11.3 Evaluating an Existing Building Against a Program

Architect Registration Examination ARE 5.0

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: ARE 5.0 Structure, Delivery & Scoring

1.1 The Six Divisions: Items, Durations, Sections & Objectives 1.2 Eligibility, PSI Delivery, Fees, Scheduling & Rescheduling 1.3 Cut Scores, Score Reports, Provisional Feedback & Retakes

2 Chapter 2: Licensure Path, Item Types & Test-Day Strategy

2.1 Education Standard, AXP Hours, Settings & Reporting Rules 2.2 The NCARB Record, Score Validity Policy & Reciprocity 2.3 Item Types, Case Studies, Exam Tools, Breaks & Pacing

3 Chapter 3: Practice Management — Firm Resources, Conduct & the Work Environment

3.1 Assessing Practice Resources: Staffing, Development & Capital Investment 3.2 Regulating the Work Environment: FLSA, Antidiscrimination Law, OSHA & ADA Title III 3.3 Ethical Standards, the NCARB Rules of Conduct & the Standard of Care 3.4 Business Structures, Firm Ownership Rules & Practice-Wide Methodologies

4 Chapter 4: Practice Management — Firm Finances & Financial Health

4.1 Utilization, Overhead, Break-Even & Net Multiplier 4.2 Liquidity, Solvency & Reading Firm Financials Strategically 4.3 Accrual vs. Cash Accounting & the Architectural Balance Sheet 4.4 The Income Statement, Net Operating Revenue & Cash Flow Management

5 Chapter 5: Practice Management — Risk, Insurance & Business Development

5.1 Risk Management & the Firm’s Insurance Portfolio 5.2 Contractual Risk Allocation, Intellectual Property & Dispute Resolution 5.3 Client Requests, Compensation Methods, Project Delivery & Project Risk

6 Chapter 6: Project Management — Team, Resources & Consultants

6.1 Assembling the Project Team: Roles, Authority & Selection Criteria 6.2 Allocating & Managing Project Resources: Hours, Rates & Leveling 6.3 Consultant Selection, Qualifications-Based Selection & Scope Boundaries 6.4 AIA C401: Flow-Through, Consultant Standard of Care, Insurance & Payment

7 Chapter 7: Project Management — Work Planning, Scheduling & Budget Control

7.1 The Project Work Plan & Phase Fee Allocation 7.2 Work Breakdown Structures, Scheduling Methods & Dependency Logic 7.3 Critical Path Calculations, Float & Schedule Compression 7.4 Project Communication: Paths, Instruments, Meetings & the Record 7.5 Monitoring the Project Budget with Earned Value Management 7.6 Scope Creep, Additional Services & Written Authorization

8 Chapter 8: Project Management — Contracts, Approvals & Quality Control

8.1 AIA B101: Initial Information, Standard of Care & Basic Services 8.2 B101: Owner Duties, Cost of the Work, Copyright, Termination & Compensation 8.3 The Owner-Contractor Agreement & A201 Contractor Responsibilities 8.4 A201: Architect Administration, Changes, Claims & Separate Contractors 8.5 Regulatory Compliance, Authorities Having Jurisdiction & Project Approvals 8.6 Documenting a Project for the Specified Delivery Method 8.7 Quality Assurance, Quality Control, Constructability & the Record

9 Chapter 9: Programming & Analysis — Site & Environmental Conditions

9.1 Climate Classification, Solar Geometry & Passive Site Opportunities 9.2 Microclimate, Wind, Topography, Grading & Site Hydrology 9.3 Environmental Due Diligence: CERCLA Liability & Phase I / Phase II Assessments 9.4 Soil Mechanics, Geotechnical Investigation & Foundation Selection 9.5 Vehicular Circulation, Access Management, Parking & Emergency Access

10 Chapter 10: Programming & Analysis — Zoning, Codes & Site Infrastructure

10.1 Pedestrian Circulation, Site Utilities & Contextual Constraints 10.2 Zoning Authority, Euclidean and Form-Based Codes & Bulk Standards 10.3 Non-Conforming Uses, Variances, Easements & Parking Feasibility 10.4 IBC Occupancy Classification, Mixed Occupancy & Incidental Uses 10.5 IBC Construction Types, Fire-Resistance Ratings & Compartmentation

11 Chapter 11: Programming & Analysis — Building Programming & Feasibility

11.1 Programming Methodology, Net vs. Gross Area & Building Efficiency 11.2 Adjacency Matrices, Bubble Diagrams, Blocking & Stacking 11.3 Evaluating an Existing Building Against a Program 11.4 Reviewing Project Budget & Schedule Feasibility Against Scope 11.5 Identifying Building & Structural System Alternatives at Programming

12 Chapter 12: Project Planning & Design — Siting, Configuration, Codes & Life Safety

12.1 Building Siting, Neighborhood Context, Zoning Application & Configuration 12.2 IBC Allowable Area: Tabular Area, Frontage & Sprinkler Increases 12.3 Building Height, Story Limits, Mixed Occupancy & Unlimited Area Buildings 12.4 Means of Egress Components & Occupant Load Calculation 12.5 Exit Count, Remoteness, Egress Capacity, Travel Distance & Dead Ends 12.6 Accessible Routes, Slopes, Protruding Objects & Ramp Design 12.7 Door Clearances, Operating Hardware & Accessible Toilet Room Geometry

13 Chapter 13: Project Planning & Design — Structural & Mechanical Systems

13.1 Selecting Structural Systems: Steel, Concrete, Wood & Masonry 13.2 Lateral Force-Resisting Systems, Wind Loads & Seismic Design 13.3 Thermal Comfort, ASHRAE Standard 55 & Psychrometrics 13.4 HVAC System Typologies, Spatial Allocation & Central Plant Equipment 13.5 Potable Water Supply, Drainage, Waste & Vent Systems 13.6 Electrical Distribution, Emergency Power, Lighting & Daylighting 13.7 Fire Suppression, Standpipes, Conveying, Security & Communications

14 Chapter 14: Project Planning & Design — Envelope, Materials & Cost

14.1 Envelope Thermodynamics, Heat Transfer & Fenestration Performance 14.2 Thermal Bridging, Continuous Insulation & Thermal Mass 14.3 Passive Solar Heating, Natural Ventilation & Daylighting Architecture 14.4 Material Selection Criteria, Fire Performance & Vapor Permeance 14.5 Life Cycle Assessment, Embodied Carbon & Material Transparency 14.6 Galvanic Compatibility, Thermal Movement & Masonry Durability 14.7 Cost Estimating by Phase & Contingency Planning 14.8 Life-Cycle Cost Analysis, Present Value & Value Engineering

15 Chapter 15: Project Development & Documentation — Roofing, Waterproofing & Wall Assemblies

15.1 Low-Slope Roofing Systems, Membranes & Drainage Geometry 15.2 Flashing, Parapets, Copings & Roof Penetration Detailing 15.3 Steep-Slope Roofing & Below-Grade Waterproofing 15.4 Enclosure Control Layers & Rain Screen Cladding Systems 15.5 Vapor Retarders, Permeance Classes & Dew Point Control

16 Chapter 16: Project Development & Documentation — Connections, Coordination & Interiors

16.1 Structural Steel Connections & Base Plate Detailing 16.2 Concrete Reinforcing, Cover & Building Movement Joints 16.3 Sizing Structural, Mechanical, Electrical & Plumbing Components 16.4 Ceiling Plenum Coordination, Clash Detection & Level of Development 16.5 Vertical Chases, Shaft Walls, Through-Penetration Firestopping & Rated Joints 16.6 Interior Partition Framing, Head-of-Wall Details & Rated Gypsum Assemblies 16.7 Sound Isolation, STC, NRC & Reverberation Time 16.8 Door and Frame Construction & Fire Door Assemblies Under NFPA 80 16.9 Hardware Functions, Fire-Protection vs. Fire-Resistance Glazing

17 Chapter 17: Project Development & Documentation — Drawings, Specifications & Estimates

17.1 The National CAD Standard, Sheet Modules & Title Blocks 17.2 Drawing Cross-Referencing, Coordination & Revision Control 17.3 Documenting Site Features: Survey, Civil, Grading, Utilities & Landscape 17.4 The Project Manual & CSI MasterFormat Divisions 17.5 Section Numbering & the CSI Three-Part SectionFormat 17.6 Specification Methods & Document Precedence 17.7 Quantity Takeoff Estimating, General Conditions, Overhead & Alternates

18 Chapter 18: Construction & Evaluation — Procurement, Bidding & Preconstruction

18.1 Procurement Methods & AIA A701 Instructions to Bidders 18.2 Addenda Mechanics & Surety Bonds 18.3 The Preconstruction Conference & Administrative Protocols 18.4 Submittal Schedules, Long-Lead Items, Permits & Special Inspections 18.5 Bid Opening, Bidder Qualification & Discrepancy Rules 18.6 Alternates, Allowances, Unit Prices & Contract Award

19 Chapter 19: Construction & Evaluation — Observation & Contract Administration

19.1 The Architect’s Site Observation Role & the Means and Methods Firewall 19.2 Rejecting Non-Conforming Work, Special Inspections & Field Reports 19.3 Submittal Workflow, Review Responsibility & Action Stamps 19.4 Delegated Design, Design-Assist & Deferred Submittals 19.5 Requests for Information & Architect’s Supplemental Instructions 19.6 Change Orders, Construction Change Directives & Instrument Comparison

20 Chapter 20: Construction & Evaluation — Payment, Closeout & Evaluation

20.1 The Schedule of Values & the Application and Certificate for Payment 20.2 Stored Materials, Retainage, Certification Duties & Withholding 20.3 Substantial Completion & the Punch List Protocol 20.4 The Certificate of Substantial Completion & Its Legal Consequences 20.5 Final Completion, Final Payment & the Closeout Package 20.6 Warranty Administration, the Eleven-Month Walk-Through & Post-Occupancy Evaluation

11.3 Evaluating an Existing Building Against a Program

Key Takeaways Explain This Topic AI

Existing structural bay spacing and load capacity often govern whether a program can be accommodated at all, independent of area.

As-built drawings are frequently inaccurate, so a measured field survey must verify conditions before design proceeds.

Existing-building codes classify work as repair, alteration levels 1 through 3, change of occupancy, or addition, and the classification determines the required upgrades.

A change of occupancy drives occupant load, exit capacity, plumbing fixture counts, and often sprinkler and alarm requirements, making it the largest cost driver in adaptive reuse.

Altering a primary function area triggers an obligation to make the serving path of travel accessible, subject to the disproportionate-cost limitation.

Last updated: September 2026

Objective 4.1 asks you to evaluate the relevant qualitative and quantitative attributes of a new or existing building as they relate to a program . The word that carries the weight is existing : a large share of architectural work is renovation, addition, adaptive reuse, and change of occupancy, and the evaluation methods differ from those used on a greenfield site.

  • What an Existing-Building Evaluation Measures
  • Quantitative Attributes

Attribute How it is established Why the program depends on it

Gross and net area by floor Measured survey or verified as-builts Determines whether the program fits at a realistic efficiency ratio

Floor-to-floor and floor-to-deck height Field measurement Governs ceiling height, duct depth, and whether new MEP can be routed

Structural bay spacing and capacity Original drawings plus structural assessment Governs layout flexibility and whether new loads — assembly occupancy, file storage, green roof, rooftop equipment — can be carried

Existing MEP capacity Equipment nameplate data, panel schedules, service size Determines whether a change of use can be served without new service

Envelope thermal performance Assembly investigation, infrared survey, blower-door testing Governs energy compliance and comfort

Egress capacity Measured stair widths, exit counts, travel distances Caps the occupant load the building can legally hold

  • Vertical transportation Elevator count, capacity, speed Caps population and governs accessibility
  • Qualitative Attributes

Architectural significance and whether the building is listed, contributing to a district, or eligible for listing.

Condition of structure, envelope, and systems, expressed as remaining service life rather than as a simple pass or fail.

Spatial character — daylight, volume, column rhythm, materials — which is usually the reason the reuse is attractive in the first place.

Hazardous materials , particularly asbestos, lead paint, and PCBs in buildings of certain eras. A hazardous-materials survey precedes any demolition planning.

Adaptability : how much of the program can be accommodated without altering the structure.

The Evaluation Sequence

Document review. Original drawings, prior permits, prior renovation records, certificate of occupancy, and any existing conditions reports.

Measured survey. Verify, never assume. As-built drawings are frequently wrong, and the error is discovered at the worst moment.

Discipline assessments. Structural, MEP, envelope, and where relevant a hazardous-materials survey and an accessibility audit.

Code evaluation under the jurisdiction's existing-building provisions.

Program fit test. Block the program into the measured building and report the surplus or deficit.

Feasibility recommendation comparing reuse against new construction.

Code Path for Existing Buildings

Most jurisdictions adopt an existing-building code (commonly the International Existing Building Code, IEBC) or the existing-building chapter of the building code. The evaluation must establish which work classification applies , because that determines how much of the building must be upgraded:

  • Work type Trigger Typical requirement
  • Repair Restoring damaged work Repair to pre-existing condition
  • Alteration Level 1 Replacement of materials with equivalents Minimal upgrade
  • Alteration Level 2 Reconfiguration of space, new systems Upgrades within the work area
  • Alteration Level 3 Work area exceeds 50% of building area Building-wide upgrades to selected systems
  • Change of occupancy New occupancy classification Compliance with the requirements of the new occupancy

Addition New construction added Addition meets new-construction requirements; existing building must not be made less compliant

Change of occupancy is the trigger that moves budgets the most. Converting a Group B office floor to a Group A-2 assembly use raises occupant load dramatically, which in turn drives exit capacity, plumbing fixture counts, and sometimes sprinkler and alarm requirements. Converting an office building to Group R residential brings dwelling-unit separations, sound transmission requirements, and different egress rules.

Accessibility in Existing Buildings

Alterations must comply with accessibility requirements to the maximum extent technically feasible , and altering a primary function area triggers an obligation to make the path of travel to that area — including restrooms, drinking fountains, and telephones serving it — accessible, subject to a disproportionate-cost limitation in the ADA regulations. Existing buildings that are not being altered still owe readily achievable barrier removal in places of public accommodation.

Exam Tip: When a programming item involves an existing building, look first for a change of occupancy and second for a structural capacity limit. Those two facts drive more feasibility answers than any aesthetic or condition issue, because they determine whether the program is legal and whether it can be carried.

Reporting the Findings

The evaluation has to end in a document the client can act on, not a list of observations.

A Property Condition Assessment performed to ASTM E2018 is the standard commercial instrument. It produces a condition rating by system, an opinion of probable cost for immediate repairs, and a table of replacement reserves over a stated horizon — commonly 10 or 12 years.

Findings are expressed as remaining useful life by system — roof, envelope, HVAC, elevators, electrical service — because owners budget against replacement years, not against adjectives.

Immediate needs (life-safety violations, active water intrusion, structural distress) are reported separately from deferred maintenance , which can be scheduled against the capital plan.

The Reuse-Versus-New Comparison

The feasibility recommendation compares reuse against new construction on four axes, and cost alone rarely decides it:

Axis Favors reuse Favors new construction

Cost Structure and enclosure already exist and are already paid for Extensive code upgrades, hazardous-materials abatement, structural strengthening

Schedule Shell exists; entitlement often already in place Concealed conditions drive change orders and delay

Program fit Bay spacing, floor heights, and capacity suit the use Program needs spans, heights, or loads the building cannot deliver

Non-financial Historic tax credits, retained embodied carbon, community and brand value Predictable performance and clean future adaptability

Two items change answers often enough to memorize:

Existing non-conforming zoning rights are frequently the most valuable asset in the building. A structure that exceeds today's height limit, covers more lot area, or sits inside today's setback may retain those rights if it is altered ; demolishing it usually extinguishes them permanently, and the replacement must meet current zoning.

Contingency must be set higher than for new construction. Renovation carries concealed conditions that no survey fully eliminates, so carrying a new-construction design contingency into an adaptive reuse budget understates the risk the owner is actually accepting.