Study guide
7.2 Work Breakdown Structures, Scheduling Methods & Dependency Logic
Architect Registration Examination ARE 5.0
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: ARE 5.0 Structure, Delivery & Scoring
1.1 The Six Divisions: Items, Durations, Sections & Objectives 1.2 Eligibility, PSI Delivery, Fees, Scheduling & Rescheduling 1.3 Cut Scores, Score Reports, Provisional Feedback & Retakes
2 Chapter 2: Licensure Path, Item Types & Test-Day Strategy
2.1 Education Standard, AXP Hours, Settings & Reporting Rules 2.2 The NCARB Record, Score Validity Policy & Reciprocity 2.3 Item Types, Case Studies, Exam Tools, Breaks & Pacing
3 Chapter 3: Practice Management — Firm Resources, Conduct & the Work Environment
3.1 Assessing Practice Resources: Staffing, Development & Capital Investment 3.2 Regulating the Work Environment: FLSA, Antidiscrimination Law, OSHA & ADA Title III 3.3 Ethical Standards, the NCARB Rules of Conduct & the Standard of Care 3.4 Business Structures, Firm Ownership Rules & Practice-Wide Methodologies
4 Chapter 4: Practice Management — Firm Finances & Financial Health
4.1 Utilization, Overhead, Break-Even & Net Multiplier 4.2 Liquidity, Solvency & Reading Firm Financials Strategically 4.3 Accrual vs. Cash Accounting & the Architectural Balance Sheet 4.4 The Income Statement, Net Operating Revenue & Cash Flow Management
5 Chapter 5: Practice Management — Risk, Insurance & Business Development
5.1 Risk Management & the Firm’s Insurance Portfolio 5.2 Contractual Risk Allocation, Intellectual Property & Dispute Resolution 5.3 Client Requests, Compensation Methods, Project Delivery & Project Risk
6 Chapter 6: Project Management — Team, Resources & Consultants
6.1 Assembling the Project Team: Roles, Authority & Selection Criteria 6.2 Allocating & Managing Project Resources: Hours, Rates & Leveling 6.3 Consultant Selection, Qualifications-Based Selection & Scope Boundaries 6.4 AIA C401: Flow-Through, Consultant Standard of Care, Insurance & Payment
7 Chapter 7: Project Management — Work Planning, Scheduling & Budget Control
7.1 The Project Work Plan & Phase Fee Allocation 7.2 Work Breakdown Structures, Scheduling Methods & Dependency Logic 7.3 Critical Path Calculations, Float & Schedule Compression 7.4 Project Communication: Paths, Instruments, Meetings & the Record 7.5 Monitoring the Project Budget with Earned Value Management 7.6 Scope Creep, Additional Services & Written Authorization
8 Chapter 8: Project Management — Contracts, Approvals & Quality Control
8.1 AIA B101: Initial Information, Standard of Care & Basic Services 8.2 B101: Owner Duties, Cost of the Work, Copyright, Termination & Compensation 8.3 The Owner-Contractor Agreement & A201 Contractor Responsibilities 8.4 A201: Architect Administration, Changes, Claims & Separate Contractors 8.5 Regulatory Compliance, Authorities Having Jurisdiction & Project Approvals 8.6 Documenting a Project for the Specified Delivery Method 8.7 Quality Assurance, Quality Control, Constructability & the Record
9 Chapter 9: Programming & Analysis — Site & Environmental Conditions
9.1 Climate Classification, Solar Geometry & Passive Site Opportunities 9.2 Microclimate, Wind, Topography, Grading & Site Hydrology 9.3 Environmental Due Diligence: CERCLA Liability & Phase I / Phase II Assessments 9.4 Soil Mechanics, Geotechnical Investigation & Foundation Selection 9.5 Vehicular Circulation, Access Management, Parking & Emergency Access
10 Chapter 10: Programming & Analysis — Zoning, Codes & Site Infrastructure
10.1 Pedestrian Circulation, Site Utilities & Contextual Constraints 10.2 Zoning Authority, Euclidean and Form-Based Codes & Bulk Standards 10.3 Non-Conforming Uses, Variances, Easements & Parking Feasibility 10.4 IBC Occupancy Classification, Mixed Occupancy & Incidental Uses 10.5 IBC Construction Types, Fire-Resistance Ratings & Compartmentation
11 Chapter 11: Programming & Analysis — Building Programming & Feasibility
11.1 Programming Methodology, Net vs. Gross Area & Building Efficiency 11.2 Adjacency Matrices, Bubble Diagrams, Blocking & Stacking 11.3 Evaluating an Existing Building Against a Program 11.4 Reviewing Project Budget & Schedule Feasibility Against Scope 11.5 Identifying Building & Structural System Alternatives at Programming
12 Chapter 12: Project Planning & Design — Siting, Configuration, Codes & Life Safety
12.1 Building Siting, Neighborhood Context, Zoning Application & Configuration 12.2 IBC Allowable Area: Tabular Area, Frontage & Sprinkler Increases 12.3 Building Height, Story Limits, Mixed Occupancy & Unlimited Area Buildings 12.4 Means of Egress Components & Occupant Load Calculation 12.5 Exit Count, Remoteness, Egress Capacity, Travel Distance & Dead Ends 12.6 Accessible Routes, Slopes, Protruding Objects & Ramp Design 12.7 Door Clearances, Operating Hardware & Accessible Toilet Room Geometry
13 Chapter 13: Project Planning & Design — Structural & Mechanical Systems
13.1 Selecting Structural Systems: Steel, Concrete, Wood & Masonry 13.2 Lateral Force-Resisting Systems, Wind Loads & Seismic Design 13.3 Thermal Comfort, ASHRAE Standard 55 & Psychrometrics 13.4 HVAC System Typologies, Spatial Allocation & Central Plant Equipment 13.5 Potable Water Supply, Drainage, Waste & Vent Systems 13.6 Electrical Distribution, Emergency Power, Lighting & Daylighting 13.7 Fire Suppression, Standpipes, Conveying, Security & Communications
14 Chapter 14: Project Planning & Design — Envelope, Materials & Cost
14.1 Envelope Thermodynamics, Heat Transfer & Fenestration Performance 14.2 Thermal Bridging, Continuous Insulation & Thermal Mass 14.3 Passive Solar Heating, Natural Ventilation & Daylighting Architecture 14.4 Material Selection Criteria, Fire Performance & Vapor Permeance 14.5 Life Cycle Assessment, Embodied Carbon & Material Transparency 14.6 Galvanic Compatibility, Thermal Movement & Masonry Durability 14.7 Cost Estimating by Phase & Contingency Planning 14.8 Life-Cycle Cost Analysis, Present Value & Value Engineering
15 Chapter 15: Project Development & Documentation — Roofing, Waterproofing & Wall Assemblies
15.1 Low-Slope Roofing Systems, Membranes & Drainage Geometry 15.2 Flashing, Parapets, Copings & Roof Penetration Detailing 15.3 Steep-Slope Roofing & Below-Grade Waterproofing 15.4 Enclosure Control Layers & Rain Screen Cladding Systems 15.5 Vapor Retarders, Permeance Classes & Dew Point Control
16 Chapter 16: Project Development & Documentation — Connections, Coordination & Interiors
16.1 Structural Steel Connections & Base Plate Detailing 16.2 Concrete Reinforcing, Cover & Building Movement Joints 16.3 Sizing Structural, Mechanical, Electrical & Plumbing Components 16.4 Ceiling Plenum Coordination, Clash Detection & Level of Development 16.5 Vertical Chases, Shaft Walls, Through-Penetration Firestopping & Rated Joints 16.6 Interior Partition Framing, Head-of-Wall Details & Rated Gypsum Assemblies 16.7 Sound Isolation, STC, NRC & Reverberation Time 16.8 Door and Frame Construction & Fire Door Assemblies Under NFPA 80 16.9 Hardware Functions, Fire-Protection vs. Fire-Resistance Glazing
17 Chapter 17: Project Development & Documentation — Drawings, Specifications & Estimates
17.1 The National CAD Standard, Sheet Modules & Title Blocks 17.2 Drawing Cross-Referencing, Coordination & Revision Control 17.3 Documenting Site Features: Survey, Civil, Grading, Utilities & Landscape 17.4 The Project Manual & CSI MasterFormat Divisions 17.5 Section Numbering & the CSI Three-Part SectionFormat 17.6 Specification Methods & Document Precedence 17.7 Quantity Takeoff Estimating, General Conditions, Overhead & Alternates
18 Chapter 18: Construction & Evaluation — Procurement, Bidding & Preconstruction
18.1 Procurement Methods & AIA A701 Instructions to Bidders 18.2 Addenda Mechanics & Surety Bonds 18.3 The Preconstruction Conference & Administrative Protocols 18.4 Submittal Schedules, Long-Lead Items, Permits & Special Inspections 18.5 Bid Opening, Bidder Qualification & Discrepancy Rules 18.6 Alternates, Allowances, Unit Prices & Contract Award
19 Chapter 19: Construction & Evaluation — Observation & Contract Administration
19.1 The Architect’s Site Observation Role & the Means and Methods Firewall 19.2 Rejecting Non-Conforming Work, Special Inspections & Field Reports 19.3 Submittal Workflow, Review Responsibility & Action Stamps 19.4 Delegated Design, Design-Assist & Deferred Submittals 19.5 Requests for Information & Architect’s Supplemental Instructions 19.6 Change Orders, Construction Change Directives & Instrument Comparison
20 Chapter 20: Construction & Evaluation — Payment, Closeout & Evaluation
20.1 The Schedule of Values & the Application and Certificate for Payment 20.2 Stored Materials, Retainage, Certification Duties & Withholding 20.3 Substantial Completion & the Punch List Protocol 20.4 The Certificate of Substantial Completion & Its Legal Consequences 20.5 Final Completion, Final Payment & the Closeout Package 20.6 Warranty Administration, the Eleven-Month Walk-Through & Post-Occupancy Evaluation
7.2 Work Breakdown Structures, Scheduling Methods & Dependency Logic
Key Takeaways Explain This Topic AI
The 100% Rule requires that child elements of any WBS parent capture the entire parent scope with no omissions and no duplication.
A Gantt chart shows timing but no dependency logic, so it cannot identify which activities are genuinely critical.
CPM is the only common method that produces float, which is what makes it the method the ARE tests quantitatively.
Finish-to-start dominates design schedules, but start-to-start and finish-to-finish relationships model overlapping document production accurately.
A lag extends a path and can change which path is critical; a lead compresses it by allowing a successor to begin early.
Last updated: September 2026
Work Breakdown Structure (WBS)
A Work Breakdown Structure (WBS) is a hierarchical decomposition of the total scope of work to be carried out by the project team. It breaks down complex, multi-year projects into small, distinct, and manageable units:
- Level 1: Project Level (e.g., Civic Health Center)
- Level 2: Phase Level (e.g., Phase 03 - Construction Documents)
- Level 3: Work Package Level (e.g., Architectural Building Enclosure Package)
- Level 4: Task Level (e.g., Exterior Wall Details, Window Head/Jamb/Sill Detailing)
- Level 5: Sub-task / Assignment Level (e.g., Draft Sheet A-501 Detail 4 - Masonry Parapet Flashing)
- The 100% Rule
The cardinal rule of the WBS is the 100% Rule : the Work Breakdown Structure must include 100% of the scope defined by the project contract and encompass all deliverables—internal, external, and interim. The sum of the work at child levels must strictly equal 100% of the work represented by the parent node, with zero omissions and zero scope creep additions.
Work Packages as Management Units
A Work Package is the lowest level in a WBS hierarchy that can be independently budgeted, scheduled, assigned to a specific individual or discipline, and monitored for earned value. In architectural practice, a work package typically correlates to a specific drawing sheet, a specification division, or an engineering coordination package.
Project Scheduling Methodologies
Architectural project managers rely on three scheduling techniques, and each answers a different question. A milestone chart lists key dates — schematic design sign-off, permit application, substantial completion — and gives principals and clients an executive summary with no task-level detail. A Gantt (bar) chart , developed by Henry Gantt, plots activities along a calendar timescale and shows durations and overlaps clearly, but standard bar charts disguise the logical dependencies between tasks. The Critical Path Method (CPM) models activities as a network linked by explicit relationships and calculates the longest path through the project, producing the earliest and latest that each activity can start and finish without extending the completion date.
Scheduling Methods Compared
Three scheduling techniques appear on the exam, and each answers a different question.
Method Form Best answers Weakness
Gantt (bar) chart Horizontal bars on a calendar "When does each task happen?" Shows no logical dependency, so it cannot identify what is truly critical
Critical Path Method (CPM) Network of activities with dependencies "Which delays push the end date?" Requires accurate durations and logic to be meaningful
Milestone schedule Dated list of fixed events "What has the owner committed to?" Carries no task-level detail
CPM is the method the ARE tests quantitatively, because it is the only one that produces float and therefore a defensible answer to "can we absorb this delay?"
Dependency Relationships
CPM logic is built from four relationships, though finish-to-start dominates design schedules:
Finish-to-Start (FS): B cannot start until A finishes. Code analysis finishes before the egress plan starts.
Start-to-Start (SS): B cannot start until A starts. Specification writing starts once drawing production starts.
Finish-to-Finish (FF): B cannot finish until A finishes. The door schedule cannot finish until the floor plans finish.
Start-to-Finish (SF): rare in design work.
Lead and Lag
A lag delays a successor after its predecessor — a two-week jurisdictional review sitting between submission and comment resolution. A lead (negative lag) lets a successor begin before its predecessor completes. Both change the critical path, and both are a frequent source of schedule items where the arithmetic looks wrong until the lag is accounted for.
Exam Tip: The 100% Rule and the critical path answer different questions. The WBS guarantees nothing in scope is missing. The CPM network guarantees you know which missing thing delays the project. A complete WBS with no schedule logic tells you what to do but not what to do first.
Estimating Activity Durations
A schedule is only as good as the durations inside it, and three estimating techniques appear in practice:
Analogous estimating applies the actual duration of a comparable past project or phase to the current one. It is fast and appropriate early, when the design is still undefined, but it inherits whatever was unusual about the comparison project.
Parametric estimating multiplies a measured unit rate by the quantity of work — hours per sheet, hours per specification section, hours per thousand square feet. It is the most defensible method for production tasks in construction documents.
Three-point estimating combines an optimistic duration (O), a most likely duration (M), and a pessimistic duration (P). The PERT weighted mean is (O + 4M + P) ÷ 6 , which pulls the estimate toward the most likely value while still carrying the tails.
Work out a case: a consultant coordination task estimated optimistically at 8 days, most likely at 12 days, and pessimistically at 28 days gives (8 + 48 + 28) ÷ 6 = 14 days — not the 12 days a manager would have written down by instinct. The long pessimistic tail moves the answer, and recognizing that is the point of the technique.
Resource Loading and Leveling
Assigning durations without assigning people produces a schedule nobody can staff. Resource loading attaches hours and a named person or discipline to each activity. Resource leveling then shifts start dates so that no individual is committed beyond their available hours. Leveling consumes float and can push out the completion date, which is why it belongs before the schedule is issued to the client rather than after the client has accepted a date the office cannot staff.
Baselining and Updating the Schedule
Once the client accepts the schedule it becomes the baseline — the fixed reference against which all later performance is measured.
Progress updates record actual start and finish dates and remaining durations at a fixed interval, typically monthly in design.
Variance is measured against the baseline , never against last month's revised schedule. Quietly re-baselining to absorb slippage destroys the only record that shows where the delay came from and who caused it.
A revised baseline is appropriate only when scope changes, and it should be issued formally alongside the change instrument that caused it.
Rolling wave planning handles the reality that distant work cannot be detailed early: near-term activities are scheduled at work-package granularity while later phases stay at phase granularity, and detail is added as each phase approaches.