Study guide

8.1 AIA B101: Initial Information, Standard of Care & Basic Services

Architect Registration Examination ARE 5.0

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: ARE 5.0 Structure, Delivery & Scoring

1.1 The Six Divisions: Items, Durations, Sections & Objectives 1.2 Eligibility, PSI Delivery, Fees, Scheduling & Rescheduling 1.3 Cut Scores, Score Reports, Provisional Feedback & Retakes

2 Chapter 2: Licensure Path, Item Types & Test-Day Strategy

2.1 Education Standard, AXP Hours, Settings & Reporting Rules 2.2 The NCARB Record, Score Validity Policy & Reciprocity 2.3 Item Types, Case Studies, Exam Tools, Breaks & Pacing

3 Chapter 3: Practice Management — Firm Resources, Conduct & the Work Environment

3.1 Assessing Practice Resources: Staffing, Development & Capital Investment 3.2 Regulating the Work Environment: FLSA, Antidiscrimination Law, OSHA & ADA Title III 3.3 Ethical Standards, the NCARB Rules of Conduct & the Standard of Care 3.4 Business Structures, Firm Ownership Rules & Practice-Wide Methodologies

4 Chapter 4: Practice Management — Firm Finances & Financial Health

4.1 Utilization, Overhead, Break-Even & Net Multiplier 4.2 Liquidity, Solvency & Reading Firm Financials Strategically 4.3 Accrual vs. Cash Accounting & the Architectural Balance Sheet 4.4 The Income Statement, Net Operating Revenue & Cash Flow Management

5 Chapter 5: Practice Management — Risk, Insurance & Business Development

5.1 Risk Management & the Firm’s Insurance Portfolio 5.2 Contractual Risk Allocation, Intellectual Property & Dispute Resolution 5.3 Client Requests, Compensation Methods, Project Delivery & Project Risk

6 Chapter 6: Project Management — Team, Resources & Consultants

6.1 Assembling the Project Team: Roles, Authority & Selection Criteria 6.2 Allocating & Managing Project Resources: Hours, Rates & Leveling 6.3 Consultant Selection, Qualifications-Based Selection & Scope Boundaries 6.4 AIA C401: Flow-Through, Consultant Standard of Care, Insurance & Payment

7 Chapter 7: Project Management — Work Planning, Scheduling & Budget Control

7.1 The Project Work Plan & Phase Fee Allocation 7.2 Work Breakdown Structures, Scheduling Methods & Dependency Logic 7.3 Critical Path Calculations, Float & Schedule Compression 7.4 Project Communication: Paths, Instruments, Meetings & the Record 7.5 Monitoring the Project Budget with Earned Value Management 7.6 Scope Creep, Additional Services & Written Authorization

8 Chapter 8: Project Management — Contracts, Approvals & Quality Control

8.1 AIA B101: Initial Information, Standard of Care & Basic Services 8.2 B101: Owner Duties, Cost of the Work, Copyright, Termination & Compensation 8.3 The Owner-Contractor Agreement & A201 Contractor Responsibilities 8.4 A201: Architect Administration, Changes, Claims & Separate Contractors 8.5 Regulatory Compliance, Authorities Having Jurisdiction & Project Approvals 8.6 Documenting a Project for the Specified Delivery Method 8.7 Quality Assurance, Quality Control, Constructability & the Record

9 Chapter 9: Programming & Analysis — Site & Environmental Conditions

9.1 Climate Classification, Solar Geometry & Passive Site Opportunities 9.2 Microclimate, Wind, Topography, Grading & Site Hydrology 9.3 Environmental Due Diligence: CERCLA Liability & Phase I / Phase II Assessments 9.4 Soil Mechanics, Geotechnical Investigation & Foundation Selection 9.5 Vehicular Circulation, Access Management, Parking & Emergency Access

10 Chapter 10: Programming & Analysis — Zoning, Codes & Site Infrastructure

10.1 Pedestrian Circulation, Site Utilities & Contextual Constraints 10.2 Zoning Authority, Euclidean and Form-Based Codes & Bulk Standards 10.3 Non-Conforming Uses, Variances, Easements & Parking Feasibility 10.4 IBC Occupancy Classification, Mixed Occupancy & Incidental Uses 10.5 IBC Construction Types, Fire-Resistance Ratings & Compartmentation

11 Chapter 11: Programming & Analysis — Building Programming & Feasibility

11.1 Programming Methodology, Net vs. Gross Area & Building Efficiency 11.2 Adjacency Matrices, Bubble Diagrams, Blocking & Stacking 11.3 Evaluating an Existing Building Against a Program 11.4 Reviewing Project Budget & Schedule Feasibility Against Scope 11.5 Identifying Building & Structural System Alternatives at Programming

12 Chapter 12: Project Planning & Design — Siting, Configuration, Codes & Life Safety

12.1 Building Siting, Neighborhood Context, Zoning Application & Configuration 12.2 IBC Allowable Area: Tabular Area, Frontage & Sprinkler Increases 12.3 Building Height, Story Limits, Mixed Occupancy & Unlimited Area Buildings 12.4 Means of Egress Components & Occupant Load Calculation 12.5 Exit Count, Remoteness, Egress Capacity, Travel Distance & Dead Ends 12.6 Accessible Routes, Slopes, Protruding Objects & Ramp Design 12.7 Door Clearances, Operating Hardware & Accessible Toilet Room Geometry

13 Chapter 13: Project Planning & Design — Structural & Mechanical Systems

13.1 Selecting Structural Systems: Steel, Concrete, Wood & Masonry 13.2 Lateral Force-Resisting Systems, Wind Loads & Seismic Design 13.3 Thermal Comfort, ASHRAE Standard 55 & Psychrometrics 13.4 HVAC System Typologies, Spatial Allocation & Central Plant Equipment 13.5 Potable Water Supply, Drainage, Waste & Vent Systems 13.6 Electrical Distribution, Emergency Power, Lighting & Daylighting 13.7 Fire Suppression, Standpipes, Conveying, Security & Communications

14 Chapter 14: Project Planning & Design — Envelope, Materials & Cost

14.1 Envelope Thermodynamics, Heat Transfer & Fenestration Performance 14.2 Thermal Bridging, Continuous Insulation & Thermal Mass 14.3 Passive Solar Heating, Natural Ventilation & Daylighting Architecture 14.4 Material Selection Criteria, Fire Performance & Vapor Permeance 14.5 Life Cycle Assessment, Embodied Carbon & Material Transparency 14.6 Galvanic Compatibility, Thermal Movement & Masonry Durability 14.7 Cost Estimating by Phase & Contingency Planning 14.8 Life-Cycle Cost Analysis, Present Value & Value Engineering

15 Chapter 15: Project Development & Documentation — Roofing, Waterproofing & Wall Assemblies

15.1 Low-Slope Roofing Systems, Membranes & Drainage Geometry 15.2 Flashing, Parapets, Copings & Roof Penetration Detailing 15.3 Steep-Slope Roofing & Below-Grade Waterproofing 15.4 Enclosure Control Layers & Rain Screen Cladding Systems 15.5 Vapor Retarders, Permeance Classes & Dew Point Control

16 Chapter 16: Project Development & Documentation — Connections, Coordination & Interiors

16.1 Structural Steel Connections & Base Plate Detailing 16.2 Concrete Reinforcing, Cover & Building Movement Joints 16.3 Sizing Structural, Mechanical, Electrical & Plumbing Components 16.4 Ceiling Plenum Coordination, Clash Detection & Level of Development 16.5 Vertical Chases, Shaft Walls, Through-Penetration Firestopping & Rated Joints 16.6 Interior Partition Framing, Head-of-Wall Details & Rated Gypsum Assemblies 16.7 Sound Isolation, STC, NRC & Reverberation Time 16.8 Door and Frame Construction & Fire Door Assemblies Under NFPA 80 16.9 Hardware Functions, Fire-Protection vs. Fire-Resistance Glazing

17 Chapter 17: Project Development & Documentation — Drawings, Specifications & Estimates

17.1 The National CAD Standard, Sheet Modules & Title Blocks 17.2 Drawing Cross-Referencing, Coordination & Revision Control 17.3 Documenting Site Features: Survey, Civil, Grading, Utilities & Landscape 17.4 The Project Manual & CSI MasterFormat Divisions 17.5 Section Numbering & the CSI Three-Part SectionFormat 17.6 Specification Methods & Document Precedence 17.7 Quantity Takeoff Estimating, General Conditions, Overhead & Alternates

18 Chapter 18: Construction & Evaluation — Procurement, Bidding & Preconstruction

18.1 Procurement Methods & AIA A701 Instructions to Bidders 18.2 Addenda Mechanics & Surety Bonds 18.3 The Preconstruction Conference & Administrative Protocols 18.4 Submittal Schedules, Long-Lead Items, Permits & Special Inspections 18.5 Bid Opening, Bidder Qualification & Discrepancy Rules 18.6 Alternates, Allowances, Unit Prices & Contract Award

19 Chapter 19: Construction & Evaluation — Observation & Contract Administration

19.1 The Architect’s Site Observation Role & the Means and Methods Firewall 19.2 Rejecting Non-Conforming Work, Special Inspections & Field Reports 19.3 Submittal Workflow, Review Responsibility & Action Stamps 19.4 Delegated Design, Design-Assist & Deferred Submittals 19.5 Requests for Information & Architect’s Supplemental Instructions 19.6 Change Orders, Construction Change Directives & Instrument Comparison

20 Chapter 20: Construction & Evaluation — Payment, Closeout & Evaluation

20.1 The Schedule of Values & the Application and Certificate for Payment 20.2 Stored Materials, Retainage, Certification Duties & Withholding 20.3 Substantial Completion & the Punch List Protocol 20.4 The Certificate of Substantial Completion & Its Legal Consequences 20.5 Final Completion, Final Payment & the Closeout Package 20.6 Warranty Administration, the Eleven-Month Walk-Through & Post-Occupancy Evaluation

8.1 AIA B101: Initial Information, Standard of Care & Basic Services

Key Takeaways Explain This Topic AI

Initial Information fixes program, budget, schedule, and delivery method, and a material change to it entitles the architect to an equitable adjustment.

B101 Article 2 states the standard of care as the skill and care of an architect performing similar services under similar circumstances in the same locality.

Basic services comprise schematic design, design development, construction documents, bidding or negotiation, and construction administration.

B101 states quantitative limits on basic services, such as the number of site visits and submittal reviews included, and exceeding them is an additional service.

Supplemental services are identified and priced at the time of signing, while additional services arise later and require notice and authorization.

Last updated: September 2026

The AIA Document B101™–2017 Standard Form of Agreement Between Owner and Architect is the preeminent contract template in United States architectural practice for design-bid-build project delivery. As the prime agreement establishing the legal relationship between the client (Owner) and the design lead (Architect), B101 defines professional scope, compensation, allocation of risks, and ownership of intellectual property. Understanding the specific mechanics of its articles is critical for passing the ARE 5.0 Project Management (PjM) and Practice Management (PcM) divisions.

Article 1: Initial Information and Project Parameters

Article 1 establishes the baseline assumptions upon which the agreement is executed. It defines:

Project Parameters: The owner's program, physical site characteristics, legal parameters, zoning constraints, and sustainable design objectives.

Budget and Schedule: The owner's budget for the Cost of the Work, project milestone dates, and the anticipated procurement or bidding method.

Project Team Representatives: The identification of the owner's authorized representative (who holds legal authority to bind the owner), the architect's designated project manager, and required specialty consultants.

Reliance Clause: Section 1.2 explicitly provides that the architect is entitled to rely on the accuracy and completeness of all information provided by the owner. If initial information changes materially during project progression, the architect is contractually entitled to adjustments in both project schedule and professional compensation.

Article 2: Standard of Care vs. Uninsurable Guarantees

Section 2.2 defines the legal standard by which the architect's professional performance is evaluated:

"The Architect shall perform its services consistent with the professional skill and care ordinarily provided by architects practicing in the same or similar locality under the same or similar circumstances."

Under common law, architects are judged by professional competence, not perfection. Custom construction involves thousands of variables, and design documents are rarely without minor discrepancies. Crucially, the architect must never agree to contractual warranties, guarantees of perfection, or strict liability clauses inserted by owners.

Professional Liability Insurance (PLI / Errors & Omissions) policies are underwritten strictly to cover common law negligence. PLI policies contain explicit exclusions for contractual liabilities assumed by an architect that exceed the common law standard of care. If an architect warrants that drawings will be "100% error-free" or "strictly compliant with every code," any discrepancy creates an uninsurable breach of contract that the insurer will refuse to defend, exposing the firm to direct personal liability.

Article 3: Scope of Architect's Basic Services

Basic Services under Article 3 comprise the five sequential phases of traditional project delivery:

Schematic Design (SD): Review the owner's program, site conditions, codes, and laws; evaluate alternative design approaches; prepare schematic drawings (site plan, floor plans, building sections, elevations); and submit a preliminary estimate of the Cost of the Work.

Design Development (DD): Refine schematic concepts into coordinated systems; establish dimensions, typical construction assemblies, structural systems, and MEP systems; prepare outline specifications; and update the cost estimate.

Construction Documents (CD): Prepare fully detailed drawings and specifications setting forth requirements for construction, permitting, and bidding; incorporate requirements of governmental authorities; and provide a final pre-bid update to the Cost of the Work estimate.

Procurement (Bidding or Negotiation): Assist the owner in preparing bidding documents, distribute sets to bidders, maintain bid logs, conduct pre-bid conferences, issue addenda in response to bidder questions, and analyze competitive bids or proposals.

Construction Phase Services: Administer the contract for construction in accordance with AIA Document A201™–2017 General Conditions. The architect acts as the owner's representative, conducts periodic site visits, reviews contractor submittals and shop drawings, issues payment certificates, evaluates change orders, and conducts inspections to determine Substantial Completion and Final Completion.

Quantitative Limits on Basic Services

To prevent scope creep during construction administration, Section 4.2.3 requires the parties to insert explicit numerical caps into the contract:

Maximum number of reviews per contractor submittal (typically 2).

Maximum number of site visits during construction (e.g., bi-weekly, or a fixed total such as 24 visits).

Maximum number of inspections for Substantial Completion and Final Completion (typically 1 or 2).

If construction delays or poor contractor performance require the architect to exceed these numbers through no fault of their own, the additional visits and reviews are compensated as Additional Services .

Article 4: Supplemental Services vs. Additional Services

AIA B101-2017 establishes a vital conceptual boundary between Supplemental Services and Additional Services:

Supplemental Services (Section 4.1): Design services identified and negotiated at the time of contract execution. These are enumerated in a comprehensive table where responsibility (Architect, Owner, or Not Provided) and compensation method are established upfront. Common examples include programming, existing facilities surveys, historic preservation, building information modeling (BIM) management, commissioning, tenant-related fit-out design, and LEED certification.

Additional Services (Section 4.2): Unanticipated services that arise during project execution due to changed circumstances beyond the architect's control. These include:

Material changes in project scope, size, quality, complexity, budget, or delivery method.

Enactment of new codes, regulations, or zoning laws after document completion.

Evaluating an extensive volume of contractor substitution requests or RFIs.

Services necessitated by contractor default, owner termination, major fire, or catastrophic site casualty.

Preparation for and attendance at public hearings or dispute resolution proceedings.

The architect must notify the owner in writing promptly upon determining that an Additional Service is required, and must receive written authorization before proceeding.