19.4 Delegated Design, Design-Assist & Deferred Submittals
Architect Registration Examination ARE 5.0
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: ARE 5.0 Structure, Delivery & Scoring
1.1 The Six Divisions: Items, Durations, Sections & Objectives 1.2 Eligibility, PSI Delivery, Fees, Scheduling & Rescheduling 1.3 Cut Scores, Score Reports, Provisional Feedback & Retakes
2 Chapter 2: Licensure Path, Item Types & Test-Day Strategy
2.1 Education Standard, AXP Hours, Settings & Reporting Rules 2.2 The NCARB Record, Score Validity Policy & Reciprocity 2.3 Item Types, Case Studies, Exam Tools, Breaks & Pacing
3 Chapter 3: Practice Management — Firm Resources, Conduct & the Work Environment
3.1 Assessing Practice Resources: Staffing, Development & Capital Investment 3.2 Regulating the Work Environment: FLSA, Antidiscrimination Law, OSHA & ADA Title III 3.3 Ethical Standards, the NCARB Rules of Conduct & the Standard of Care 3.4 Business Structures, Firm Ownership Rules & Practice-Wide Methodologies
4 Chapter 4: Practice Management — Firm Finances & Financial Health
4.1 Utilization, Overhead, Break-Even & Net Multiplier 4.2 Liquidity, Solvency & Reading Firm Financials Strategically 4.3 Accrual vs. Cash Accounting & the Architectural Balance Sheet 4.4 The Income Statement, Net Operating Revenue & Cash Flow Management
5 Chapter 5: Practice Management — Risk, Insurance & Business Development
5.1 Risk Management & the Firm’s Insurance Portfolio 5.2 Contractual Risk Allocation, Intellectual Property & Dispute Resolution 5.3 Client Requests, Compensation Methods, Project Delivery & Project Risk
6 Chapter 6: Project Management — Team, Resources & Consultants
6.1 Assembling the Project Team: Roles, Authority & Selection Criteria 6.2 Allocating & Managing Project Resources: Hours, Rates & Leveling 6.3 Consultant Selection, Qualifications-Based Selection & Scope Boundaries 6.4 AIA C401: Flow-Through, Consultant Standard of Care, Insurance & Payment
7 Chapter 7: Project Management — Work Planning, Scheduling & Budget Control
7.1 The Project Work Plan & Phase Fee Allocation 7.2 Work Breakdown Structures, Scheduling Methods & Dependency Logic 7.3 Critical Path Calculations, Float & Schedule Compression 7.4 Project Communication: Paths, Instruments, Meetings & the Record 7.5 Monitoring the Project Budget with Earned Value Management 7.6 Scope Creep, Additional Services & Written Authorization
8 Chapter 8: Project Management — Contracts, Approvals & Quality Control
8.1 AIA B101: Initial Information, Standard of Care & Basic Services 8.2 B101: Owner Duties, Cost of the Work, Copyright, Termination & Compensation 8.3 The Owner-Contractor Agreement & A201 Contractor Responsibilities 8.4 A201: Architect Administration, Changes, Claims & Separate Contractors 8.5 Regulatory Compliance, Authorities Having Jurisdiction & Project Approvals 8.6 Documenting a Project for the Specified Delivery Method 8.7 Quality Assurance, Quality Control, Constructability & the Record
9 Chapter 9: Programming & Analysis — Site & Environmental Conditions
9.1 Climate Classification, Solar Geometry & Passive Site Opportunities 9.2 Microclimate, Wind, Topography, Grading & Site Hydrology 9.3 Environmental Due Diligence: CERCLA Liability & Phase I / Phase II Assessments 9.4 Soil Mechanics, Geotechnical Investigation & Foundation Selection 9.5 Vehicular Circulation, Access Management, Parking & Emergency Access
10 Chapter 10: Programming & Analysis — Zoning, Codes & Site Infrastructure
10.1 Pedestrian Circulation, Site Utilities & Contextual Constraints 10.2 Zoning Authority, Euclidean and Form-Based Codes & Bulk Standards 10.3 Non-Conforming Uses, Variances, Easements & Parking Feasibility 10.4 IBC Occupancy Classification, Mixed Occupancy & Incidental Uses 10.5 IBC Construction Types, Fire-Resistance Ratings & Compartmentation
11 Chapter 11: Programming & Analysis — Building Programming & Feasibility
11.1 Programming Methodology, Net vs. Gross Area & Building Efficiency 11.2 Adjacency Matrices, Bubble Diagrams, Blocking & Stacking 11.3 Evaluating an Existing Building Against a Program 11.4 Reviewing Project Budget & Schedule Feasibility Against Scope 11.5 Identifying Building & Structural System Alternatives at Programming
12 Chapter 12: Project Planning & Design — Siting, Configuration, Codes & Life Safety
12.1 Building Siting, Neighborhood Context, Zoning Application & Configuration 12.2 IBC Allowable Area: Tabular Area, Frontage & Sprinkler Increases 12.3 Building Height, Story Limits, Mixed Occupancy & Unlimited Area Buildings 12.4 Means of Egress Components & Occupant Load Calculation 12.5 Exit Count, Remoteness, Egress Capacity, Travel Distance & Dead Ends 12.6 Accessible Routes, Slopes, Protruding Objects & Ramp Design 12.7 Door Clearances, Operating Hardware & Accessible Toilet Room Geometry
13 Chapter 13: Project Planning & Design — Structural & Mechanical Systems
13.1 Selecting Structural Systems: Steel, Concrete, Wood & Masonry 13.2 Lateral Force-Resisting Systems, Wind Loads & Seismic Design 13.3 Thermal Comfort, ASHRAE Standard 55 & Psychrometrics 13.4 HVAC System Typologies, Spatial Allocation & Central Plant Equipment 13.5 Potable Water Supply, Drainage, Waste & Vent Systems 13.6 Electrical Distribution, Emergency Power, Lighting & Daylighting 13.7 Fire Suppression, Standpipes, Conveying, Security & Communications
14 Chapter 14: Project Planning & Design — Envelope, Materials & Cost
14.1 Envelope Thermodynamics, Heat Transfer & Fenestration Performance 14.2 Thermal Bridging, Continuous Insulation & Thermal Mass 14.3 Passive Solar Heating, Natural Ventilation & Daylighting Architecture 14.4 Material Selection Criteria, Fire Performance & Vapor Permeance 14.5 Life Cycle Assessment, Embodied Carbon & Material Transparency 14.6 Galvanic Compatibility, Thermal Movement & Masonry Durability 14.7 Cost Estimating by Phase & Contingency Planning 14.8 Life-Cycle Cost Analysis, Present Value & Value Engineering
15 Chapter 15: Project Development & Documentation — Roofing, Waterproofing & Wall Assemblies
15.1 Low-Slope Roofing Systems, Membranes & Drainage Geometry 15.2 Flashing, Parapets, Copings & Roof Penetration Detailing 15.3 Steep-Slope Roofing & Below-Grade Waterproofing 15.4 Enclosure Control Layers & Rain Screen Cladding Systems 15.5 Vapor Retarders, Permeance Classes & Dew Point Control
16 Chapter 16: Project Development & Documentation — Connections, Coordination & Interiors
16.1 Structural Steel Connections & Base Plate Detailing 16.2 Concrete Reinforcing, Cover & Building Movement Joints 16.3 Sizing Structural, Mechanical, Electrical & Plumbing Components 16.4 Ceiling Plenum Coordination, Clash Detection & Level of Development 16.5 Vertical Chases, Shaft Walls, Through-Penetration Firestopping & Rated Joints 16.6 Interior Partition Framing, Head-of-Wall Details & Rated Gypsum Assemblies 16.7 Sound Isolation, STC, NRC & Reverberation Time 16.8 Door and Frame Construction & Fire Door Assemblies Under NFPA 80 16.9 Hardware Functions, Fire-Protection vs. Fire-Resistance Glazing
17 Chapter 17: Project Development & Documentation — Drawings, Specifications & Estimates
17.1 The National CAD Standard, Sheet Modules & Title Blocks 17.2 Drawing Cross-Referencing, Coordination & Revision Control 17.3 Documenting Site Features: Survey, Civil, Grading, Utilities & Landscape 17.4 The Project Manual & CSI MasterFormat Divisions 17.5 Section Numbering & the CSI Three-Part SectionFormat 17.6 Specification Methods & Document Precedence 17.7 Quantity Takeoff Estimating, General Conditions, Overhead & Alternates
18 Chapter 18: Construction & Evaluation — Procurement, Bidding & Preconstruction
18.1 Procurement Methods & AIA A701 Instructions to Bidders 18.2 Addenda Mechanics & Surety Bonds 18.3 The Preconstruction Conference & Administrative Protocols 18.4 Submittal Schedules, Long-Lead Items, Permits & Special Inspections 18.5 Bid Opening, Bidder Qualification & Discrepancy Rules 18.6 Alternates, Allowances, Unit Prices & Contract Award
19 Chapter 19: Construction & Evaluation — Observation & Contract Administration
19.1 The Architect’s Site Observation Role & the Means and Methods Firewall 19.2 Rejecting Non-Conforming Work, Special Inspections & Field Reports 19.3 Submittal Workflow, Review Responsibility & Action Stamps 19.4 Delegated Design, Design-Assist & Deferred Submittals 19.5 Requests for Information & Architect’s Supplemental Instructions 19.6 Change Orders, Construction Change Directives & Instrument Comparison
20 Chapter 20: Construction & Evaluation — Payment, Closeout & Evaluation
20.1 The Schedule of Values & the Application and Certificate for Payment 20.2 Stored Materials, Retainage, Certification Duties & Withholding 20.3 Substantial Completion & the Punch List Protocol 20.4 The Certificate of Substantial Completion & Its Legal Consequences 20.5 Final Completion, Final Payment & the Closeout Package 20.6 Warranty Administration, the Eleven-Month Walk-Through & Post-Occupancy Evaluation
19.4 Delegated Design, Design-Assist & Deferred Submittals
Key Takeaways Explain This Topic AI
Delegated design requires the architect to specify performance and design criteria, after which a licensed professional retained by the contractor performs the engineering.
The architect reviews delegated design submittals only for conformance with the specified performance criteria, not for the adequacy of the engineering.
Design-assist brings a contractor or fabricator into the design process for constructability and pricing input, while design responsibility remains with the architect.
Common delegated design items include trusses, curtain wall anchorage, precast connections, and fire sprinkler layout.
Deferred submittals must be identified on the permit documents, reviewed by the design professional in responsible charge, and approved by the building official before that work is installed.
Last updated: September 2026
Delegated Design & Design-Assist
Modern construction documentation frequently delegates the detailed engineering of specialized building components to the general contractor and specialty trade fabricators. AIA Document A201 Section 3.12.10 governs this delivery mechanism, known as Delegated Design .
Common Applications of Delegated Design
Structural Steel Connections: Fabricator's licensed engineer designs shear tabs, moment connections, and gusset plates based on reactions provided on structural drawings.
Precast / Prestressed Concrete: Specialty structural engineer calculates strand prestressing, handling stresses, and erection anchorage.
Curtain Wall & Glazing Systems: Specialty engineer calculates aluminum extrusion mullion profiles, wind-load deflections, thermal expansion joints, and anchor attachments.
Open-Web Steel Joists: Joist manufacturer designs internal web lacing and weld connections based on specified uniform and concentrated load diagrams.
Fire Suppression Sprinkler Systems: Fire protection contractor calculates hydraulic flow rates, pipe friction losses, and sprinkler head layouts per NFPA 13.
Metal Stairs and Handrails: Fabricator designs stringers, treads, and railing post attachments to resist code-mandated 200 lb concentrated loads and 50 lb/ft uniform loads.
Division of Responsibilities under A201 Section 3.12.10
The contractual division of professional liability in delegated design is articulated in Section 3.12.10: ┌────────────────────────────────────────────────────────────────────────┐
- │ DELEGATED DESIGN HIERARCHY │
- ├────────────────────────────────────────────────────────────────────────┤
- │ ARCHITECT OF RECORD / STRUCTURAL ENGINEER OF RECORD (EOR): │
- │ • Establishes design concept, overall performance criteria, loads, │
- │ spans, geometric constraints, deflection limits, and design codes. │
- │ │
- │ CONTRACTOR'S SPECIALTY STRUCTURAL ENGINEER (SSE / DELEGATED ENGINEER): │
- │ • Retained and compensated by contractor or specialty subcontractor. │
- │ • Must be legally licensed in the jurisdiction where project is built. │
- │ • Prepares, signs, and SEALS all delegated calculations and drawings. │
- │ • Carries professional liability for the performance of the component.│
- │ │
- │ ARCHITECT'S REVIEW BOUNDARY (A201 § 3.12.10.1): │
- │ • Reviews delegated submittals ONLY for design concept conformance. │
- │ • Legally ENTITLED TO RELY upon the adequacy, accuracy, and │
- │ completeness of the calculations and certifications sealed by the │
- │ contractor's licensed professional engineer. │
- │ • Architect NEVER stamps or seals the specialty engineer's calcs! │
- └────────────────────────────────────────────────────────────────────────┘
Under Section 3.12.10.1, the architect and owner are granted a legal safe harbor : they are explicitly entitled to rely upon the adequacy and accuracy of the performance and design criteria, calculations, and certifications provided by the contractor's licensed design professional. The architect does not perform secondary engineering calculations or co-sign the specialty engineer's work.
Delegated Design vs. Design-Assist
Candidates must distinguish delegated design from design-assist :
Delegated Design: Formal contractual assignment of complete design and engineering responsibility for a distinct component to a licensed professional retained by the contractor, occurring during the construction phase via sealed submittals.
Design-Assist: An early procurement collaboration where key trade contractors (e.g., curtain wall, mechanical, steel) are brought onto the project team during Schematic Design or Design Development to provide constructability reviews, budget estimating, detailing advice, and value engineering before the architect completes the construction documents. The architect retains ultimate design responsibility for the completed drawings.
Submittal Types and Deferred Submittals
Not every submittal is a shop drawing, and the type determines what the architect's review actually certifies.
Submittal type What it is What the architect reviews it for
Shop drawings Contractor-prepared fabrication and installation drawings Conformance with the design concept and with the information in the contract documents
Product data Manufacturer literature for a specified product That the product proposed is the product specified
Samples Physical examples of material, finish, or workmanship Color, texture, and finish only, unless the specification says otherwise
Mock-ups Full-scale constructed assemblies Workmanship standard and assembly performance, sometimes with field testing
Test reports and certificates Third-party verification That required testing was performed and passed
Delegated design submittals Engineered design by a contractor's licensed engineer Conformance with the performance criteria the architect specified
Deferred Submittals
Some engineered components are not designed at the time of permit — trusses, curtain wall anchorage, fire sprinkler layout, precast connections. The building code permits these as deferred submittals when the registered design professional in responsible charge identifies them on the permit documents. The deferred submittal documents are reviewed by that design professional for general conformance with the design of the building, then forwarded to the building official. No deferred work may be installed until the building official has approved the deferred submittal.
That sequence produces a recurring exam scenario: a contractor who fabricates and installs a deferred-submittal item before the authority having jurisdiction has approved it has assumed the risk of removal, regardless of whether the architect reviewed the submittal.