8.2 B101: Owner Duties, Cost of the Work, Copyright, Termination & Compensation

Architect Registration Examination ARE 5.0

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: ARE 5.0 Structure, Delivery & Scoring

1.1 The Six Divisions: Items, Durations, Sections & Objectives 1.2 Eligibility, PSI Delivery, Fees, Scheduling & Rescheduling 1.3 Cut Scores, Score Reports, Provisional Feedback & Retakes

2 Chapter 2: Licensure Path, Item Types & Test-Day Strategy

2.1 Education Standard, AXP Hours, Settings & Reporting Rules 2.2 The NCARB Record, Score Validity Policy & Reciprocity 2.3 Item Types, Case Studies, Exam Tools, Breaks & Pacing

3 Chapter 3: Practice Management — Firm Resources, Conduct & the Work Environment

3.1 Assessing Practice Resources: Staffing, Development & Capital Investment 3.2 Regulating the Work Environment: FLSA, Antidiscrimination Law, OSHA & ADA Title III 3.3 Ethical Standards, the NCARB Rules of Conduct & the Standard of Care 3.4 Business Structures, Firm Ownership Rules & Practice-Wide Methodologies

4 Chapter 4: Practice Management — Firm Finances & Financial Health

4.1 Utilization, Overhead, Break-Even & Net Multiplier 4.2 Liquidity, Solvency & Reading Firm Financials Strategically 4.3 Accrual vs. Cash Accounting & the Architectural Balance Sheet 4.4 The Income Statement, Net Operating Revenue & Cash Flow Management

5 Chapter 5: Practice Management — Risk, Insurance & Business Development

5.1 Risk Management & the Firm’s Insurance Portfolio 5.2 Contractual Risk Allocation, Intellectual Property & Dispute Resolution 5.3 Client Requests, Compensation Methods, Project Delivery & Project Risk

6 Chapter 6: Project Management — Team, Resources & Consultants

6.1 Assembling the Project Team: Roles, Authority & Selection Criteria 6.2 Allocating & Managing Project Resources: Hours, Rates & Leveling 6.3 Consultant Selection, Qualifications-Based Selection & Scope Boundaries 6.4 AIA C401: Flow-Through, Consultant Standard of Care, Insurance & Payment

7 Chapter 7: Project Management — Work Planning, Scheduling & Budget Control

7.1 The Project Work Plan & Phase Fee Allocation 7.2 Work Breakdown Structures, Scheduling Methods & Dependency Logic 7.3 Critical Path Calculations, Float & Schedule Compression 7.4 Project Communication: Paths, Instruments, Meetings & the Record 7.5 Monitoring the Project Budget with Earned Value Management 7.6 Scope Creep, Additional Services & Written Authorization

8 Chapter 8: Project Management — Contracts, Approvals & Quality Control

8.1 AIA B101: Initial Information, Standard of Care & Basic Services 8.2 B101: Owner Duties, Cost of the Work, Copyright, Termination & Compensation 8.3 The Owner-Contractor Agreement & A201 Contractor Responsibilities 8.4 A201: Architect Administration, Changes, Claims & Separate Contractors 8.5 Regulatory Compliance, Authorities Having Jurisdiction & Project Approvals 8.6 Documenting a Project for the Specified Delivery Method 8.7 Quality Assurance, Quality Control, Constructability & the Record

9 Chapter 9: Programming & Analysis — Site & Environmental Conditions

9.1 Climate Classification, Solar Geometry & Passive Site Opportunities 9.2 Microclimate, Wind, Topography, Grading & Site Hydrology 9.3 Environmental Due Diligence: CERCLA Liability & Phase I / Phase II Assessments 9.4 Soil Mechanics, Geotechnical Investigation & Foundation Selection 9.5 Vehicular Circulation, Access Management, Parking & Emergency Access

10 Chapter 10: Programming & Analysis — Zoning, Codes & Site Infrastructure

10.1 Pedestrian Circulation, Site Utilities & Contextual Constraints 10.2 Zoning Authority, Euclidean and Form-Based Codes & Bulk Standards 10.3 Non-Conforming Uses, Variances, Easements & Parking Feasibility 10.4 IBC Occupancy Classification, Mixed Occupancy & Incidental Uses 10.5 IBC Construction Types, Fire-Resistance Ratings & Compartmentation

11 Chapter 11: Programming & Analysis — Building Programming & Feasibility

11.1 Programming Methodology, Net vs. Gross Area & Building Efficiency 11.2 Adjacency Matrices, Bubble Diagrams, Blocking & Stacking 11.3 Evaluating an Existing Building Against a Program 11.4 Reviewing Project Budget & Schedule Feasibility Against Scope 11.5 Identifying Building & Structural System Alternatives at Programming

12 Chapter 12: Project Planning & Design — Siting, Configuration, Codes & Life Safety

12.1 Building Siting, Neighborhood Context, Zoning Application & Configuration 12.2 IBC Allowable Area: Tabular Area, Frontage & Sprinkler Increases 12.3 Building Height, Story Limits, Mixed Occupancy & Unlimited Area Buildings 12.4 Means of Egress Components & Occupant Load Calculation 12.5 Exit Count, Remoteness, Egress Capacity, Travel Distance & Dead Ends 12.6 Accessible Routes, Slopes, Protruding Objects & Ramp Design 12.7 Door Clearances, Operating Hardware & Accessible Toilet Room Geometry

13 Chapter 13: Project Planning & Design — Structural & Mechanical Systems

13.1 Selecting Structural Systems: Steel, Concrete, Wood & Masonry 13.2 Lateral Force-Resisting Systems, Wind Loads & Seismic Design 13.3 Thermal Comfort, ASHRAE Standard 55 & Psychrometrics 13.4 HVAC System Typologies, Spatial Allocation & Central Plant Equipment 13.5 Potable Water Supply, Drainage, Waste & Vent Systems 13.6 Electrical Distribution, Emergency Power, Lighting & Daylighting 13.7 Fire Suppression, Standpipes, Conveying, Security & Communications

14 Chapter 14: Project Planning & Design — Envelope, Materials & Cost

14.1 Envelope Thermodynamics, Heat Transfer & Fenestration Performance 14.2 Thermal Bridging, Continuous Insulation & Thermal Mass 14.3 Passive Solar Heating, Natural Ventilation & Daylighting Architecture 14.4 Material Selection Criteria, Fire Performance & Vapor Permeance 14.5 Life Cycle Assessment, Embodied Carbon & Material Transparency 14.6 Galvanic Compatibility, Thermal Movement & Masonry Durability 14.7 Cost Estimating by Phase & Contingency Planning 14.8 Life-Cycle Cost Analysis, Present Value & Value Engineering

15 Chapter 15: Project Development & Documentation — Roofing, Waterproofing & Wall Assemblies

15.1 Low-Slope Roofing Systems, Membranes & Drainage Geometry 15.2 Flashing, Parapets, Copings & Roof Penetration Detailing 15.3 Steep-Slope Roofing & Below-Grade Waterproofing 15.4 Enclosure Control Layers & Rain Screen Cladding Systems 15.5 Vapor Retarders, Permeance Classes & Dew Point Control

16 Chapter 16: Project Development & Documentation — Connections, Coordination & Interiors

16.1 Structural Steel Connections & Base Plate Detailing 16.2 Concrete Reinforcing, Cover & Building Movement Joints 16.3 Sizing Structural, Mechanical, Electrical & Plumbing Components 16.4 Ceiling Plenum Coordination, Clash Detection & Level of Development 16.5 Vertical Chases, Shaft Walls, Through-Penetration Firestopping & Rated Joints 16.6 Interior Partition Framing, Head-of-Wall Details & Rated Gypsum Assemblies 16.7 Sound Isolation, STC, NRC & Reverberation Time 16.8 Door and Frame Construction & Fire Door Assemblies Under NFPA 80 16.9 Hardware Functions, Fire-Protection vs. Fire-Resistance Glazing

17 Chapter 17: Project Development & Documentation — Drawings, Specifications & Estimates

17.1 The National CAD Standard, Sheet Modules & Title Blocks 17.2 Drawing Cross-Referencing, Coordination & Revision Control 17.3 Documenting Site Features: Survey, Civil, Grading, Utilities & Landscape 17.4 The Project Manual & CSI MasterFormat Divisions 17.5 Section Numbering & the CSI Three-Part SectionFormat 17.6 Specification Methods & Document Precedence 17.7 Quantity Takeoff Estimating, General Conditions, Overhead & Alternates

18 Chapter 18: Construction & Evaluation — Procurement, Bidding & Preconstruction

18.1 Procurement Methods & AIA A701 Instructions to Bidders 18.2 Addenda Mechanics & Surety Bonds 18.3 The Preconstruction Conference & Administrative Protocols 18.4 Submittal Schedules, Long-Lead Items, Permits & Special Inspections 18.5 Bid Opening, Bidder Qualification & Discrepancy Rules 18.6 Alternates, Allowances, Unit Prices & Contract Award

19 Chapter 19: Construction & Evaluation — Observation & Contract Administration

19.1 The Architect’s Site Observation Role & the Means and Methods Firewall 19.2 Rejecting Non-Conforming Work, Special Inspections & Field Reports 19.3 Submittal Workflow, Review Responsibility & Action Stamps 19.4 Delegated Design, Design-Assist & Deferred Submittals 19.5 Requests for Information & Architect’s Supplemental Instructions 19.6 Change Orders, Construction Change Directives & Instrument Comparison

20 Chapter 20: Construction & Evaluation — Payment, Closeout & Evaluation

20.1 The Schedule of Values & the Application and Certificate for Payment 20.2 Stored Materials, Retainage, Certification Duties & Withholding 20.3 Substantial Completion & the Punch List Protocol 20.4 The Certificate of Substantial Completion & Its Legal Consequences 20.5 Final Completion, Final Payment & the Closeout Package 20.6 Warranty Administration, the Eleven-Month Walk-Through & Post-Occupancy Evaluation

8.2 B101: Owner Duties, Cost of the Work, Copyright, Termination & Compensation

Key Takeaways Explain This Topic AI

Article 5 obligates the owner to furnish the program, the budget, the survey, geotechnical data, and timely decisions the design depends on.

When the lowest bona fide bid exceeds the owner’s budget, B101 gives the owner five remedies, and modifying the documents to reduce cost is an architect service without additional compensation only in the defined circumstance.

Under Article 7 the architect retains copyright in the instruments of service and the owner receives a non-exclusive license that terminates on the owner’s default.

Termination for convenience entitles the architect to compensation for services performed plus reimbursable and termination expenses.

A modified B101 governs over the standard form, so a case study exhibit containing struck or added language is the correct basis for the answer.

Last updated: September 2026

Article 5: Owner's Responsibilities

Under Article 5, the owner holds affirmative duties to furnish essential project information:

The owner's project program, budgetary constraints, and schedule parameters.

A land survey detailing boundary lines, topography, easements, rights-of-way, zoning, utilities, and benchmarks.

Geotechnical engineering services, including soil borings, test pits, percolation tests, ground water elevations, and foundation recommendations.

Environmental testing, hazardous materials abatement reports (asbestos, lead), and lab testing.

Legal, accounting, and insurance counseling services.

The architect is legally entitled to rely on the accuracy of all owner-furnished surveys, reports, and tests without independent verification.

Article 6: Cost of the Work & Budget Overruns

Section 6.1 defines the Cost of the Work as the total cost to the owner to construct all elements designed or specified by the architect, including contractor general conditions, overhead, and profit. Crucially, the Cost of the Work excludes :

Compensation of the architect and consultants.

Costs of the land, rights-of-way, financing, or financing contingencies.

Other costs that are the legal responsibility of the owner.

Five Contractual Remedies for Budget Overruns

If the lowest bona fide contractor bid or negotiated proposal exceeds the agreed budget for the Cost of the Work, Section 6.6 grants the owner five specific options:

Increase the budget for the Cost of the Work.

Authorize rebidding or renegotiating the project within a reasonable time.

Terminate the agreement in accordance with Article 9.

Cooperate with the architect to revise project scope and quality to reduce the Cost of the Work.

Implement any other mutually acceptable alternative.

If the owner selects Option 4 (revise scope and quality), Section 6.7 mandates that the architect must modify the construction documents without additional compensation . This redesign obligation represents the limit of the architect's contractual liability for budget overruns.

Article 7: Copyright and Instruments of Service

Under Article 7, the architect and the architect's consultants retain all common law, statutory, and reserved rights—specifically including copyright —in their respective Instruments of Service (drawings, specifications, BIM models, and sketches).

The owner receives a non-exclusive license to use the Instruments of Service solely and exclusively for constructing, using, maintaining, and altering the project. This license is contingent upon the owner substantially performing its contractual obligations, including prompt payment of all professional fees. If the owner terminates the architect for convenience, the owner can only continue using the Instruments of Service if they pay a negotiated licensing fee and agree to indemnify the architect against third-party claims.

Article 9: Suspension and Termination

Either party may terminate the agreement upon not less than 7 days' written notice if the other party fails substantially to perform its obligations (termination for cause). If the owner fails to make payments when due, the architect may suspend services upon 7 days' written notice; the architect must be reimbursed for remobilization expenses and granted a schedule extension.

If the owner terminates for convenience (without cause), the architect is entitled to:

Payment for all services executed to date.

Reimbursable expenses incurred.

Direct termination expenses.

The Termination Fee and Licensing Fee explicitly stipulated in Article 11.

Article 11: Compensation Structures

B101 accommodates multiple compensation structures:

Stipulated Sum (Fixed Fee): Common in well-defined projects; typically billed monthly based on percentage completion across the five Basic Services phases (standard industry baseline: SD 15%, DD 20%, CD 40%, Bidding 5%, CA 20%).

Percentage of Construction Cost: Fee varies based on final Cost of the Work; creates potential conflicts if scope changes.

Hourly / Time & Materials: Standard for Additional Services or projects with undefined scope, utilizing Direct Personnel Expense (DPE) with a multiplier (e.g., 2.5x to 3.2x) or fixed billing rate schedules.

Reading a Modified B101

Owners routinely present the architect with a marked-up B101 or with an owner-drafted agreement that borrows B101's structure. Objective 3.1 asks you to verify adherence to the owner-architect agreement, which means reading the agreement you actually signed rather than the standard form you remember.

The provisions most often modified, and what the modification does:

Provision Standard B101 position Typical owner modification Effect on the architect

Standard of care Skill and care of an architect performing similar services in the same locality "Highest standard," "best practices," or an express warranty Creates uninsurable liability

Instruments of service Architect retains copyright; owner receives a license Assignment of copyright to the owner, or work-made-for-hire Architect loses reuse rights and control

Consequential damages Mutual waiver Waiver deleted, or made one-way Exposes architect to lost profit and lost use claims

Certification requests Architect signs only certificates in a form the architect approves Owner or lender certificates required on demand Architect may certify facts it cannot verify

Termination Termination for convenience with compensation for work performed plus termination expenses Termination without termination expenses Unrecovered demobilization cost

Dispute resolution Mediation as condition precedent, then selected binding method Litigation in a distant venue, jury waiver, fee shifting Cost and venue risk

Suspension for non-payment Architect may suspend after seven days' notice Right to suspend deleted Architect must keep working while unpaid

Two habits matter on the exam and in practice. First, the exhibit governs : a case study will hand you a modified clause, and the modified clause is the correct basis for the answer. Second, the architect's obligation to verify adherence runs both ways — it includes confirming that the owner is performing its own Article 5 responsibilities, such as providing the program, the budget, the survey, and the geotechnical report on which the design depends.