Study guide

18.6 Alternates, Allowances, Unit Prices & Contract Award

Architect Registration Examination ARE 5.0

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: ARE 5.0 Structure, Delivery & Scoring

1.1 The Six Divisions: Items, Durations, Sections & Objectives 1.2 Eligibility, PSI Delivery, Fees, Scheduling & Rescheduling 1.3 Cut Scores, Score Reports, Provisional Feedback & Retakes

2 Chapter 2: Licensure Path, Item Types & Test-Day Strategy

2.1 Education Standard, AXP Hours, Settings & Reporting Rules 2.2 The NCARB Record, Score Validity Policy & Reciprocity 2.3 Item Types, Case Studies, Exam Tools, Breaks & Pacing

3 Chapter 3: Practice Management — Firm Resources, Conduct & the Work Environment

3.1 Assessing Practice Resources: Staffing, Development & Capital Investment 3.2 Regulating the Work Environment: FLSA, Antidiscrimination Law, OSHA & ADA Title III 3.3 Ethical Standards, the NCARB Rules of Conduct & the Standard of Care 3.4 Business Structures, Firm Ownership Rules & Practice-Wide Methodologies

4 Chapter 4: Practice Management — Firm Finances & Financial Health

4.1 Utilization, Overhead, Break-Even & Net Multiplier 4.2 Liquidity, Solvency & Reading Firm Financials Strategically 4.3 Accrual vs. Cash Accounting & the Architectural Balance Sheet 4.4 The Income Statement, Net Operating Revenue & Cash Flow Management

5 Chapter 5: Practice Management — Risk, Insurance & Business Development

5.1 Risk Management & the Firm’s Insurance Portfolio 5.2 Contractual Risk Allocation, Intellectual Property & Dispute Resolution 5.3 Client Requests, Compensation Methods, Project Delivery & Project Risk

6 Chapter 6: Project Management — Team, Resources & Consultants

6.1 Assembling the Project Team: Roles, Authority & Selection Criteria 6.2 Allocating & Managing Project Resources: Hours, Rates & Leveling 6.3 Consultant Selection, Qualifications-Based Selection & Scope Boundaries 6.4 AIA C401: Flow-Through, Consultant Standard of Care, Insurance & Payment

7 Chapter 7: Project Management — Work Planning, Scheduling & Budget Control

7.1 The Project Work Plan & Phase Fee Allocation 7.2 Work Breakdown Structures, Scheduling Methods & Dependency Logic 7.3 Critical Path Calculations, Float & Schedule Compression 7.4 Project Communication: Paths, Instruments, Meetings & the Record 7.5 Monitoring the Project Budget with Earned Value Management 7.6 Scope Creep, Additional Services & Written Authorization

8 Chapter 8: Project Management — Contracts, Approvals & Quality Control

8.1 AIA B101: Initial Information, Standard of Care & Basic Services 8.2 B101: Owner Duties, Cost of the Work, Copyright, Termination & Compensation 8.3 The Owner-Contractor Agreement & A201 Contractor Responsibilities 8.4 A201: Architect Administration, Changes, Claims & Separate Contractors 8.5 Regulatory Compliance, Authorities Having Jurisdiction & Project Approvals 8.6 Documenting a Project for the Specified Delivery Method 8.7 Quality Assurance, Quality Control, Constructability & the Record

9 Chapter 9: Programming & Analysis — Site & Environmental Conditions

9.1 Climate Classification, Solar Geometry & Passive Site Opportunities 9.2 Microclimate, Wind, Topography, Grading & Site Hydrology 9.3 Environmental Due Diligence: CERCLA Liability & Phase I / Phase II Assessments 9.4 Soil Mechanics, Geotechnical Investigation & Foundation Selection 9.5 Vehicular Circulation, Access Management, Parking & Emergency Access

10 Chapter 10: Programming & Analysis — Zoning, Codes & Site Infrastructure

10.1 Pedestrian Circulation, Site Utilities & Contextual Constraints 10.2 Zoning Authority, Euclidean and Form-Based Codes & Bulk Standards 10.3 Non-Conforming Uses, Variances, Easements & Parking Feasibility 10.4 IBC Occupancy Classification, Mixed Occupancy & Incidental Uses 10.5 IBC Construction Types, Fire-Resistance Ratings & Compartmentation

11 Chapter 11: Programming & Analysis — Building Programming & Feasibility

11.1 Programming Methodology, Net vs. Gross Area & Building Efficiency 11.2 Adjacency Matrices, Bubble Diagrams, Blocking & Stacking 11.3 Evaluating an Existing Building Against a Program 11.4 Reviewing Project Budget & Schedule Feasibility Against Scope 11.5 Identifying Building & Structural System Alternatives at Programming

12 Chapter 12: Project Planning & Design — Siting, Configuration, Codes & Life Safety

12.1 Building Siting, Neighborhood Context, Zoning Application & Configuration 12.2 IBC Allowable Area: Tabular Area, Frontage & Sprinkler Increases 12.3 Building Height, Story Limits, Mixed Occupancy & Unlimited Area Buildings 12.4 Means of Egress Components & Occupant Load Calculation 12.5 Exit Count, Remoteness, Egress Capacity, Travel Distance & Dead Ends 12.6 Accessible Routes, Slopes, Protruding Objects & Ramp Design 12.7 Door Clearances, Operating Hardware & Accessible Toilet Room Geometry

13 Chapter 13: Project Planning & Design — Structural & Mechanical Systems

13.1 Selecting Structural Systems: Steel, Concrete, Wood & Masonry 13.2 Lateral Force-Resisting Systems, Wind Loads & Seismic Design 13.3 Thermal Comfort, ASHRAE Standard 55 & Psychrometrics 13.4 HVAC System Typologies, Spatial Allocation & Central Plant Equipment 13.5 Potable Water Supply, Drainage, Waste & Vent Systems 13.6 Electrical Distribution, Emergency Power, Lighting & Daylighting 13.7 Fire Suppression, Standpipes, Conveying, Security & Communications

14 Chapter 14: Project Planning & Design — Envelope, Materials & Cost

14.1 Envelope Thermodynamics, Heat Transfer & Fenestration Performance 14.2 Thermal Bridging, Continuous Insulation & Thermal Mass 14.3 Passive Solar Heating, Natural Ventilation & Daylighting Architecture 14.4 Material Selection Criteria, Fire Performance & Vapor Permeance 14.5 Life Cycle Assessment, Embodied Carbon & Material Transparency 14.6 Galvanic Compatibility, Thermal Movement & Masonry Durability 14.7 Cost Estimating by Phase & Contingency Planning 14.8 Life-Cycle Cost Analysis, Present Value & Value Engineering

15 Chapter 15: Project Development & Documentation — Roofing, Waterproofing & Wall Assemblies

15.1 Low-Slope Roofing Systems, Membranes & Drainage Geometry 15.2 Flashing, Parapets, Copings & Roof Penetration Detailing 15.3 Steep-Slope Roofing & Below-Grade Waterproofing 15.4 Enclosure Control Layers & Rain Screen Cladding Systems 15.5 Vapor Retarders, Permeance Classes & Dew Point Control

16 Chapter 16: Project Development & Documentation — Connections, Coordination & Interiors

16.1 Structural Steel Connections & Base Plate Detailing 16.2 Concrete Reinforcing, Cover & Building Movement Joints 16.3 Sizing Structural, Mechanical, Electrical & Plumbing Components 16.4 Ceiling Plenum Coordination, Clash Detection & Level of Development 16.5 Vertical Chases, Shaft Walls, Through-Penetration Firestopping & Rated Joints 16.6 Interior Partition Framing, Head-of-Wall Details & Rated Gypsum Assemblies 16.7 Sound Isolation, STC, NRC & Reverberation Time 16.8 Door and Frame Construction & Fire Door Assemblies Under NFPA 80 16.9 Hardware Functions, Fire-Protection vs. Fire-Resistance Glazing

17 Chapter 17: Project Development & Documentation — Drawings, Specifications & Estimates

17.1 The National CAD Standard, Sheet Modules & Title Blocks 17.2 Drawing Cross-Referencing, Coordination & Revision Control 17.3 Documenting Site Features: Survey, Civil, Grading, Utilities & Landscape 17.4 The Project Manual & CSI MasterFormat Divisions 17.5 Section Numbering & the CSI Three-Part SectionFormat 17.6 Specification Methods & Document Precedence 17.7 Quantity Takeoff Estimating, General Conditions, Overhead & Alternates

18 Chapter 18: Construction & Evaluation — Procurement, Bidding & Preconstruction

18.1 Procurement Methods & AIA A701 Instructions to Bidders 18.2 Addenda Mechanics & Surety Bonds 18.3 The Preconstruction Conference & Administrative Protocols 18.4 Submittal Schedules, Long-Lead Items, Permits & Special Inspections 18.5 Bid Opening, Bidder Qualification & Discrepancy Rules 18.6 Alternates, Allowances, Unit Prices & Contract Award

19 Chapter 19: Construction & Evaluation — Observation & Contract Administration

19.1 The Architect’s Site Observation Role & the Means and Methods Firewall 19.2 Rejecting Non-Conforming Work, Special Inspections & Field Reports 19.3 Submittal Workflow, Review Responsibility & Action Stamps 19.4 Delegated Design, Design-Assist & Deferred Submittals 19.5 Requests for Information & Architect’s Supplemental Instructions 19.6 Change Orders, Construction Change Directives & Instrument Comparison

20 Chapter 20: Construction & Evaluation — Payment, Closeout & Evaluation

20.1 The Schedule of Values & the Application and Certificate for Payment 20.2 Stored Materials, Retainage, Certification Duties & Withholding 20.3 Substantial Completion & the Punch List Protocol 20.4 The Certificate of Substantial Completion & Its Legal Consequences 20.5 Final Completion, Final Payment & the Closeout Package 20.6 Warranty Administration, the Eleven-Month Walk-Through & Post-Occupancy Evaluation

18.6 Alternates, Allowances, Unit Prices & Contract Award

Key Takeaways Explain This Topic AI

An add alternate prices scope added to the base bid, and a deduct alternate prices scope removed from it.

Alternates must be selected in the predetermined order stated in the bidding documents, so that the low bidder cannot be manipulated after bids are opened.

A cash allowance under A201 Section 3.8 covers the cost of materials and delivery, with the contractor’s overhead and profit carried in the base bid.

A unit price is a stated price per unit of measurement used to adjust the contract sum when the actual quantity differs from the estimate.

The notice to proceed establishes the date of commencement from which the contract time runs, and it is the point at which liquidated damages exposure begins to accrue.

Last updated: September 2026

Handling Alternates, Allowances & Unit Prices

To balance construction scope with rigid client budgets, architects integrate financial adjustment mechanisms into the procurement documents.

Alternates (AIA Document A701 Section 4.2.1)

An alternate is a defined portion of work described in the bidding documents for which bidders submit a separate price that may be added to or deducted from the base bid:

Add Alternates: Scope enhancements that increase the base bid if accepted (e.g., adding a rooftop photovoltaic solar array, finishing a third-floor shell space, or upgrading acoustic ceilings).

Deduct Alternates: Scope deletions that decrease the base bid if accepted (e.g., omitting decorative aluminum sunshades, substituting resilient flooring for terrazzo, or deleting exterior landscaping beds).

Budget Balancing Strategy: Alternates provide the owner with pre-priced contractual levers. If competitive base bids come in over budget, the owner can accept deduct alternates to bring the contract sum within available capital funds without cancelling the procurement or redesigning the project. ALTERNATE SELECTION & PREVENTING BID MANIPULATION

  • ═══════════════════════════════════════════════════════════════════════════════════════════
  • Bidder A: Base Bid = $1,000,000 | Alt 1 (Add) = $50,000 | Alt 2 (Add) = $30,000
  • Bidder B: Base Bid = $1,020,000 | Alt 1 (Add) = $10,000 | Alt 2 (Add) = $40,000
  • ───────────────────────────────────────────────────────────────────────────────────────────
  • SCENARIO 1 (Base Bid Only): Bidder A is Low ($1,000,000 vs $1,020,000)
  • SCENARIO 2 (Base Bid + Alt 1): Bidder B is Low ($1,030,000 vs $1,050,000)
  • ───────────────────────────────────────────────────────────────────────────────────────────

LEGAL RULE: Public owners CANNOT arbitrarily select Alt 1 to favor Bidder B.

Alternates MUST be accepted in the strict numerical sequence listed in the bid documents!

  • ═══════════════════════════════════════════════════════════════════════════════════════════
  • Prevention of Bid Rigging in Alternate Selection

In public competitive bidding, the handling of alternates represents a significant ethical and legal risk. If an owner could freely pick and choose alternates after opening bids, the owner could manipulate combinations to steer the contract award to a favored contractor (as illustrated above). To guarantee procurement integrity:

Rigid Priority Order: Bidding documents must establish an unyielding, pre-determined priority sequence (e.g., Base Bid, then Alternate No. 1, then Alternate No. 2). The owner must accept alternates in that exact order down to the limit of available funding.

Determining Low Bidder: The lowest responsive bidder is identified based on the total sum of the Base Bid plus all sequentially accepted alternates within the established budget ceiling.

Cash Allowances (AIA Document A201 Section 3.8)

Cash allowances are stipulated monetary sums included in the contract when specific material or equipment selections cannot be finalized prior to bidding (e.g., decorative lighting fixtures, custom architectural hardware, imported stone tiles):

Costs Included in Allowance: Under AIA A201 Section 3.8.2, the allowance covers the net purchase price of materials and equipment delivered to the jobsite , including all applicable taxes and trade discounts.

Costs Excluded from Allowance (In Base Contract): The contractor's costs for unloading, uncrating, on-site storage, handling, labor for installation, overhead, profit, and commercial insurance are excluded from the allowance and must be included by the contractor in the base Contract Sum.

Contract Adjustment: If the actual cost of purchasing the approved materials exceeds or is less than the allowance sum, the Contract Sum is adjusted by a Change Order reflecting the exact net difference without contractor markup for overhead and profit.

Unit Prices

Unit prices represent pre-established rates per unit of measurement for specific items of work where exact quantities are unknown during bidding (e.g., cubic yards of unexpected rock excavation, linear feet of helical micropiles, square feet of decayed timber decking replacement):

Balanced vs. Unbalanced Bids: Unit prices must reflect realistic market rates. Contractors sometimes submit unbalanced bids —artificially inflating unit prices for early excavation work while deflating later unit prices—to front-load payments or exploit anticipated quantity underestimates. The architect must scrutinize unit price tabulations; an excessively unbalanced bid can be deemed non-responsive and rejected.

Contract Award Instruments, Execution & Date of Commencement

Once the architect and owner complete bid evaluations and identify the lowest responsive and responsible bidder, the project moves into formal contract execution.

Bid Irrevocability Period

Under AIA Document A701 Section 4.4, bidders agree that their bids remain binding and cannot be withdrawn for a designated evaluation period—standardly 30, 60, or 90 calendar days following bid opening. This window provides the owner and architect necessary time to verify references, obtain public council approvals, and finalize project financing.

Notice of Award

The owner issues a formal, written Notice of Award notifying the successful contractor that their bid has been selected. The Notice of Award directs the contractor to submit the following required documents within a stipulated timeframe (standardly 7 to 10 calendar days ):

Executed Owner-Contractor Agreement.

Executed AIA Document A312 Performance Bond and Payment Bond.

Certificates of Insurance (AIA Document G715 or ACORD Form) demonstrating compliance with contractual insurance limits.

Standard Owner-Contractor Agreements

The standard legal instruments governing construction include:

AIA Document A101: Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum (Lump Sum) . Utilized for traditional Design-Bid-Build projects where comprehensive Construction Documents define a static scope.

AIA Document A102: Standard Form of Agreement Between Owner and Contractor where the basis of payment is the Cost of the Work Plus a Fee with a Guaranteed Maximum Price (GMP) . Standardly utilized for CM at-Risk and fast-track negotiated contracts.

Notice to Proceed (NTP) & Date of Commencement

Under AIA Document A201 Section 8.1.2, the Date of Commencement of the Work is the date established in the agreement, or if no date is fixed, the date specified in a formal written Notice to Proceed (NTP) issued by the owner. CONTRACT AWARD & COMMENCEMENT SEQUENCE

  • ┌──────────────────────────────┐
  • │ Bid Opening & Evaluation │ Low responsive & responsible bidder selected
  • └──────────────┬───────────────┘
  • │
  • ┌──────────────▼───────────────┐
  • │ Notice of Award Issued │ Contractor has 7-10 days to deliver bonds/insurance
  • └──────────────┬───────────────┘
  • │
  • ┌──────────────▼───────────────┐
  • │ Contract Execution (A101) │ Agreement signed; construction loan recorded
  • └──────────────┬───────────────┘
  • │
  • ┌──────────────▼───────────────┐
  • │ Notice to Proceed (NTP) │ Formally establishes DATE OF COMMENCEMENT;
  • └──────────────────────────────┘ starts clock on Contract Time & Substantial Completion
  • Critical Legal & Financial Significance of the NTP

The formal Notice to Proceed carries immense legal and financial significance:

Starts Contract Time: The Date of Commencement established in the NTP officially starts the running clock for Contract Time . The contractual deadline for Substantial Completion (and the accrual of liquidated damages for late completion) is calculated directly from this benchmark.

Mechanics' Lien & Mortgage Priority Protection: The contractor is strictly prohibited from commencing any physical work on site—including clearing trees, grading earth, or delivering storage trailers—prior to the Date of Commencement. In many legal jurisdictions, if a contractor performs physical work on site before the construction lender records their mortgage or deed of trust, subsequent mechanics' liens filed by unpaid subcontractors can "relate back" to the very first day of physical activity, wiping out the lender's primary security interest. The owner and lender issue the Notice to Proceed only after verifying that the mortgage has been officially recorded in public land records.