7.1 The Project Work Plan & Phase Fee Allocation
Architect Registration Examination ARE 5.0
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: ARE 5.0 Structure, Delivery & Scoring
1.1 The Six Divisions: Items, Durations, Sections & Objectives 1.2 Eligibility, PSI Delivery, Fees, Scheduling & Rescheduling 1.3 Cut Scores, Score Reports, Provisional Feedback & Retakes
2 Chapter 2: Licensure Path, Item Types & Test-Day Strategy
2.1 Education Standard, AXP Hours, Settings & Reporting Rules 2.2 The NCARB Record, Score Validity Policy & Reciprocity 2.3 Item Types, Case Studies, Exam Tools, Breaks & Pacing
3 Chapter 3: Practice Management — Firm Resources, Conduct & the Work Environment
3.1 Assessing Practice Resources: Staffing, Development & Capital Investment 3.2 Regulating the Work Environment: FLSA, Antidiscrimination Law, OSHA & ADA Title III 3.3 Ethical Standards, the NCARB Rules of Conduct & the Standard of Care 3.4 Business Structures, Firm Ownership Rules & Practice-Wide Methodologies
4 Chapter 4: Practice Management — Firm Finances & Financial Health
4.1 Utilization, Overhead, Break-Even & Net Multiplier 4.2 Liquidity, Solvency & Reading Firm Financials Strategically 4.3 Accrual vs. Cash Accounting & the Architectural Balance Sheet 4.4 The Income Statement, Net Operating Revenue & Cash Flow Management
5 Chapter 5: Practice Management — Risk, Insurance & Business Development
5.1 Risk Management & the Firm’s Insurance Portfolio 5.2 Contractual Risk Allocation, Intellectual Property & Dispute Resolution 5.3 Client Requests, Compensation Methods, Project Delivery & Project Risk
6 Chapter 6: Project Management — Team, Resources & Consultants
6.1 Assembling the Project Team: Roles, Authority & Selection Criteria 6.2 Allocating & Managing Project Resources: Hours, Rates & Leveling 6.3 Consultant Selection, Qualifications-Based Selection & Scope Boundaries 6.4 AIA C401: Flow-Through, Consultant Standard of Care, Insurance & Payment
7 Chapter 7: Project Management — Work Planning, Scheduling & Budget Control
7.1 The Project Work Plan & Phase Fee Allocation 7.2 Work Breakdown Structures, Scheduling Methods & Dependency Logic 7.3 Critical Path Calculations, Float & Schedule Compression 7.4 Project Communication: Paths, Instruments, Meetings & the Record 7.5 Monitoring the Project Budget with Earned Value Management 7.6 Scope Creep, Additional Services & Written Authorization
8 Chapter 8: Project Management — Contracts, Approvals & Quality Control
8.1 AIA B101: Initial Information, Standard of Care & Basic Services 8.2 B101: Owner Duties, Cost of the Work, Copyright, Termination & Compensation 8.3 The Owner-Contractor Agreement & A201 Contractor Responsibilities 8.4 A201: Architect Administration, Changes, Claims & Separate Contractors 8.5 Regulatory Compliance, Authorities Having Jurisdiction & Project Approvals 8.6 Documenting a Project for the Specified Delivery Method 8.7 Quality Assurance, Quality Control, Constructability & the Record
9 Chapter 9: Programming & Analysis — Site & Environmental Conditions
9.1 Climate Classification, Solar Geometry & Passive Site Opportunities 9.2 Microclimate, Wind, Topography, Grading & Site Hydrology 9.3 Environmental Due Diligence: CERCLA Liability & Phase I / Phase II Assessments 9.4 Soil Mechanics, Geotechnical Investigation & Foundation Selection 9.5 Vehicular Circulation, Access Management, Parking & Emergency Access
10 Chapter 10: Programming & Analysis — Zoning, Codes & Site Infrastructure
10.1 Pedestrian Circulation, Site Utilities & Contextual Constraints 10.2 Zoning Authority, Euclidean and Form-Based Codes & Bulk Standards 10.3 Non-Conforming Uses, Variances, Easements & Parking Feasibility 10.4 IBC Occupancy Classification, Mixed Occupancy & Incidental Uses 10.5 IBC Construction Types, Fire-Resistance Ratings & Compartmentation
11 Chapter 11: Programming & Analysis — Building Programming & Feasibility
11.1 Programming Methodology, Net vs. Gross Area & Building Efficiency 11.2 Adjacency Matrices, Bubble Diagrams, Blocking & Stacking 11.3 Evaluating an Existing Building Against a Program 11.4 Reviewing Project Budget & Schedule Feasibility Against Scope 11.5 Identifying Building & Structural System Alternatives at Programming
12 Chapter 12: Project Planning & Design — Siting, Configuration, Codes & Life Safety
12.1 Building Siting, Neighborhood Context, Zoning Application & Configuration 12.2 IBC Allowable Area: Tabular Area, Frontage & Sprinkler Increases 12.3 Building Height, Story Limits, Mixed Occupancy & Unlimited Area Buildings 12.4 Means of Egress Components & Occupant Load Calculation 12.5 Exit Count, Remoteness, Egress Capacity, Travel Distance & Dead Ends 12.6 Accessible Routes, Slopes, Protruding Objects & Ramp Design 12.7 Door Clearances, Operating Hardware & Accessible Toilet Room Geometry
13 Chapter 13: Project Planning & Design — Structural & Mechanical Systems
13.1 Selecting Structural Systems: Steel, Concrete, Wood & Masonry 13.2 Lateral Force-Resisting Systems, Wind Loads & Seismic Design 13.3 Thermal Comfort, ASHRAE Standard 55 & Psychrometrics 13.4 HVAC System Typologies, Spatial Allocation & Central Plant Equipment 13.5 Potable Water Supply, Drainage, Waste & Vent Systems 13.6 Electrical Distribution, Emergency Power, Lighting & Daylighting 13.7 Fire Suppression, Standpipes, Conveying, Security & Communications
14 Chapter 14: Project Planning & Design — Envelope, Materials & Cost
14.1 Envelope Thermodynamics, Heat Transfer & Fenestration Performance 14.2 Thermal Bridging, Continuous Insulation & Thermal Mass 14.3 Passive Solar Heating, Natural Ventilation & Daylighting Architecture 14.4 Material Selection Criteria, Fire Performance & Vapor Permeance 14.5 Life Cycle Assessment, Embodied Carbon & Material Transparency 14.6 Galvanic Compatibility, Thermal Movement & Masonry Durability 14.7 Cost Estimating by Phase & Contingency Planning 14.8 Life-Cycle Cost Analysis, Present Value & Value Engineering
15 Chapter 15: Project Development & Documentation — Roofing, Waterproofing & Wall Assemblies
15.1 Low-Slope Roofing Systems, Membranes & Drainage Geometry 15.2 Flashing, Parapets, Copings & Roof Penetration Detailing 15.3 Steep-Slope Roofing & Below-Grade Waterproofing 15.4 Enclosure Control Layers & Rain Screen Cladding Systems 15.5 Vapor Retarders, Permeance Classes & Dew Point Control
16 Chapter 16: Project Development & Documentation — Connections, Coordination & Interiors
16.1 Structural Steel Connections & Base Plate Detailing 16.2 Concrete Reinforcing, Cover & Building Movement Joints 16.3 Sizing Structural, Mechanical, Electrical & Plumbing Components 16.4 Ceiling Plenum Coordination, Clash Detection & Level of Development 16.5 Vertical Chases, Shaft Walls, Through-Penetration Firestopping & Rated Joints 16.6 Interior Partition Framing, Head-of-Wall Details & Rated Gypsum Assemblies 16.7 Sound Isolation, STC, NRC & Reverberation Time 16.8 Door and Frame Construction & Fire Door Assemblies Under NFPA 80 16.9 Hardware Functions, Fire-Protection vs. Fire-Resistance Glazing
17 Chapter 17: Project Development & Documentation — Drawings, Specifications & Estimates
17.1 The National CAD Standard, Sheet Modules & Title Blocks 17.2 Drawing Cross-Referencing, Coordination & Revision Control 17.3 Documenting Site Features: Survey, Civil, Grading, Utilities & Landscape 17.4 The Project Manual & CSI MasterFormat Divisions 17.5 Section Numbering & the CSI Three-Part SectionFormat 17.6 Specification Methods & Document Precedence 17.7 Quantity Takeoff Estimating, General Conditions, Overhead & Alternates
18 Chapter 18: Construction & Evaluation — Procurement, Bidding & Preconstruction
18.1 Procurement Methods & AIA A701 Instructions to Bidders 18.2 Addenda Mechanics & Surety Bonds 18.3 The Preconstruction Conference & Administrative Protocols 18.4 Submittal Schedules, Long-Lead Items, Permits & Special Inspections 18.5 Bid Opening, Bidder Qualification & Discrepancy Rules 18.6 Alternates, Allowances, Unit Prices & Contract Award
19 Chapter 19: Construction & Evaluation — Observation & Contract Administration
19.1 The Architect’s Site Observation Role & the Means and Methods Firewall 19.2 Rejecting Non-Conforming Work, Special Inspections & Field Reports 19.3 Submittal Workflow, Review Responsibility & Action Stamps 19.4 Delegated Design, Design-Assist & Deferred Submittals 19.5 Requests for Information & Architect’s Supplemental Instructions 19.6 Change Orders, Construction Change Directives & Instrument Comparison
20 Chapter 20: Construction & Evaluation — Payment, Closeout & Evaluation
20.1 The Schedule of Values & the Application and Certificate for Payment 20.2 Stored Materials, Retainage, Certification Duties & Withholding 20.3 Substantial Completion & the Punch List Protocol 20.4 The Certificate of Substantial Completion & Its Legal Consequences 20.5 Final Completion, Final Payment & the Closeout Package 20.6 Warranty Administration, the Eleven-Month Walk-Through & Post-Occupancy Evaluation
7.1 The Project Work Plan & Phase Fee Allocation
Key Takeaways Explain This Topic AI
Traditional architectural phase fee allocation is roughly 15% Schematic Design, 20% Design Development, 40% Construction Documents, 5% Bidding, and 20% Construction Administration.
Alternative delivery shifts allocations: CM at Risk and design-build move effort earlier, and fast-tracked work front-loads documentation.
The work plan is re-forecast at every phase boundary and whenever scope, schedule, consultant structure, or actual hours change.
The work plan is the evidence that makes an additional-services claim credible, because it fixes the original deliverable list and hour budget.
A work plan without named deliverables per phase cannot distinguish an in-scope refinement from an out-of-scope request.
Last updated: September 2026
The Project Work Plan (PWP)
In professional architectural practice, an assignment cannot be successfully managed without an active, documented roadmap. The Project Work Plan (PWP) is the primary operational tool used by an architectural Project Manager to define project objectives, assign resources, sequence production tasks, and control fee expenditures. According to The Architect's Handbook of Professional Practice (AHPP), a PWP should be established immediately upon project initiation (or during proposal development) and continuously updated as design parameters evolve.
Five Core Components of a Project Work Plan
A comprehensive Project Work Plan integrates five structural elements:
Scope Statement: Explicitly outlines what is included in the project scope—and equally important, what is excluded. It defines building square footage, site boundaries, targeted sustainability certifications (e.g., LEED or WELL), programmatic requirements, and contractual service boundaries under the AIA B101 agreement.
Deliverables List: A comprehensive inventory of concrete instruments of service required at each milestone. This includes specific drawing sheets (site plans, floor plans, building sections, exterior wall details), 3D digital coordination models, CSI MasterFormat specifications, code compliance summaries, and structural/energy calculation reports.
Master Task Schedule: Defines the project timeline from pre-design through post-occupancy facility evaluation. It incorporates contractual owner review periods, public entitlement and zoning board approvals, building department plan check timelines, bidding/negotiation intervals, and construction duration.
Phase Budget Breakdown: Allocates the total contract fee across individual design phases, engineering disciplines, and profit reserves.
Staffing & Resource Allocation Plan: Maps individual team members (principals, project architects, BIM technicians) to specific work packages, establishing authorized hours per week and tracking planned billable hours against phase fee targets.
Traditional Architectural Phase Fee Allocations
In standard design-bid-build project delivery governed by the AIA Document B101 Owner-Architect Agreement, architectural fees for Basic Services are traditionally distributed across five fundamental project phases:
Design Phase Traditional Fee % Allocation Primary Objectives & Milestone Deliverables
Schematic Design (SD) 15% Conceptual massing, preliminary space planning, site zoning verification, structural grid concepts, schematic outline specifications, preliminary cost of work estimate.
Design Development (DD) 20% Finalizing spatial layouts, fixing architectural dimensions, establishing structural member sizes, routing primary MEP distribution loops, selecting exterior envelope materials.
Construction Documents (CD) 40% Comprehensive, coordinated drawings and technical specifications (Project Manual) required for building permits, contractor bidding, and construction execution. Largest labor expenditure.
Bidding & Negotiation (BN) 5% Issuing bid packages, organizing pre-bid conferences, answering contractor pre-bid questions, issuing addenda, evaluating bids, assisting owner with contractor selection.
Construction Administration (CA) 20% Reviewing submittals and shop drawings, responding to RFIs, conducting periodic on-site field visits, certifying payment applications (G702), preparing change orders (G701), substantial completion inspections.
Total Basic Services Fee 100% Complete professional delivery pipeline under AIA B101 Article 3.
Adapting Allocations to Alternative Delivery Models
While the 15% / 20% / 40% / 5% / 20% distribution represents the traditional industry benchmark, project managers must adjust these percentages based on project delivery methods and unique project constraints:
Integrated Project Delivery (IPD) & Design-Build: Front-loads design effort into Schematic Design and Design Development (e.g., SD = 20%–25%, DD = 25%–30%) to resolve detailing and trade coordination early with the trade contractors, reducing Construction Documents to 25%–30%.
Complex Renovations / Historic Preservation: Requires expanded Schematic Design and field investigation allowances (SD = 20%) to address existing conditions.
Protracted Permitting or Contested Entitlements: May require allocating a dedicated contingency percentage before proceeding to construction documentation.
Converting Phase Fees to Labor Hours
Project managers translate net fee allocations into executable labor budgets using the planned blended hourly billing rate: Phase Net Labor Fee = Gross Phase Fee − Consultant Fees − Reimbursables − Contingency \text{Phase Net Labor Fee} = \text{Gross Phase Fee} - \text{Consultant Fees} - \text{Reimbursables} - \text{Contingency} Phase Net Labor Fee = Gross Phase Fee − Consultant Fees − Reimbursables − Contingency Total Available Staff Hours = Phase Net Labor Fee Blended Hourly Billing Rate \text{Total Available Staff Hours} = \frac{\text{Phase Net Labor Fee}}{\text{Blended Hourly Billing Rate}} Total Available Staff Hours = Blended Hourly Billing Rate Phase Net Labor Fee
If a firm maintains a blended billing rate of $125.00/hour and has a net architectural fee of $100,000 for the Design Development phase, the team has exactly 800 billable hours available ($100,000 / 125.00 = 800 hours 125.00 = 800\text{ hours} 125.00 = 800 hours ).
Keeping the Work Plan Alive
A work plan that is written once and filed is a marketing document, not a management tool. The plan is re-forecast at every phase boundary and whenever any of four things changes:
- Trigger What must be re-forecast
- Scope change, authorized or not Fee, hours, deliverable list, schedule
- Schedule change imposed by the owner Staffing curve, overtime exposure, consultant deadlines
Consultant added, removed, or moved to the owner's agreement Fee, coordination responsibility, deliverable list
Actual hours diverging from budgeted hours Remaining-hours forecast and the corrective action
The work plan is also the instrument that makes an additional services claim credible. When the architect can show the client the original deliverable list, the original hour budget, and the specific request that changed them, the conversation is factual. Without it, the conversation is an argument about memory.