19.6 Change Orders, Construction Change Directives & Instrument Comparison
Architect Registration Examination ARE 5.0
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: ARE 5.0 Structure, Delivery & Scoring
1.1 The Six Divisions: Items, Durations, Sections & Objectives 1.2 Eligibility, PSI Delivery, Fees, Scheduling & Rescheduling 1.3 Cut Scores, Score Reports, Provisional Feedback & Retakes
2 Chapter 2: Licensure Path, Item Types & Test-Day Strategy
2.1 Education Standard, AXP Hours, Settings & Reporting Rules 2.2 The NCARB Record, Score Validity Policy & Reciprocity 2.3 Item Types, Case Studies, Exam Tools, Breaks & Pacing
3 Chapter 3: Practice Management — Firm Resources, Conduct & the Work Environment
3.1 Assessing Practice Resources: Staffing, Development & Capital Investment 3.2 Regulating the Work Environment: FLSA, Antidiscrimination Law, OSHA & ADA Title III 3.3 Ethical Standards, the NCARB Rules of Conduct & the Standard of Care 3.4 Business Structures, Firm Ownership Rules & Practice-Wide Methodologies
4 Chapter 4: Practice Management — Firm Finances & Financial Health
4.1 Utilization, Overhead, Break-Even & Net Multiplier 4.2 Liquidity, Solvency & Reading Firm Financials Strategically 4.3 Accrual vs. Cash Accounting & the Architectural Balance Sheet 4.4 The Income Statement, Net Operating Revenue & Cash Flow Management
5 Chapter 5: Practice Management — Risk, Insurance & Business Development
5.1 Risk Management & the Firm’s Insurance Portfolio 5.2 Contractual Risk Allocation, Intellectual Property & Dispute Resolution 5.3 Client Requests, Compensation Methods, Project Delivery & Project Risk
6 Chapter 6: Project Management — Team, Resources & Consultants
6.1 Assembling the Project Team: Roles, Authority & Selection Criteria 6.2 Allocating & Managing Project Resources: Hours, Rates & Leveling 6.3 Consultant Selection, Qualifications-Based Selection & Scope Boundaries 6.4 AIA C401: Flow-Through, Consultant Standard of Care, Insurance & Payment
7 Chapter 7: Project Management — Work Planning, Scheduling & Budget Control
7.1 The Project Work Plan & Phase Fee Allocation 7.2 Work Breakdown Structures, Scheduling Methods & Dependency Logic 7.3 Critical Path Calculations, Float & Schedule Compression 7.4 Project Communication: Paths, Instruments, Meetings & the Record 7.5 Monitoring the Project Budget with Earned Value Management 7.6 Scope Creep, Additional Services & Written Authorization
8 Chapter 8: Project Management — Contracts, Approvals & Quality Control
8.1 AIA B101: Initial Information, Standard of Care & Basic Services 8.2 B101: Owner Duties, Cost of the Work, Copyright, Termination & Compensation 8.3 The Owner-Contractor Agreement & A201 Contractor Responsibilities 8.4 A201: Architect Administration, Changes, Claims & Separate Contractors 8.5 Regulatory Compliance, Authorities Having Jurisdiction & Project Approvals 8.6 Documenting a Project for the Specified Delivery Method 8.7 Quality Assurance, Quality Control, Constructability & the Record
9 Chapter 9: Programming & Analysis — Site & Environmental Conditions
9.1 Climate Classification, Solar Geometry & Passive Site Opportunities 9.2 Microclimate, Wind, Topography, Grading & Site Hydrology 9.3 Environmental Due Diligence: CERCLA Liability & Phase I / Phase II Assessments 9.4 Soil Mechanics, Geotechnical Investigation & Foundation Selection 9.5 Vehicular Circulation, Access Management, Parking & Emergency Access
10 Chapter 10: Programming & Analysis — Zoning, Codes & Site Infrastructure
10.1 Pedestrian Circulation, Site Utilities & Contextual Constraints 10.2 Zoning Authority, Euclidean and Form-Based Codes & Bulk Standards 10.3 Non-Conforming Uses, Variances, Easements & Parking Feasibility 10.4 IBC Occupancy Classification, Mixed Occupancy & Incidental Uses 10.5 IBC Construction Types, Fire-Resistance Ratings & Compartmentation
11 Chapter 11: Programming & Analysis — Building Programming & Feasibility
11.1 Programming Methodology, Net vs. Gross Area & Building Efficiency 11.2 Adjacency Matrices, Bubble Diagrams, Blocking & Stacking 11.3 Evaluating an Existing Building Against a Program 11.4 Reviewing Project Budget & Schedule Feasibility Against Scope 11.5 Identifying Building & Structural System Alternatives at Programming
12 Chapter 12: Project Planning & Design — Siting, Configuration, Codes & Life Safety
12.1 Building Siting, Neighborhood Context, Zoning Application & Configuration 12.2 IBC Allowable Area: Tabular Area, Frontage & Sprinkler Increases 12.3 Building Height, Story Limits, Mixed Occupancy & Unlimited Area Buildings 12.4 Means of Egress Components & Occupant Load Calculation 12.5 Exit Count, Remoteness, Egress Capacity, Travel Distance & Dead Ends 12.6 Accessible Routes, Slopes, Protruding Objects & Ramp Design 12.7 Door Clearances, Operating Hardware & Accessible Toilet Room Geometry
13 Chapter 13: Project Planning & Design — Structural & Mechanical Systems
13.1 Selecting Structural Systems: Steel, Concrete, Wood & Masonry 13.2 Lateral Force-Resisting Systems, Wind Loads & Seismic Design 13.3 Thermal Comfort, ASHRAE Standard 55 & Psychrometrics 13.4 HVAC System Typologies, Spatial Allocation & Central Plant Equipment 13.5 Potable Water Supply, Drainage, Waste & Vent Systems 13.6 Electrical Distribution, Emergency Power, Lighting & Daylighting 13.7 Fire Suppression, Standpipes, Conveying, Security & Communications
14 Chapter 14: Project Planning & Design — Envelope, Materials & Cost
14.1 Envelope Thermodynamics, Heat Transfer & Fenestration Performance 14.2 Thermal Bridging, Continuous Insulation & Thermal Mass 14.3 Passive Solar Heating, Natural Ventilation & Daylighting Architecture 14.4 Material Selection Criteria, Fire Performance & Vapor Permeance 14.5 Life Cycle Assessment, Embodied Carbon & Material Transparency 14.6 Galvanic Compatibility, Thermal Movement & Masonry Durability 14.7 Cost Estimating by Phase & Contingency Planning 14.8 Life-Cycle Cost Analysis, Present Value & Value Engineering
15 Chapter 15: Project Development & Documentation — Roofing, Waterproofing & Wall Assemblies
15.1 Low-Slope Roofing Systems, Membranes & Drainage Geometry 15.2 Flashing, Parapets, Copings & Roof Penetration Detailing 15.3 Steep-Slope Roofing & Below-Grade Waterproofing 15.4 Enclosure Control Layers & Rain Screen Cladding Systems 15.5 Vapor Retarders, Permeance Classes & Dew Point Control
16 Chapter 16: Project Development & Documentation — Connections, Coordination & Interiors
16.1 Structural Steel Connections & Base Plate Detailing 16.2 Concrete Reinforcing, Cover & Building Movement Joints 16.3 Sizing Structural, Mechanical, Electrical & Plumbing Components 16.4 Ceiling Plenum Coordination, Clash Detection & Level of Development 16.5 Vertical Chases, Shaft Walls, Through-Penetration Firestopping & Rated Joints 16.6 Interior Partition Framing, Head-of-Wall Details & Rated Gypsum Assemblies 16.7 Sound Isolation, STC, NRC & Reverberation Time 16.8 Door and Frame Construction & Fire Door Assemblies Under NFPA 80 16.9 Hardware Functions, Fire-Protection vs. Fire-Resistance Glazing
17 Chapter 17: Project Development & Documentation — Drawings, Specifications & Estimates
17.1 The National CAD Standard, Sheet Modules & Title Blocks 17.2 Drawing Cross-Referencing, Coordination & Revision Control 17.3 Documenting Site Features: Survey, Civil, Grading, Utilities & Landscape 17.4 The Project Manual & CSI MasterFormat Divisions 17.5 Section Numbering & the CSI Three-Part SectionFormat 17.6 Specification Methods & Document Precedence 17.7 Quantity Takeoff Estimating, General Conditions, Overhead & Alternates
18 Chapter 18: Construction & Evaluation — Procurement, Bidding & Preconstruction
18.1 Procurement Methods & AIA A701 Instructions to Bidders 18.2 Addenda Mechanics & Surety Bonds 18.3 The Preconstruction Conference & Administrative Protocols 18.4 Submittal Schedules, Long-Lead Items, Permits & Special Inspections 18.5 Bid Opening, Bidder Qualification & Discrepancy Rules 18.6 Alternates, Allowances, Unit Prices & Contract Award
19 Chapter 19: Construction & Evaluation — Observation & Contract Administration
19.1 The Architect’s Site Observation Role & the Means and Methods Firewall 19.2 Rejecting Non-Conforming Work, Special Inspections & Field Reports 19.3 Submittal Workflow, Review Responsibility & Action Stamps 19.4 Delegated Design, Design-Assist & Deferred Submittals 19.5 Requests for Information & Architect’s Supplemental Instructions 19.6 Change Orders, Construction Change Directives & Instrument Comparison
20 Chapter 20: Construction & Evaluation — Payment, Closeout & Evaluation
20.1 The Schedule of Values & the Application and Certificate for Payment 20.2 Stored Materials, Retainage, Certification Duties & Withholding 20.3 Substantial Completion & the Punch List Protocol 20.4 The Certificate of Substantial Completion & Its Legal Consequences 20.5 Final Completion, Final Payment & the Closeout Package 20.6 Warranty Administration, the Eleven-Month Walk-Through & Post-Occupancy Evaluation
19.6 Change Orders, Construction Change Directives & Instrument Comparison
Key Takeaways Explain This Topic AI
A change order on AIA G701 requires the signatures of the owner, the contractor, and the architect, and it records agreement on scope, cost, and time.
A construction change directive on AIA G714 is signed by the owner and the architect but not the contractor, and it directs a change before agreement is reached.
Under A201 Section 7.3.5 the contractor must promptly proceed with work directed by a construction change directive even while the cost remains in dispute.
Where cost is disputed, A201 Section 7.3.4 permits the architect to determine the adjustment based on cost plus a reasonable allowance for overhead and profit.
A construction change directive converts to a change order once the contractor agrees with the adjustment, and interim amounts may be certified for payment in the meantime.
Last updated: September 2026
Change Orders (AIA Document G701)
When a change in the work impacts the project scope, cost, or timeline, the standard instrument for modifying the contract is AIA Document G701™ (Change Order) . AIA A201 Section 7.2.1 defines a Change Order as a written instrument prepared by the architect and signed by the Owner, Architect, and Contractor .
The Tripartite Agreement Rule
A Change Order is a consensual, tripartite contract amendment. It requires the agreement and signatures of all three primary project participants:
The Owner: Authorizes the expenditure of capital and/or schedule alteration.
The Contractor: Agrees to perform the modified work for the agreed cost and time adjustments.
The Architect: Certifies that the change is consistent with the design concept, verifies that proposed unit costs or labor rates are fair and reasonable, and coordinates documentation. ┌────────────────────────────────────────────────────────────────────────┐
- │ THE CHANGE ORDER TRIAD │
- │ (AIA Document G701) │
- ├────────────────────────────────────────────────────────────────────────┤
- │ Complete mutual agreement on ALL THREE components is legally required: │
- │ │
- │ 1. The CHANGE IN THE WORK (Scope Definition) │
- │ ▲ │
- │ ╱ ╲ │
- │ ╱ ╲ │
- │ ▼ ▼ │
- │ 2. ADJUSTMENT IN CONTRACT SUM 3. ADJUSTMENT IN CONTRACT TIME │
- │ (Agreed Dollar Amount) (Agreed Number of Calendar Days) │
- └────────────────────────────────────────────────────────────────────────┘
- The Change Order Processing Lifecycle
Proposal Request (AIA Document G709™): The architect issues a formal Proposal Request (PR) or Bulletin to the contractor, describing the contemplated scope change with accompanying sketches. The PR is not an instruction to stop work or execute changes; it is a request for a detailed cost and schedule quotation.
Contractor's Change Proposal: The contractor compiles an itemized cost estimate from subcontractors and suppliers, detailing direct labor hours, wage rates, material quantities, equipment rental, taxes, insurance, and allowable contractor overhead and profit markup.
Architectural Evaluation: The architect evaluates the contractor's quotation against independent cost estimates, verifies that overhead and profit markups comply with contractual caps, and advises the owner.
Execution of G701: Upon owner approval, the architect prepares AIA Document G701, detailing the original Contract Sum, net change by previous Change Orders, Contract Sum prior to this Change Order, sum adjustment, new Contract Sum, and new Substantial Completion date. All three parties execute the document.
Construction Change Directives (AIA Document G714)
In fast-track construction or complex projects, situations frequently arise where work must proceed immediately to maintain the critical-path schedule, but the owner and contractor cannot agree on the price or time adjustment. Alternatively, emergency conditions (such as encountering unanticipated buried bedrock or contaminated soil) may require immediate action before an itemized cost proposal can be prepared.
To resolve this dilemma and prevent project paralysis, AIA A201 Section 7.3 provides the Construction Change Directive (CCD) , documented on AIA Document G714™ .
Legal Nature & Signatures of a CCD
Under AIA A201 Section 7.3.1, a Construction Change Directive is a written order prepared by the architect and signed by the Owner and Architect only (a bilateral instrument). It bypasses the contractor's signature.
Contractor's Mandatory Duty to Proceed (A201 Section 7.3.5)
Upon receipt of a Construction Change Directive signed by the owner and architect, the contractor MUST promptly proceed with the change in the work . The contractor has no contractual right to halt operations, delay construction, or stage a work stoppage pending price negotiation. Refusal to proceed constitutes a material breach of contract.
Contractor Agreement with CCD (A201 Section 7.3.6)
If the CCD includes a proposed basis for adjusting the Contract Sum and Contract Time, and the contractor agrees with that proposal, the contractor signs the CCD. Under Section 7.3.6, such agreement becomes effective immediately as a Change Order, formally amending the Contract Sum and Contract Time.
Determining Cost under A201 Section 7.3.4 (Disputed or Unknown Costs)
If the contractor does not agree with the proposed adjustment or if no method was agreed upon in advance, AIA A201 Section 7.3.4 dictates that the cost adjustment shall be determined by the architect on the basis of actual reasonable expenditures and savings : ┌────────────────────────────────────────────────────────────────────────┐
- │ ALLOWABLE DIRECT COSTS UNDER A201 § 7.3.4 │
- ├────────────────────────────────────────────────────────────────────────┤
- │ 1. LABOR: Hourly wages, payroll taxes, fringe benefits, workers' comp. │
- │ 2. MATERIALS: Actual cost of materials, supplies, equipment, freight. │
- │ 3. EQUIPMENT RENTAL: Rental cost of machinery and hand tools. │
- │ 4. INSURANCE & BONDS: Premiums for additional bonds and liability. │
- │ 5. FIELD SUPERVISION: Additional job site supervisory personnel costs │
- │ directly attributable to the change. │
- │ 6. OVERHEAD & PROFIT: Standard contractor markup as defined in contract│
- └────────────────────────────────────────────────────────────────────────┘
The contractor must submit detailed, itemized daily records—certified payroll slips, material invoices, equipment rental receipts, and subcontractor billings—to document actual expenditures.
Interim Payment Certification under a CCD (A201 Section 7.3.9)
A common ARE 5.0 scenario tests how the contractor gets paid while a CCD cost dispute is being resolved. Under AIA A201 Section 7.3.9:
"Pending final determination of the total cost of a Construction Change Directive to the Owner, the Contractor may request payment for Work completed under the Construction Change Directive in Applications for Payment. The Architect will make an interim determination for purposes of monthly certification for payment for those costs and certify for payment the amount that the Architect determines, in the Architect's professional judgment, to be reasonably justified."
The architect certifies undisputed amounts on interim pay applications (AIA G702), ensuring the contractor's cash flow is maintained while disputed balance items are adjudicated through claims and dispute resolution.
Comparison of Contract Administration Instruments
Instrument AIA Document Required Signatures Adjusts Contract Sum? Adjusts Contract Time? Governing Circumstance
Request for Information (RFI) Industry Standard / Proprietary Initiated by Contractor; Answered by Architect NO NO Contractor requests interpretation or clarification of design intent.
Architect's Supplemental Instructions (ASI) AIA G710 Architect ONLY NO ($0.00) NO (0 days) Minor modifications consistent with contract intent; no cost or time impact.
Change Order (CO) AIA G701 Owner + Architect + Contractor (Tripartite) YES (Mutual Accord) YES (Mutual Accord) Scope changes with fully agreed cost and schedule adjustments.
Construction Change Directive (CCD) AIA G714 Owner + Architect (Bilateral) YES (Determined per § 7.3.4) YES (Determined by Architect) Urgent change required where cost or time is not mutually agreed; contractor must proceed immediately.