8.4 A201: Architect Administration, Changes, Claims & Separate Contractors

Architect Registration Examination ARE 5.0

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: ARE 5.0 Structure, Delivery & Scoring

1.1 The Six Divisions: Items, Durations, Sections & Objectives 1.2 Eligibility, PSI Delivery, Fees, Scheduling & Rescheduling 1.3 Cut Scores, Score Reports, Provisional Feedback & Retakes

2 Chapter 2: Licensure Path, Item Types & Test-Day Strategy

2.1 Education Standard, AXP Hours, Settings & Reporting Rules 2.2 The NCARB Record, Score Validity Policy & Reciprocity 2.3 Item Types, Case Studies, Exam Tools, Breaks & Pacing

3 Chapter 3: Practice Management — Firm Resources, Conduct & the Work Environment

3.1 Assessing Practice Resources: Staffing, Development & Capital Investment 3.2 Regulating the Work Environment: FLSA, Antidiscrimination Law, OSHA & ADA Title III 3.3 Ethical Standards, the NCARB Rules of Conduct & the Standard of Care 3.4 Business Structures, Firm Ownership Rules & Practice-Wide Methodologies

4 Chapter 4: Practice Management — Firm Finances & Financial Health

4.1 Utilization, Overhead, Break-Even & Net Multiplier 4.2 Liquidity, Solvency & Reading Firm Financials Strategically 4.3 Accrual vs. Cash Accounting & the Architectural Balance Sheet 4.4 The Income Statement, Net Operating Revenue & Cash Flow Management

5 Chapter 5: Practice Management — Risk, Insurance & Business Development

5.1 Risk Management & the Firm’s Insurance Portfolio 5.2 Contractual Risk Allocation, Intellectual Property & Dispute Resolution 5.3 Client Requests, Compensation Methods, Project Delivery & Project Risk

6 Chapter 6: Project Management — Team, Resources & Consultants

6.1 Assembling the Project Team: Roles, Authority & Selection Criteria 6.2 Allocating & Managing Project Resources: Hours, Rates & Leveling 6.3 Consultant Selection, Qualifications-Based Selection & Scope Boundaries 6.4 AIA C401: Flow-Through, Consultant Standard of Care, Insurance & Payment

7 Chapter 7: Project Management — Work Planning, Scheduling & Budget Control

7.1 The Project Work Plan & Phase Fee Allocation 7.2 Work Breakdown Structures, Scheduling Methods & Dependency Logic 7.3 Critical Path Calculations, Float & Schedule Compression 7.4 Project Communication: Paths, Instruments, Meetings & the Record 7.5 Monitoring the Project Budget with Earned Value Management 7.6 Scope Creep, Additional Services & Written Authorization

8 Chapter 8: Project Management — Contracts, Approvals & Quality Control

8.1 AIA B101: Initial Information, Standard of Care & Basic Services 8.2 B101: Owner Duties, Cost of the Work, Copyright, Termination & Compensation 8.3 The Owner-Contractor Agreement & A201 Contractor Responsibilities 8.4 A201: Architect Administration, Changes, Claims & Separate Contractors 8.5 Regulatory Compliance, Authorities Having Jurisdiction & Project Approvals 8.6 Documenting a Project for the Specified Delivery Method 8.7 Quality Assurance, Quality Control, Constructability & the Record

9 Chapter 9: Programming & Analysis — Site & Environmental Conditions

9.1 Climate Classification, Solar Geometry & Passive Site Opportunities 9.2 Microclimate, Wind, Topography, Grading & Site Hydrology 9.3 Environmental Due Diligence: CERCLA Liability & Phase I / Phase II Assessments 9.4 Soil Mechanics, Geotechnical Investigation & Foundation Selection 9.5 Vehicular Circulation, Access Management, Parking & Emergency Access

10 Chapter 10: Programming & Analysis — Zoning, Codes & Site Infrastructure

10.1 Pedestrian Circulation, Site Utilities & Contextual Constraints 10.2 Zoning Authority, Euclidean and Form-Based Codes & Bulk Standards 10.3 Non-Conforming Uses, Variances, Easements & Parking Feasibility 10.4 IBC Occupancy Classification, Mixed Occupancy & Incidental Uses 10.5 IBC Construction Types, Fire-Resistance Ratings & Compartmentation

11 Chapter 11: Programming & Analysis — Building Programming & Feasibility

11.1 Programming Methodology, Net vs. Gross Area & Building Efficiency 11.2 Adjacency Matrices, Bubble Diagrams, Blocking & Stacking 11.3 Evaluating an Existing Building Against a Program 11.4 Reviewing Project Budget & Schedule Feasibility Against Scope 11.5 Identifying Building & Structural System Alternatives at Programming

12 Chapter 12: Project Planning & Design — Siting, Configuration, Codes & Life Safety

12.1 Building Siting, Neighborhood Context, Zoning Application & Configuration 12.2 IBC Allowable Area: Tabular Area, Frontage & Sprinkler Increases 12.3 Building Height, Story Limits, Mixed Occupancy & Unlimited Area Buildings 12.4 Means of Egress Components & Occupant Load Calculation 12.5 Exit Count, Remoteness, Egress Capacity, Travel Distance & Dead Ends 12.6 Accessible Routes, Slopes, Protruding Objects & Ramp Design 12.7 Door Clearances, Operating Hardware & Accessible Toilet Room Geometry

13 Chapter 13: Project Planning & Design — Structural & Mechanical Systems

13.1 Selecting Structural Systems: Steel, Concrete, Wood & Masonry 13.2 Lateral Force-Resisting Systems, Wind Loads & Seismic Design 13.3 Thermal Comfort, ASHRAE Standard 55 & Psychrometrics 13.4 HVAC System Typologies, Spatial Allocation & Central Plant Equipment 13.5 Potable Water Supply, Drainage, Waste & Vent Systems 13.6 Electrical Distribution, Emergency Power, Lighting & Daylighting 13.7 Fire Suppression, Standpipes, Conveying, Security & Communications

14 Chapter 14: Project Planning & Design — Envelope, Materials & Cost

14.1 Envelope Thermodynamics, Heat Transfer & Fenestration Performance 14.2 Thermal Bridging, Continuous Insulation & Thermal Mass 14.3 Passive Solar Heating, Natural Ventilation & Daylighting Architecture 14.4 Material Selection Criteria, Fire Performance & Vapor Permeance 14.5 Life Cycle Assessment, Embodied Carbon & Material Transparency 14.6 Galvanic Compatibility, Thermal Movement & Masonry Durability 14.7 Cost Estimating by Phase & Contingency Planning 14.8 Life-Cycle Cost Analysis, Present Value & Value Engineering

15 Chapter 15: Project Development & Documentation — Roofing, Waterproofing & Wall Assemblies

15.1 Low-Slope Roofing Systems, Membranes & Drainage Geometry 15.2 Flashing, Parapets, Copings & Roof Penetration Detailing 15.3 Steep-Slope Roofing & Below-Grade Waterproofing 15.4 Enclosure Control Layers & Rain Screen Cladding Systems 15.5 Vapor Retarders, Permeance Classes & Dew Point Control

16 Chapter 16: Project Development & Documentation — Connections, Coordination & Interiors

16.1 Structural Steel Connections & Base Plate Detailing 16.2 Concrete Reinforcing, Cover & Building Movement Joints 16.3 Sizing Structural, Mechanical, Electrical & Plumbing Components 16.4 Ceiling Plenum Coordination, Clash Detection & Level of Development 16.5 Vertical Chases, Shaft Walls, Through-Penetration Firestopping & Rated Joints 16.6 Interior Partition Framing, Head-of-Wall Details & Rated Gypsum Assemblies 16.7 Sound Isolation, STC, NRC & Reverberation Time 16.8 Door and Frame Construction & Fire Door Assemblies Under NFPA 80 16.9 Hardware Functions, Fire-Protection vs. Fire-Resistance Glazing

17 Chapter 17: Project Development & Documentation — Drawings, Specifications & Estimates

17.1 The National CAD Standard, Sheet Modules & Title Blocks 17.2 Drawing Cross-Referencing, Coordination & Revision Control 17.3 Documenting Site Features: Survey, Civil, Grading, Utilities & Landscape 17.4 The Project Manual & CSI MasterFormat Divisions 17.5 Section Numbering & the CSI Three-Part SectionFormat 17.6 Specification Methods & Document Precedence 17.7 Quantity Takeoff Estimating, General Conditions, Overhead & Alternates

18 Chapter 18: Construction & Evaluation — Procurement, Bidding & Preconstruction

18.1 Procurement Methods & AIA A701 Instructions to Bidders 18.2 Addenda Mechanics & Surety Bonds 18.3 The Preconstruction Conference & Administrative Protocols 18.4 Submittal Schedules, Long-Lead Items, Permits & Special Inspections 18.5 Bid Opening, Bidder Qualification & Discrepancy Rules 18.6 Alternates, Allowances, Unit Prices & Contract Award

19 Chapter 19: Construction & Evaluation — Observation & Contract Administration

19.1 The Architect’s Site Observation Role & the Means and Methods Firewall 19.2 Rejecting Non-Conforming Work, Special Inspections & Field Reports 19.3 Submittal Workflow, Review Responsibility & Action Stamps 19.4 Delegated Design, Design-Assist & Deferred Submittals 19.5 Requests for Information & Architect’s Supplemental Instructions 19.6 Change Orders, Construction Change Directives & Instrument Comparison

20 Chapter 20: Construction & Evaluation — Payment, Closeout & Evaluation

20.1 The Schedule of Values & the Application and Certificate for Payment 20.2 Stored Materials, Retainage, Certification Duties & Withholding 20.3 Substantial Completion & the Punch List Protocol 20.4 The Certificate of Substantial Completion & Its Legal Consequences 20.5 Final Completion, Final Payment & the Closeout Package 20.6 Warranty Administration, the Eleven-Month Walk-Through & Post-Occupancy Evaluation

8.4 A201: Architect Administration, Changes, Claims & Separate Contractors

Key Takeaways Explain This Topic AI

The architect visits the site at intervals appropriate to the stage of construction and is not required to make exhaustive or continuous on-site inspections.

The architect may reject non-conforming work, but only the owner has the authority to stop the work.

Article 7 provides three change instruments: the change order, the construction change directive, and the architect’s order for a minor change.

Under Article 6 the owner may perform work with its own forces or separate contractors, and each separate contractor is treated as a contractor under the general conditions.

The contractor must give prompt written notice of apparent defects in a separate contractor’s work, and failing to do so constitutes acceptance of that work as fit to receive its own.

Last updated: September 2026

Architect Contract Administration Under Article 4

Article 4 details the architect's authority and administrative responsibilities during construction:

Site Observation vs. Continuous Inspection (Section 4.2.2)

The architect visits the jobsite at intervals appropriate to the stage of construction to:

Become generally familiar with the progress and quality of the work.

Guard the owner against defects and deficiencies in the work.

Determine in general if the work is being performed in accordance with the Contract Documents.

The architect is explicitly not required to make exhaustive or continuous on-site inspections to check the quality or quantity of the work. The architect does not guarantee the contractor's performance or assume responsibility for the contractor's failure to perform the work in accordance with the contract.

Authority to Reject Work vs. Authority to Stop Work

A critical distinction frequently tested on the ARE is the division between rejecting work and stopping work:

Authority to Reject Work (Section 4.2.6): The architect has the contractual authority to reject work that does not conform to the Contract Documents. The architect may also require special inspection or testing of work whenever necessary.

Authority to Stop Work (Section 2.8): The architect does not have the authority to stop the work . Only the Owner has the legal right to issue a formal written order to stop work if the contractor fails to correct defective work or persistently fails to carry out the work in accordance with the contract. An architect who orders a job shut down may face substantial tort claims from the contractor for delayed performance and idle equipment.

Submittal Review (Section 4.2.7)

The architect reviews and takes action upon contractor submittals (shop drawings, product data, and samples) solely to check for conformance with the design concept expressed in the Contract Documents. Submittals are not Contract Documents. Architect approval of a submittal does not relieve the contractor of responsibility for deviations from the Contract Documents unless the contractor specifically called out the deviation in writing and the architect gave written approval to the specific deviation.

Changes in the Work Under Article 7

Modifications to the construction contract occur through three distinct legal instruments:

Modification Instrument Signatures Required Adjusts Cost? Adjusts Time? Typical Application

Change Order (CO) Owner, Contractor, Architect (All 3) Yes (Agreed) Yes (Agreed) Mutual agreement on added scope, price, and schedule adjustment.

Construction Change Directive (CCD) Owner and Architect (2) Yes (Determined) Yes (Determined) Urgent work directed when contractor and owner disagree on price or time. Contractor must proceed immediately.

Minor Change in the Work (ASI) Architect Only (1) No (None) No (None) Minor clarifications or shifts consistent with design intent that do not affect cost or schedule.

Construction Change Directives (Section 7.3)

When an emergency or critical schedule deadline requires immediate field modification, but the owner and contractor cannot agree on an adjustment in the Contract Sum or Contract Time, the architect and owner issue a Construction Change Directive (CCD) .

Upon receipt of a signed CCD, the contractor is contractually bound to proceed with the work immediately. Cost adjustments under a CCD are calculated based on: (1) mutual acceptance of a lump sum, (2) unit prices stated in the contract, (3) cost to be determined in a manner agreed upon by the parties, or (4) in the absence of agreement, the architect's determination of actual documented net costs of labor, equipment, materials, and standard overhead/profit.

Claims and Disputes Under Article 15

Article 15 establishes the progressive dispute escalation continuum:

Notice of Claim (Section 15.1.3): A Claim is a written demand by either party seeking money, time extension, or interpretation. Claims must be initiated within 21 days after occurrence of the event or within 21 days after the claimant first recognizes the condition.

Initial Decision Maker (IDM - Section 15.2): Claims must be submitted to the IDM for an initial evaluation. The Architect serves as the IDM by default unless another party is appointed. The IDM must review the claim and issue a written decision within 30 days. Rendering an initial decision is a condition precedent to mediation.

Mandatory Mediation (Section 15.3): Mediation is a mandatory condition precedent to binding dispute resolution. If the IDM rejects a claim or fails to render a decision within 30 days, the parties must submit the dispute to non-binding mediation administered by the American Arbitration Association (AAA).

Binding Dispute Resolution (Section 15.4): If mediation fails, the dispute proceeds to the binding method selected in the prime agreement—either Arbitration (binding, private, no formal public appeal) or Litigation (public court system).

Waiver of Consequential Damages (Section 15.1.7): The owner and contractor mutually waive claims for consequential damages (indirect damages such as loss of anticipated profits, rental income, loss of financing, or home office overhead), restricting claims strictly to direct damages.

The Owner's Separate Contractors and Consultants

AIA A201 Article 6 addresses construction by the owner or by separate contractors , and PjM objective 3.4 asks how the architect integrates an owner's consultant's work into the project.

The owner frequently holds contracts outside the architect's agreement — a hazardous-materials abatement contractor, an audiovisual or security integrator, a furniture vendor, an owner-retained commissioning agent, or an owner's civil engineer. The governing rules:

The owner reserves the right to perform work with its own forces or with separate contractors, and must provide for coordination among them.

Each separate contractor is treated as though it were the contractor for purposes of the general conditions, including insurance and mutual access.

The general contractor must give the owner prompt written notice of apparent discrepancies or defects in a separate contractor's work; failing to report constitutes acceptance of that work as fit to receive its own.

The architect coordinates with an owner's consultant but does not direct their work and does not warrant it.

The practical risks the exam tests:

Risk Why it arises Mitigation

Schedule interference Separate contractor work is not in the contractor's schedule Require the owner to supply separate contractors' schedules and incorporate them

Gaps in scope Neither contract includes a connection or a substrate Define interface responsibility in Division 01 and on the drawings

Damaged or defective preceding work One trade builds on another's defect Enforce the notice obligation before covering work

Delay claims Contractor claims impact from the separate contractor Document schedule impacts contemporaneously

Coordination of owner-consultant information Owner's civil or geotechnical data arrives late Fix delivery dates in the owner's agreement, per B101 Article 5