7.3 Critical Path Calculations, Float & Schedule Compression
Architect Registration Examination ARE 5.0
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: ARE 5.0 Structure, Delivery & Scoring
1.1 The Six Divisions: Items, Durations, Sections & Objectives 1.2 Eligibility, PSI Delivery, Fees, Scheduling & Rescheduling 1.3 Cut Scores, Score Reports, Provisional Feedback & Retakes
2 Chapter 2: Licensure Path, Item Types & Test-Day Strategy
2.1 Education Standard, AXP Hours, Settings & Reporting Rules 2.2 The NCARB Record, Score Validity Policy & Reciprocity 2.3 Item Types, Case Studies, Exam Tools, Breaks & Pacing
3 Chapter 3: Practice Management — Firm Resources, Conduct & the Work Environment
3.1 Assessing Practice Resources: Staffing, Development & Capital Investment 3.2 Regulating the Work Environment: FLSA, Antidiscrimination Law, OSHA & ADA Title III 3.3 Ethical Standards, the NCARB Rules of Conduct & the Standard of Care 3.4 Business Structures, Firm Ownership Rules & Practice-Wide Methodologies
4 Chapter 4: Practice Management — Firm Finances & Financial Health
4.1 Utilization, Overhead, Break-Even & Net Multiplier 4.2 Liquidity, Solvency & Reading Firm Financials Strategically 4.3 Accrual vs. Cash Accounting & the Architectural Balance Sheet 4.4 The Income Statement, Net Operating Revenue & Cash Flow Management
5 Chapter 5: Practice Management — Risk, Insurance & Business Development
5.1 Risk Management & the Firm’s Insurance Portfolio 5.2 Contractual Risk Allocation, Intellectual Property & Dispute Resolution 5.3 Client Requests, Compensation Methods, Project Delivery & Project Risk
6 Chapter 6: Project Management — Team, Resources & Consultants
6.1 Assembling the Project Team: Roles, Authority & Selection Criteria 6.2 Allocating & Managing Project Resources: Hours, Rates & Leveling 6.3 Consultant Selection, Qualifications-Based Selection & Scope Boundaries 6.4 AIA C401: Flow-Through, Consultant Standard of Care, Insurance & Payment
7 Chapter 7: Project Management — Work Planning, Scheduling & Budget Control
7.1 The Project Work Plan & Phase Fee Allocation 7.2 Work Breakdown Structures, Scheduling Methods & Dependency Logic 7.3 Critical Path Calculations, Float & Schedule Compression 7.4 Project Communication: Paths, Instruments, Meetings & the Record 7.5 Monitoring the Project Budget with Earned Value Management 7.6 Scope Creep, Additional Services & Written Authorization
8 Chapter 8: Project Management — Contracts, Approvals & Quality Control
8.1 AIA B101: Initial Information, Standard of Care & Basic Services 8.2 B101: Owner Duties, Cost of the Work, Copyright, Termination & Compensation 8.3 The Owner-Contractor Agreement & A201 Contractor Responsibilities 8.4 A201: Architect Administration, Changes, Claims & Separate Contractors 8.5 Regulatory Compliance, Authorities Having Jurisdiction & Project Approvals 8.6 Documenting a Project for the Specified Delivery Method 8.7 Quality Assurance, Quality Control, Constructability & the Record
9 Chapter 9: Programming & Analysis — Site & Environmental Conditions
9.1 Climate Classification, Solar Geometry & Passive Site Opportunities 9.2 Microclimate, Wind, Topography, Grading & Site Hydrology 9.3 Environmental Due Diligence: CERCLA Liability & Phase I / Phase II Assessments 9.4 Soil Mechanics, Geotechnical Investigation & Foundation Selection 9.5 Vehicular Circulation, Access Management, Parking & Emergency Access
10 Chapter 10: Programming & Analysis — Zoning, Codes & Site Infrastructure
10.1 Pedestrian Circulation, Site Utilities & Contextual Constraints 10.2 Zoning Authority, Euclidean and Form-Based Codes & Bulk Standards 10.3 Non-Conforming Uses, Variances, Easements & Parking Feasibility 10.4 IBC Occupancy Classification, Mixed Occupancy & Incidental Uses 10.5 IBC Construction Types, Fire-Resistance Ratings & Compartmentation
11 Chapter 11: Programming & Analysis — Building Programming & Feasibility
11.1 Programming Methodology, Net vs. Gross Area & Building Efficiency 11.2 Adjacency Matrices, Bubble Diagrams, Blocking & Stacking 11.3 Evaluating an Existing Building Against a Program 11.4 Reviewing Project Budget & Schedule Feasibility Against Scope 11.5 Identifying Building & Structural System Alternatives at Programming
12 Chapter 12: Project Planning & Design — Siting, Configuration, Codes & Life Safety
12.1 Building Siting, Neighborhood Context, Zoning Application & Configuration 12.2 IBC Allowable Area: Tabular Area, Frontage & Sprinkler Increases 12.3 Building Height, Story Limits, Mixed Occupancy & Unlimited Area Buildings 12.4 Means of Egress Components & Occupant Load Calculation 12.5 Exit Count, Remoteness, Egress Capacity, Travel Distance & Dead Ends 12.6 Accessible Routes, Slopes, Protruding Objects & Ramp Design 12.7 Door Clearances, Operating Hardware & Accessible Toilet Room Geometry
13 Chapter 13: Project Planning & Design — Structural & Mechanical Systems
13.1 Selecting Structural Systems: Steel, Concrete, Wood & Masonry 13.2 Lateral Force-Resisting Systems, Wind Loads & Seismic Design 13.3 Thermal Comfort, ASHRAE Standard 55 & Psychrometrics 13.4 HVAC System Typologies, Spatial Allocation & Central Plant Equipment 13.5 Potable Water Supply, Drainage, Waste & Vent Systems 13.6 Electrical Distribution, Emergency Power, Lighting & Daylighting 13.7 Fire Suppression, Standpipes, Conveying, Security & Communications
14 Chapter 14: Project Planning & Design — Envelope, Materials & Cost
14.1 Envelope Thermodynamics, Heat Transfer & Fenestration Performance 14.2 Thermal Bridging, Continuous Insulation & Thermal Mass 14.3 Passive Solar Heating, Natural Ventilation & Daylighting Architecture 14.4 Material Selection Criteria, Fire Performance & Vapor Permeance 14.5 Life Cycle Assessment, Embodied Carbon & Material Transparency 14.6 Galvanic Compatibility, Thermal Movement & Masonry Durability 14.7 Cost Estimating by Phase & Contingency Planning 14.8 Life-Cycle Cost Analysis, Present Value & Value Engineering
15 Chapter 15: Project Development & Documentation — Roofing, Waterproofing & Wall Assemblies
15.1 Low-Slope Roofing Systems, Membranes & Drainage Geometry 15.2 Flashing, Parapets, Copings & Roof Penetration Detailing 15.3 Steep-Slope Roofing & Below-Grade Waterproofing 15.4 Enclosure Control Layers & Rain Screen Cladding Systems 15.5 Vapor Retarders, Permeance Classes & Dew Point Control
16 Chapter 16: Project Development & Documentation — Connections, Coordination & Interiors
16.1 Structural Steel Connections & Base Plate Detailing 16.2 Concrete Reinforcing, Cover & Building Movement Joints 16.3 Sizing Structural, Mechanical, Electrical & Plumbing Components 16.4 Ceiling Plenum Coordination, Clash Detection & Level of Development 16.5 Vertical Chases, Shaft Walls, Through-Penetration Firestopping & Rated Joints 16.6 Interior Partition Framing, Head-of-Wall Details & Rated Gypsum Assemblies 16.7 Sound Isolation, STC, NRC & Reverberation Time 16.8 Door and Frame Construction & Fire Door Assemblies Under NFPA 80 16.9 Hardware Functions, Fire-Protection vs. Fire-Resistance Glazing
17 Chapter 17: Project Development & Documentation — Drawings, Specifications & Estimates
17.1 The National CAD Standard, Sheet Modules & Title Blocks 17.2 Drawing Cross-Referencing, Coordination & Revision Control 17.3 Documenting Site Features: Survey, Civil, Grading, Utilities & Landscape 17.4 The Project Manual & CSI MasterFormat Divisions 17.5 Section Numbering & the CSI Three-Part SectionFormat 17.6 Specification Methods & Document Precedence 17.7 Quantity Takeoff Estimating, General Conditions, Overhead & Alternates
18 Chapter 18: Construction & Evaluation — Procurement, Bidding & Preconstruction
18.1 Procurement Methods & AIA A701 Instructions to Bidders 18.2 Addenda Mechanics & Surety Bonds 18.3 The Preconstruction Conference & Administrative Protocols 18.4 Submittal Schedules, Long-Lead Items, Permits & Special Inspections 18.5 Bid Opening, Bidder Qualification & Discrepancy Rules 18.6 Alternates, Allowances, Unit Prices & Contract Award
19 Chapter 19: Construction & Evaluation — Observation & Contract Administration
19.1 The Architect’s Site Observation Role & the Means and Methods Firewall 19.2 Rejecting Non-Conforming Work, Special Inspections & Field Reports 19.3 Submittal Workflow, Review Responsibility & Action Stamps 19.4 Delegated Design, Design-Assist & Deferred Submittals 19.5 Requests for Information & Architect’s Supplemental Instructions 19.6 Change Orders, Construction Change Directives & Instrument Comparison
20 Chapter 20: Construction & Evaluation — Payment, Closeout & Evaluation
20.1 The Schedule of Values & the Application and Certificate for Payment 20.2 Stored Materials, Retainage, Certification Duties & Withholding 20.3 Substantial Completion & the Punch List Protocol 20.4 The Certificate of Substantial Completion & Its Legal Consequences 20.5 Final Completion, Final Payment & the Closeout Package 20.6 Warranty Administration, the Eleven-Month Walk-Through & Post-Occupancy Evaluation
7.3 Critical Path Calculations, Float & Schedule Compression
Key Takeaways Explain This Topic AI
The forward pass computes early start and early finish and yields the project duration; the backward pass computes late start and late finish.
Total float equals late start minus early start, or late finish minus early finish, and activities with zero total float form the critical path.
Crashing shortens critical-path activities by adding labor or overtime, raising direct cost without changing the sequence of work.
Fast-tracking overlaps activities that were planned sequentially, which adds no direct cost but creates coordination risk and potential rework.
Shortening a non-critical activity never shortens the project, and crashing one critical path can expose a second path that becomes critical.
Last updated: September 2026
Critical Path Method (CPM) Calculations
In an Activity-on-Node (AON) CPM diagram, each activity is represented as a node with four critical timing values derived through forward and backward passes: +---------------+---------------+
- | Early Start | Early Finish |
- | (ES) | (EF) |
- +---------------+---------------+
- | Activity Name |
- | (Duration) |
- +---------------+---------------+
- | Late Start | Late Finish |
- | (LS) | (LF) |
- +---------------+---------------+
- The Forward Pass (Early Dates & Project Duration)
The forward pass determines the earliest possible dates an activity can begin and conclude based on logical network predecessors:
Early Start (ES): The earliest time an activity can begin. For the initial project activity, ES = 0 \text{ES} = 0 ES = 0 . For any subsequent activity with multiple predecessors, Early Start equals the maximum of the Early Finish dates of all its immediate predecessors: ES = max ( EF predecessors ) \text{ES} = \max(\text{EF}_{\text{predecessors}}) ES = max ( EF predecessors )
Early Finish (EF): The earliest time an activity can finish: EF = ES + Duration \text{EF} = \text{ES} + \text{Duration} EF = ES + Duration
The Backward Pass (Late Dates & Float Calculation)
Once the forward pass calculates the total project duration, the backward pass determines the latest possible dates activities can occur without delaying the overall project completion date:
Late Finish (LF): For the final activity, Late Finish equals its Early Finish ( LF = EF \text{LF} = \text{EF} LF = EF ). For any preceding activity with multiple successors, Late Finish equals the minimum of the Late Start dates of all its immediate successors: LF = min ( LS successors ) \text{LF} = \min(\text{LS}_{\text{successors}}) LF = min ( LS successors )
Late Start (LS): The latest time an activity can begin without delaying the project: LS = LF − Duration \text{LS} = \text{LF} - \text{Duration} LS = LF − Duration
Understanding Float (Slack)
Total Float (TF): The total amount of time an activity can be delayed from its Early Start without delaying the contractual project completion date: Total Float = LS − ES = LF − EF \text{Total Float} = \text{LS} - \text{ES} = \text{LF} - \text{EF} Total Float = LS − ES = LF − EF
Free Float (FF): The amount of time an activity can be delayed without delaying the Early Start of any immediate successor activity: Free Float = min ( ES successors ) − EF \text{Free Float} = \min(\text{ES}_{\text{successors}}) - \text{EF} Free Float = min ( ES successors ) − EF
The Critical Path
The Critical Path is the continuous sequence of dependent activities through the network with Total Float = 0 . It represents the longest duration path through the project. Any delay to an activity situated on the critical path directly delays the project completion date by an identical amount of time. Activities with positive float can experience delays up to their float threshold without affecting the project completion date.
Schedule Compression Techniques: Crashing vs. Fast-Tracking
When an owner demands that an architectural team accelerate project delivery—or when project delays must be recovered—project managers deploy two primary schedule compression techniques:
Feature Schedule Crashing Fast-Tracking
Operational Definition Adding labor resources or authorized overtime to critical path tasks to shorten duration Executing tasks concurrently that were originally planned in sequential order
Primary Mechanism Overtime hours, reassigning senior staff, hiring outside drafting consultants Overlapping phases (e.g., starting CDs during DD; issuing foundation permits early)
Cost Impact Significantly increases direct project cost (overtime premiums, outside consultant fees) Minimal upfront labor cost addition ; fee remains theoretically constant
Risk Profile Low-to-moderate technical risk ; design logic and review sequences remain intact High project risk ; creates severe potential for coordination clashes and rework
Diminishing Returns Brooks's Law: Adding manpower to late software/design projects can make them later Revisions to upstream design alter already-documented or constructed foundations
1. Schedule Crashing
Crashing focuses strictly on critical path activities where additional labor can compress duration. Crashing non-critical activities wastes money because it merely increases unused float. While crashing guarantees the logical sequence of work remains intact, it incurs diminishing marginal returns: staff fatigue from excessive overtime leads to increased coordination errors, and bringing new personnel onto an active drawing set requires training time that diverts senior staff.
2. Fast-Tracking
Fast-tracking compresses schedules by taking sequential activities and performing them in parallel. A classic architectural example is issuing early bid/permit packages for site excavation and concrete foundations while the architectural superstructure and MEP building enclosure drawings are still undergoing Design Development.
While fast-tracking can cut months from a project timeline without increasing initial labor fees, it introduces immense operational risk. If subsequent structural wind analyses or interior layout modifications require shifting shear walls or column grid lines, already-poured footings or fabricated steel must be demolished or modified via costly construction change orders. Under AIA B101, the architect must warn the owner in writing of the increased risks of rework inherent in fast-tracked project delivery.