8.6 Documenting a Project for the Specified Delivery Method
Architect Registration Examination ARE 5.0
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: ARE 5.0 Structure, Delivery & Scoring
1.1 The Six Divisions: Items, Durations, Sections & Objectives 1.2 Eligibility, PSI Delivery, Fees, Scheduling & Rescheduling 1.3 Cut Scores, Score Reports, Provisional Feedback & Retakes
2 Chapter 2: Licensure Path, Item Types & Test-Day Strategy
2.1 Education Standard, AXP Hours, Settings & Reporting Rules 2.2 The NCARB Record, Score Validity Policy & Reciprocity 2.3 Item Types, Case Studies, Exam Tools, Breaks & Pacing
3 Chapter 3: Practice Management — Firm Resources, Conduct & the Work Environment
3.1 Assessing Practice Resources: Staffing, Development & Capital Investment 3.2 Regulating the Work Environment: FLSA, Antidiscrimination Law, OSHA & ADA Title III 3.3 Ethical Standards, the NCARB Rules of Conduct & the Standard of Care 3.4 Business Structures, Firm Ownership Rules & Practice-Wide Methodologies
4 Chapter 4: Practice Management — Firm Finances & Financial Health
4.1 Utilization, Overhead, Break-Even & Net Multiplier 4.2 Liquidity, Solvency & Reading Firm Financials Strategically 4.3 Accrual vs. Cash Accounting & the Architectural Balance Sheet 4.4 The Income Statement, Net Operating Revenue & Cash Flow Management
5 Chapter 5: Practice Management — Risk, Insurance & Business Development
5.1 Risk Management & the Firm’s Insurance Portfolio 5.2 Contractual Risk Allocation, Intellectual Property & Dispute Resolution 5.3 Client Requests, Compensation Methods, Project Delivery & Project Risk
6 Chapter 6: Project Management — Team, Resources & Consultants
6.1 Assembling the Project Team: Roles, Authority & Selection Criteria 6.2 Allocating & Managing Project Resources: Hours, Rates & Leveling 6.3 Consultant Selection, Qualifications-Based Selection & Scope Boundaries 6.4 AIA C401: Flow-Through, Consultant Standard of Care, Insurance & Payment
7 Chapter 7: Project Management — Work Planning, Scheduling & Budget Control
7.1 The Project Work Plan & Phase Fee Allocation 7.2 Work Breakdown Structures, Scheduling Methods & Dependency Logic 7.3 Critical Path Calculations, Float & Schedule Compression 7.4 Project Communication: Paths, Instruments, Meetings & the Record 7.5 Monitoring the Project Budget with Earned Value Management 7.6 Scope Creep, Additional Services & Written Authorization
8 Chapter 8: Project Management — Contracts, Approvals & Quality Control
8.1 AIA B101: Initial Information, Standard of Care & Basic Services 8.2 B101: Owner Duties, Cost of the Work, Copyright, Termination & Compensation 8.3 The Owner-Contractor Agreement & A201 Contractor Responsibilities 8.4 A201: Architect Administration, Changes, Claims & Separate Contractors 8.5 Regulatory Compliance, Authorities Having Jurisdiction & Project Approvals 8.6 Documenting a Project for the Specified Delivery Method 8.7 Quality Assurance, Quality Control, Constructability & the Record
9 Chapter 9: Programming & Analysis — Site & Environmental Conditions
9.1 Climate Classification, Solar Geometry & Passive Site Opportunities 9.2 Microclimate, Wind, Topography, Grading & Site Hydrology 9.3 Environmental Due Diligence: CERCLA Liability & Phase I / Phase II Assessments 9.4 Soil Mechanics, Geotechnical Investigation & Foundation Selection 9.5 Vehicular Circulation, Access Management, Parking & Emergency Access
10 Chapter 10: Programming & Analysis — Zoning, Codes & Site Infrastructure
10.1 Pedestrian Circulation, Site Utilities & Contextual Constraints 10.2 Zoning Authority, Euclidean and Form-Based Codes & Bulk Standards 10.3 Non-Conforming Uses, Variances, Easements & Parking Feasibility 10.4 IBC Occupancy Classification, Mixed Occupancy & Incidental Uses 10.5 IBC Construction Types, Fire-Resistance Ratings & Compartmentation
11 Chapter 11: Programming & Analysis — Building Programming & Feasibility
11.1 Programming Methodology, Net vs. Gross Area & Building Efficiency 11.2 Adjacency Matrices, Bubble Diagrams, Blocking & Stacking 11.3 Evaluating an Existing Building Against a Program 11.4 Reviewing Project Budget & Schedule Feasibility Against Scope 11.5 Identifying Building & Structural System Alternatives at Programming
12 Chapter 12: Project Planning & Design — Siting, Configuration, Codes & Life Safety
12.1 Building Siting, Neighborhood Context, Zoning Application & Configuration 12.2 IBC Allowable Area: Tabular Area, Frontage & Sprinkler Increases 12.3 Building Height, Story Limits, Mixed Occupancy & Unlimited Area Buildings 12.4 Means of Egress Components & Occupant Load Calculation 12.5 Exit Count, Remoteness, Egress Capacity, Travel Distance & Dead Ends 12.6 Accessible Routes, Slopes, Protruding Objects & Ramp Design 12.7 Door Clearances, Operating Hardware & Accessible Toilet Room Geometry
13 Chapter 13: Project Planning & Design — Structural & Mechanical Systems
13.1 Selecting Structural Systems: Steel, Concrete, Wood & Masonry 13.2 Lateral Force-Resisting Systems, Wind Loads & Seismic Design 13.3 Thermal Comfort, ASHRAE Standard 55 & Psychrometrics 13.4 HVAC System Typologies, Spatial Allocation & Central Plant Equipment 13.5 Potable Water Supply, Drainage, Waste & Vent Systems 13.6 Electrical Distribution, Emergency Power, Lighting & Daylighting 13.7 Fire Suppression, Standpipes, Conveying, Security & Communications
14 Chapter 14: Project Planning & Design — Envelope, Materials & Cost
14.1 Envelope Thermodynamics, Heat Transfer & Fenestration Performance 14.2 Thermal Bridging, Continuous Insulation & Thermal Mass 14.3 Passive Solar Heating, Natural Ventilation & Daylighting Architecture 14.4 Material Selection Criteria, Fire Performance & Vapor Permeance 14.5 Life Cycle Assessment, Embodied Carbon & Material Transparency 14.6 Galvanic Compatibility, Thermal Movement & Masonry Durability 14.7 Cost Estimating by Phase & Contingency Planning 14.8 Life-Cycle Cost Analysis, Present Value & Value Engineering
15 Chapter 15: Project Development & Documentation — Roofing, Waterproofing & Wall Assemblies
15.1 Low-Slope Roofing Systems, Membranes & Drainage Geometry 15.2 Flashing, Parapets, Copings & Roof Penetration Detailing 15.3 Steep-Slope Roofing & Below-Grade Waterproofing 15.4 Enclosure Control Layers & Rain Screen Cladding Systems 15.5 Vapor Retarders, Permeance Classes & Dew Point Control
16 Chapter 16: Project Development & Documentation — Connections, Coordination & Interiors
16.1 Structural Steel Connections & Base Plate Detailing 16.2 Concrete Reinforcing, Cover & Building Movement Joints 16.3 Sizing Structural, Mechanical, Electrical & Plumbing Components 16.4 Ceiling Plenum Coordination, Clash Detection & Level of Development 16.5 Vertical Chases, Shaft Walls, Through-Penetration Firestopping & Rated Joints 16.6 Interior Partition Framing, Head-of-Wall Details & Rated Gypsum Assemblies 16.7 Sound Isolation, STC, NRC & Reverberation Time 16.8 Door and Frame Construction & Fire Door Assemblies Under NFPA 80 16.9 Hardware Functions, Fire-Protection vs. Fire-Resistance Glazing
17 Chapter 17: Project Development & Documentation — Drawings, Specifications & Estimates
17.1 The National CAD Standard, Sheet Modules & Title Blocks 17.2 Drawing Cross-Referencing, Coordination & Revision Control 17.3 Documenting Site Features: Survey, Civil, Grading, Utilities & Landscape 17.4 The Project Manual & CSI MasterFormat Divisions 17.5 Section Numbering & the CSI Three-Part SectionFormat 17.6 Specification Methods & Document Precedence 17.7 Quantity Takeoff Estimating, General Conditions, Overhead & Alternates
18 Chapter 18: Construction & Evaluation — Procurement, Bidding & Preconstruction
18.1 Procurement Methods & AIA A701 Instructions to Bidders 18.2 Addenda Mechanics & Surety Bonds 18.3 The Preconstruction Conference & Administrative Protocols 18.4 Submittal Schedules, Long-Lead Items, Permits & Special Inspections 18.5 Bid Opening, Bidder Qualification & Discrepancy Rules 18.6 Alternates, Allowances, Unit Prices & Contract Award
19 Chapter 19: Construction & Evaluation — Observation & Contract Administration
19.1 The Architect’s Site Observation Role & the Means and Methods Firewall 19.2 Rejecting Non-Conforming Work, Special Inspections & Field Reports 19.3 Submittal Workflow, Review Responsibility & Action Stamps 19.4 Delegated Design, Design-Assist & Deferred Submittals 19.5 Requests for Information & Architect’s Supplemental Instructions 19.6 Change Orders, Construction Change Directives & Instrument Comparison
20 Chapter 20: Construction & Evaluation — Payment, Closeout & Evaluation
20.1 The Schedule of Values & the Application and Certificate for Payment 20.2 Stored Materials, Retainage, Certification Duties & Withholding 20.3 Substantial Completion & the Punch List Protocol 20.4 The Certificate of Substantial Completion & Its Legal Consequences 20.5 Final Completion, Final Payment & the Closeout Package 20.6 Warranty Administration, the Eleven-Month Walk-Through & Post-Occupancy Evaluation
8.6 Documenting a Project for the Specified Delivery Method
Key Takeaways Explain This Topic AI
Design-bid-build requires a complete, self-sufficient set before pricing, while every other delivery method prices documents that are still in progress.
A guaranteed maximum price set needs basis-of-design narratives, an assumptions log, defined allowances, and outline specifications to be priced accurately.
Under multiple prime contracts, Division 01 must assign supply and install responsibility at every interface, because unassigned gaps become change orders in every contract at once.
Fast-track freezes the parameters of each released package, and later design must work within them or pay for the change.
Every issued set must carry an explicit issue purpose — not for construction, for permit, for pricing, or for construction — under a firm document-control procedure.
Last updated: September 2026
Objective 4.3 asks the architect to implement appropriate policies and procedures to document a project for a specified delivery method . The same building requires different documents, issued at different levels of completeness, at different moments, depending on how it will be delivered.
Why Delivery Method Changes Documentation
Under design-bid-build, the construction documents are complete before anyone prices the work, so the set must be self-sufficient: a bidder receives it, prices it, and builds from it with no further design input. Under every other method, pricing happens while design is still in progress, which means documents are issued for purposes other than construction.
Delivery method What documents are issued for Documentation consequence
Design-Bid-Build A single complete bid set Documents must be complete and coordinated; no design development occurs after bidding
CM as Adviser Multiple bid packages for multiple prime contracts Scope must be divided cleanly among packages with no gaps or overlaps in Division 01
CM at Risk Progressive pricing sets, then a GMP set A GMP set that is 60–70% complete must define quality and scope well enough to price, usually through performance narratives and assumptions logs
Design-Build A bridging or performance-criteria document, then design-builder's documents The architect may author criteria rather than construction documents, or may work for the design-builder
Integrated Project Delivery Shared model with agreed model element authorship The BIM execution plan, not the drawing set, becomes the primary coordination instrument
Fast-track Sequential packages (site, foundation, structure, envelope, fit-out) Earlier packages are released before later design is fixed, so assumptions must be recorded and verified
Documenting for a GMP or Progressive Pricing Set
When a set is priced before it is finished, the architect's job is to eliminate ambiguity about what is not yet drawn:
Basis-of-design narratives for each system, stating performance where the product is not yet selected.
An assumptions and clarifications log issued with the set, recording what the estimator should assume.
Allowances for scope that is genuinely undefined, with the allowance amount and its inclusions written into Division 01.
Outline specifications in MasterFormat order so nothing is omitted, even where sections are not yet fully written.
Quality level statements — a "fully finished" note is not a specification, and it becomes an argument at buyout.
Documenting for Multiple Prime Contracts
Where the owner holds several prime contracts, scope division is the documentation problem:
Division 01 must state the scope of each contract , including who supplies and who installs at every interface.
Drawings should carry contract-scope identification where scope changes within a single view.
Coordination of schedules among primes is the owner's responsibility, exercised through the CM as Adviser; the documents must give that coordination something to work with.
Every gap — the connection, the substrate, the blocking, the final connection to equipment furnished by another contract — must be assigned. Unassigned interfaces become change orders in every prime contract at once.
Documenting for Fast-Track
Fast-track releases construction before design is complete, which creates a class of risk that documentation must manage:
Freeze the parameters that later packages depend on. Once the foundation package is released, the structural grid and the building footprint are fixed.
Record the assumptions each package relies on, and verify them before the dependent package is released.
Expect and budget for rework. Fast-track compresses the calendar but does not reduce effort; the coordination burden and the change-order exposure both rise.
Track deferred submittals — delegated-design items such as trusses, curtain wall, and fire sprinkler design that will be submitted to the AHJ after permit issuance.
Firm Policies That Make This Work
A document control procedure defining issue purpose ("Not for Construction," "Issued for Permit," "Issued for GMP Pricing," "Issued for Construction") on every set.
Revision control so superseded sets are identifiable and cannot be built from.
Consistent transmittals recording what was issued, to whom, when, and for what purpose.
A model element table under AIA G202 on BIM-delivered projects, assigning authorship and level of development for each element at each milestone.
Exam Tip: The recurring error on this objective is issuing an incomplete set without labeling its purpose or recording its assumptions. An 65%-complete set issued for GMP pricing is appropriate; the same set issued with no assumptions log, no basis-of-design narrative, and no allowance structure is how an architect ends up owning the difference between the GMP and the real cost.