps 19.4 Delegated Design, Design-Assist & Deferred Submittals 19.5 Requests for Information & Architect’s Supplemental Instructions 19.6 Change Orders, Construction Change Directives & Instrument Comparison
20 Chapter 20: Construction & Evaluation — Payment, Closeout & Evaluation
20.1 The Schedule of Values & the Application and Certificate for Payment 20.2 Stored Materials, Retainage, Certification Duties & Withholding 20.3 Substantial Completion & the Punch List Protocol 20.4 The Certificate of Substantial Completion & Its Legal Consequences 20.5 Final Completion, Final Payment & the Closeout Package 20.6 Warranty Administration, the Eleven-Month Walk-Through & Post-Occupancy Evaluation
7.5 Monitoring the Project Budget with Earned Value Management
Key Takeaways Explain This Topic AI
Planned value is budgeted work scheduled, earned value is budgeted cost of work performed, and actual cost is what was actually spent.
Cost variance is earned value minus actual cost and schedule variance is earned value minus planned value; negative values signal overrun or delay.
Cost performance index is earned value divided by actual cost and schedule performance index is earned value divided by planned value; values below 1.0 are unfavorable.
Estimate at completion is budget at completion divided by the cost performance index, and estimate to complete is estimate at completion minus actual cost.
Percent of fee spent is not percent complete — earned value exists precisely to separate the two.
Last updated: September 2026
Earned Value Management (EVM) in Architectural Practice
Traditional architectural accounting methods rely on two metrics to monitor project finances: the fees billed to the client and the payroll expenses recorded on employee timesheets. However, comparing billed revenue directly to incurred costs creates a dangerous blind spot. For example, if an architecture firm has expended 75% of its labor fee budget on the Construction Documents phase, leadership might assume the project is on track. But if an objective technical audit reveals that only 50% of the required drawing sheets and specifications are complete, the project is severely over budget and behind schedule.
Earned Value Management (EVM) is an objective project management methodology that integrates project scope, schedule, and cost. It measures the true progress of an architectural commission by translating physical work accomplished into monetary terms.
Core EVM Metrics & Formulas
EVM relies on three fundamental baseline values, two variance calculations, two performance indices, and forecasting metrics:
EVM Metric Alternative Term Formula / Definition Architectural Interpretation
Budget at Completion (BAC) Total Project Budget BAC = Total Approved Labor Budget \text{BAC} = \text{Total Approved Labor Budget} BAC = Total Approved Labor Budget Total direct labor fee allocated to complete the project or phase.
Planned Value (PV) Budgeted Cost of Work Scheduled (BCWS) PV = BAC × Planned % Complete \text{PV} = \text{BAC} \times \text{Planned \% Complete} PV = BAC × Planned % Complete The dollar value of work scheduled to be completed by the reporting date.
Earned Value (EV) Budgeted Cost of Work Performed (BCWP) EV = BAC × Actual % Complete \text{EV} = \text{BAC} \times \text{Actual \% Complete} EV = BAC × Actual % Complete The dollar value of physical work objectively completed by the reporting date.
Actual Cost (AC) Actual Cost of Work Performed (ACWP) AC = Total Direct Costs Incurred \text{AC} = \text{Total Direct Costs Incurred} AC = Total Direct Costs Incurred The actual direct labor payroll cost expended to accomplish the work to date.
Cost Variance (CV) — CV = EV − AC \text{CV} = \text{EV} - \text{AC} CV = EV − AC Difference between work earned and cost spent. Positive = Under Budget; Negative = Over Budget.
Schedule Variance (SV) — SV = EV − PV \text{SV} = \text{EV} - \text{PV} SV = EV − PV Difference between work earned and work planned. Positive = Ahead of Schedule; Negative = Behind Schedule.
Cost Performance Index (CPI) — CPI = EV AC \text{CPI} = \frac{\text{EV}}{\text{AC}} CPI = AC EV Measure of cost efficiency. > 1.0 = Efficient > 1.0 = \text{Efficient} > 1.0 = Efficient ; < 1.0 = Cost Inefficient < 1.0 = \text{Cost Inefficient} < 1.0 = Cost Inefficient .
Schedule Performance Index (SPI) — SPI = EV PV \text{SPI} = \frac{\text{EV}}{\text{PV}} SPI = PV EV Measure of schedule velocity. > 1.0 = Ahead of Schedule > 1.0 = \text{Ahead of Schedule} > 1.0 = Ahead of Schedule ; < 1.0 = Behind Schedule < 1.0 = \text{Behind Schedule} < 1.0 = Behind Schedule .
Estimate at Completion (EAC) — EAC = BAC CPI \text{EAC} = \frac{\text{BAC}}{\text{CPI}} EAC = CPI BAC Expected total cost at project completion assuming current cost efficiency continues.
Estimate to Complete (ETC) — ETC = EAC − AC = BAC − EV CPI \text{ETC} = \text{EAC} - \text{AC} = \frac{\text{BAC} - \text{EV}}{\text{CPI}} ETC = EAC − AC = CPI BAC − EV Expected additional direct funds required to complete all remaining scope.
Variance at Completion (VAC) — VAC = BAC − EAC \text{VAC} = \text{BAC} - \text{EAC} VAC = BAC − EAC Forecasted final cost overrun or surplus. Positive = Under Budget; Negative = Deficit.
Worked Numerical Case Study: Architectural CD Phase
To master EVM for the ARE 5.0 Project Management division, consider a real-world scenario evaluated by an architectural Project Manager:
- Project Parameters
- Project Commission: 60,000 sq ft Commercial Office Building
- Phase: Phase 03 — Construction Documents (CD)
- Phase Labor Budget (BAC): $200,000 direct architectural labor fee
- Total Phase Schedule: 20 weeks
- Reporting Cutoff Date: End of Week 12
- Status at Week 12 Reporting Date
Planned Schedule Progress: 12 weeks elapsed out of 20 total weeks: Planned % Complete = 12 20 = 60 % \text{Planned \% Complete} = \frac{12}{20} = 60\% Planned % Complete = 20 12 = 60% Planned Value (PV) = 60 % × $ 200 , 000 = $ 120 , 000 \text{Planned Value (PV)} = 60\% \times \$200,000 = \$120,000 Planned Value (PV) = 60% × $200 , 000 = $120 , 000
Actual Work Completed (Physical Audit): The Project Architect and PM perform a rigorous sheet-by-sheet audit of the BIM model, detail sheets, and Project Manual specifications. They determine the CD set is objectively 50% complete : Actual % Complete = 50 % \text{Actual \% Complete} = 50\% Actual % Complete = 50% Earned Value (EV) = 50 % × $ 200 , 000 = $ 100 , 000 \text{Earned Value (EV)} = 50\% \times \$200,000 = \$100,000 Earned Value (EV) = 50% × $200 , 000 = $100 , 000
Actual Costs Logged (Timesheet Records): Direct payroll records indicate staff have logged hours totaling $125,000 in direct labor costs on this phase: Actual Cost (AC) = $ 125 , 000 \text{Actual Cost (AC)} = \$125,000 Actual Cost (AC) = $125 , 000
Step 1: Calculate Variances
Cost Variance (CV): CV = EV − AC = $ 100 , 000 − $ 125 , 000 = − $ 25 , 000 \text{CV} = \text{EV} - \text{AC} = \$100,000 - \$125,000 = -\$25,000 CV = EV − AC = $100 , 000 − $125 , 000 = − $25 , 000 Interpretation: Negative Cost Variance ( − $ 25 , 000 -\text{\textdollar}25,000 − $ 25 , 000 ) indicates the project is over budget . The firm has expended $25,000 more than the value of the physical work delivered.
Schedule Variance (SV): SV = EV − PV = $ 100 , 000 − $ 120 , 000 = − $ 20 , 000 \text{SV} = \text{EV} - \text{PV} = \$100,000 - \$120,000 = -\$20,000 SV = EV − PV = $100 , 000 − $120 , 000 = − $20 , 000 Interpretation: Negative Schedule Variance ( − $ 20 , 000 -\text{\textdollar}20,000 − $ 20 , 000 ) indicates the project is behind schedule . The team has completed $20,000 less work than planned for Week 12.
Step 2: Calculate Performance Indices
Cost Performance Index (CPI): CPI = EV AC = $ 100 , 000 $ 125 , 000 = 0.80 \text{CPI} = \frac{\text{EV}}{\text{AC}} = \frac{\$100,000}{\$125,000} = 0.80 CPI = AC EV = $125 , 000 $100 , 000 = 0.80 Interpretation: For every $1.00 of direct billable labor spent, the project is generating only $0.80 of deliverable value. The project is operating at an acute cost inefficiency.
Schedule Performance Index (SPI): SPI = EV PV = $ 100 , 000 $ 120 , 000 ≈ 0.833 \text{SPI} = \frac{\text{EV}}{\text{PV}} = \frac{\$100,000}{\$120,000} \approx 0.833 SPI = PV EV = $120 , 000 $100 , 000 ≈ 0.833 Interpretation: The project team is progressing at only 83.3% of its scheduled velocity.
Step 3: Project Final Forecasts (EAC, ETC, VAC)
Estimate at Completion (EAC): EAC = BAC CPI = $ 200 , 000 0.80 = $ 250 , 000 \text{EAC} = \frac{\text{BAC}}{\text{CPI}} = \frac{\$200,000}{0.80} = \$250,000 EAC = CPI BAC = 0.80 $200 , 000 = $250 , 000 Interpretation: If performance continues at the current pace, the CD phase will cost $250,000 to complete, exhausting the original $200,000 budget and wiping out firm profit.
Estimate to Complete (ETC): ETC = EAC − AC = $ 250 , 000 − $ 125 , 000 = $ 125 , 000 \text{ETC} = \text{EAC} - \text{AC} = \$250,000 - \$125,000 = \$125,000 ETC = EAC − AC = $250 , 000 − $125 , 000 = $125 , 000 Interpretation: The firm must spend an additional $125,000 to finish the remaining 50% of the documents.
Variance at Completion (VAC): VAC = BAC − EAC = $ 200 , 000 − $ 250 , 000 = − $ 50 , 000 \text{VAC} = \text{BAC} - \text{EAC} = \$200,000 - \$250,000 = -\$50,000 VAC = BAC − EAC = $200 , 000 − $250 , 000 = − $50 , 000 Interpretation: Projected net loss on the phase is $50,000 .
Managerial Corrective Actions
Armed with EVM diagnostic data at Week 12 rather than discovering a deficit at Week 20, the PM can execute corrective interventions:
Rebalance the team by replacing high-rate senior personnel with skilled mid-level production staff for standard detailing.
Eliminate redundant drafting details by relying on standard CSI MasterFormat specification references.
Establish rigid bi-weekly milestone checkpoints to ensure drawing production catches up to the planned timeline.