19.5 Requests for Information & Architect’s Supplemental Instructions

Architect Registration Examination ARE 5.0

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: ARE 5.0 Structure, Delivery & Scoring

1.1 The Six Divisions: Items, Durations, Sections & Objectives 1.2 Eligibility, PSI Delivery, Fees, Scheduling & Rescheduling 1.3 Cut Scores, Score Reports, Provisional Feedback & Retakes

2 Chapter 2: Licensure Path, Item Types & Test-Day Strategy

2.1 Education Standard, AXP Hours, Settings & Reporting Rules 2.2 The NCARB Record, Score Validity Policy & Reciprocity 2.3 Item Types, Case Studies, Exam Tools, Breaks & Pacing

3 Chapter 3: Practice Management — Firm Resources, Conduct & the Work Environment

3.1 Assessing Practice Resources: Staffing, Development & Capital Investment 3.2 Regulating the Work Environment: FLSA, Antidiscrimination Law, OSHA & ADA Title III 3.3 Ethical Standards, the NCARB Rules of Conduct & the Standard of Care 3.4 Business Structures, Firm Ownership Rules & Practice-Wide Methodologies

4 Chapter 4: Practice Management — Firm Finances & Financial Health

4.1 Utilization, Overhead, Break-Even & Net Multiplier 4.2 Liquidity, Solvency & Reading Firm Financials Strategically 4.3 Accrual vs. Cash Accounting & the Architectural Balance Sheet 4.4 The Income Statement, Net Operating Revenue & Cash Flow Management

5 Chapter 5: Practice Management — Risk, Insurance & Business Development

5.1 Risk Management & the Firm’s Insurance Portfolio 5.2 Contractual Risk Allocation, Intellectual Property & Dispute Resolution 5.3 Client Requests, Compensation Methods, Project Delivery & Project Risk

6 Chapter 6: Project Management — Team, Resources & Consultants

6.1 Assembling the Project Team: Roles, Authority & Selection Criteria 6.2 Allocating & Managing Project Resources: Hours, Rates & Leveling 6.3 Consultant Selection, Qualifications-Based Selection & Scope Boundaries 6.4 AIA C401: Flow-Through, Consultant Standard of Care, Insurance & Payment

7 Chapter 7: Project Management — Work Planning, Scheduling & Budget Control

7.1 The Project Work Plan & Phase Fee Allocation 7.2 Work Breakdown Structures, Scheduling Methods & Dependency Logic 7.3 Critical Path Calculations, Float & Schedule Compression 7.4 Project Communication: Paths, Instruments, Meetings & the Record 7.5 Monitoring the Project Budget with Earned Value Management 7.6 Scope Creep, Additional Services & Written Authorization

8 Chapter 8: Project Management — Contracts, Approvals & Quality Control

8.1 AIA B101: Initial Information, Standard of Care & Basic Services 8.2 B101: Owner Duties, Cost of the Work, Copyright, Termination & Compensation 8.3 The Owner-Contractor Agreement & A201 Contractor Responsibilities 8.4 A201: Architect Administration, Changes, Claims & Separate Contractors 8.5 Regulatory Compliance, Authorities Having Jurisdiction & Project Approvals 8.6 Documenting a Project for the Specified Delivery Method 8.7 Quality Assurance, Quality Control, Constructability & the Record

9 Chapter 9: Programming & Analysis — Site & Environmental Conditions

9.1 Climate Classification, Solar Geometry & Passive Site Opportunities 9.2 Microclimate, Wind, Topography, Grading & Site Hydrology 9.3 Environmental Due Diligence: CERCLA Liability & Phase I / Phase II Assessments 9.4 Soil Mechanics, Geotechnical Investigation & Foundation Selection 9.5 Vehicular Circulation, Access Management, Parking & Emergency Access

10 Chapter 10: Programming & Analysis — Zoning, Codes & Site Infrastructure

10.1 Pedestrian Circulation, Site Utilities & Contextual Constraints 10.2 Zoning Authority, Euclidean and Form-Based Codes & Bulk Standards 10.3 Non-Conforming Uses, Variances, Easements & Parking Feasibility 10.4 IBC Occupancy Classification, Mixed Occupancy & Incidental Uses 10.5 IBC Construction Types, Fire-Resistance Ratings & Compartmentation

11 Chapter 11: Programming & Analysis — Building Programming & Feasibility

11.1 Programming Methodology, Net vs. Gross Area & Building Efficiency 11.2 Adjacency Matrices, Bubble Diagrams, Blocking & Stacking 11.3 Evaluating an Existing Building Against a Program 11.4 Reviewing Project Budget & Schedule Feasibility Against Scope 11.5 Identifying Building & Structural System Alternatives at Programming

12 Chapter 12: Project Planning & Design — Siting, Configuration, Codes & Life Safety

12.1 Building Siting, Neighborhood Context, Zoning Application & Configuration 12.2 IBC Allowable Area: Tabular Area, Frontage & Sprinkler Increases 12.3 Building Height, Story Limits, Mixed Occupancy & Unlimited Area Buildings 12.4 Means of Egress Components & Occupant Load Calculation 12.5 Exit Count, Remoteness, Egress Capacity, Travel Distance & Dead Ends 12.6 Accessible Routes, Slopes, Protruding Objects & Ramp Design 12.7 Door Clearances, Operating Hardware & Accessible Toilet Room Geometry

13 Chapter 13: Project Planning & Design — Structural & Mechanical Systems

13.1 Selecting Structural Systems: Steel, Concrete, Wood & Masonry 13.2 Lateral Force-Resisting Systems, Wind Loads & Seismic Design 13.3 Thermal Comfort, ASHRAE Standard 55 & Psychrometrics 13.4 HVAC System Typologies, Spatial Allocation & Central Plant Equipment 13.5 Potable Water Supply, Drainage, Waste & Vent Systems 13.6 Electrical Distribution, Emergency Power, Lighting & Daylighting 13.7 Fire Suppression, Standpipes, Conveying, Security & Communications

14 Chapter 14: Project Planning & Design — Envelope, Materials & Cost

14.1 Envelope Thermodynamics, Heat Transfer & Fenestration Performance 14.2 Thermal Bridging, Continuous Insulation & Thermal Mass 14.3 Passive Solar Heating, Natural Ventilation & Daylighting Architecture 14.4 Material Selection Criteria, Fire Performance & Vapor Permeance 14.5 Life Cycle Assessment, Embodied Carbon & Material Transparency 14.6 Galvanic Compatibility, Thermal Movement & Masonry Durability 14.7 Cost Estimating by Phase & Contingency Planning 14.8 Life-Cycle Cost Analysis, Present Value & Value Engineering

15 Chapter 15: Project Development & Documentation — Roofing, Waterproofing & Wall Assemblies

15.1 Low-Slope Roofing Systems, Membranes & Drainage Geometry 15.2 Flashing, Parapets, Copings & Roof Penetration Detailing 15.3 Steep-Slope Roofing & Below-Grade Waterproofing 15.4 Enclosure Control Layers & Rain Screen Cladding Systems 15.5 Vapor Retarders, Permeance Classes & Dew Point Control

16 Chapter 16: Project Development & Documentation — Connections, Coordination & Interiors

16.1 Structural Steel Connections & Base Plate Detailing 16.2 Concrete Reinforcing, Cover & Building Movement Joints 16.3 Sizing Structural, Mechanical, Electrical & Plumbing Components 16.4 Ceiling Plenum Coordination, Clash Detection & Level of Development 16.5 Vertical Chases, Shaft Walls, Through-Penetration Firestopping & Rated Joints 16.6 Interior Partition Framing, Head-of-Wall Details & Rated Gypsum Assemblies 16.7 Sound Isolation, STC, NRC & Reverberation Time 16.8 Door and Frame Construction & Fire Door Assemblies Under NFPA 80 16.9 Hardware Functions, Fire-Protection vs. Fire-Resistance Glazing

17 Chapter 17: Project Development & Documentation — Drawings, Specifications & Estimates

17.1 The National CAD Standard, Sheet Modules & Title Blocks 17.2 Drawing Cross-Referencing, Coordination & Revision Control 17.3 Documenting Site Features: Survey, Civil, Grading, Utilities & Landscape 17.4 The Project Manual & CSI MasterFormat Divisions 17.5 Section Numbering & the CSI Three-Part SectionFormat 17.6 Specification Methods & Document Precedence 17.7 Quantity Takeoff Estimating, General Conditions, Overhead & Alternates

18 Chapter 18: Construction & Evaluation — Procurement, Bidding & Preconstruction

18.1 Procurement Methods & AIA A701 Instructions to Bidders 18.2 Addenda Mechanics & Surety Bonds 18.3 The Preconstruction Conference & Administrative Protocols 18.4 Submittal Schedules, Long-Lead Items, Permits & Special Inspections 18.5 Bid Opening, Bidder Qualification & Discrepancy Rules 18.6 Alternates, Allowances, Unit Prices & Contract Award

19 Chapter 19: Construction & Evaluation — Observation & Contract Administration

19.1 The Architect’s Site Observation Role & the Means and Methods Firewall 19.2 Rejecting Non-Conforming Work, Special Inspections & Field Reports 19.3 Submittal Workflow, Review Responsibility & Action Stamps 19.4 Delegated Design, Design-Assist & Deferred Submittals 19.5 Requests for Information & Architect’s Supplemental Instructions 19.6 Change Orders, Construction Change Directives & Instrument Comparison

20 Chapter 20: Construction & Evaluation — Payment, Closeout & Evaluation

20.1 The Schedule of Values & the Application and Certificate for Payment 20.2 Stored Materials, Retainage, Certification Duties & Withholding 20.3 Substantial Completion & the Punch List Protocol 20.4 The Certificate of Substantial Completion & Its Legal Consequences 20.5 Final Completion, Final Payment & the Closeout Package 20.6 Warranty Administration, the Eleven-Month Walk-Through & Post-Occupancy Evaluation

19.5 Requests for Information & Architect’s Supplemental Instructions

Key Takeaways Explain This Topic AI

A request for information seeks clarification of the contract documents and is never authorization for a change in the work.

The architect must respond to RFIs with reasonable promptness, and unreasonable delay can itself become the basis of a delay claim.

High RFI volume on a single trade or detail is a leading indicator of a documentation problem that should be addressed at its source.

An architect’s supplemental instruction on AIA Document G710 orders a minor change consistent with the intent of the contract documents.

A G710 may be issued only where the change involves no adjustment to the contract sum or contract time, and it is signed by the architect alone.

Last updated: September 2026

Clarification & Contract Modification Instruments under AIA A201

During the construction phase of a building project, changes and clarifications are inevitable. Unforeseen subsurface site conditions, building code interpretations by local officials, owner-requested scope modifications, and documentation ambiguities require standardized administrative instruments to maintain contract integrity.

AIA Document A201–2017 establishes a rigid hierarchy of clarification and contract modification instruments, each designed for specific contractual circumstances and governed by strict signature rules: ┌────────────────────────────────────────────────────────────────────────┐

  • │ CONTRACT MODIFICATION INSTRUMENT HIERARCHY │
  • ├────────────────────────────────────────────────────────────────────────┤
  • │ 1. REQUEST FOR INFORMATION (RFI): │
  • │ Inquiry mechanism seeking interpretation. NOT a change instrument. │
  • │ │
  • │ 2. ARCHITECT'S SUPPLEMENTAL INSTRUCTIONS (ASI - AIA G710): │
  • │ • Signed by ARCHITECT ONLY. │
  • │ • Minor change in the work. $0 cost change, 0 days time change. │
  • │ │
  • │ 3. CONSTRUCTION CHANGE DIRECTIVE (CCD - AIA G714): │
  • │ • Signed by OWNER + ARCHITECT (Bilateral). │
  • │ • Mandatory order to proceed when cost/time is disputed or unknown. │
  • │ │
  • │ 4. CHANGE ORDER (CO - AIA G701): │
  • │ • Signed by OWNER + ARCHITECT + CONTRACTOR (Tripartite agreement). │
  • │ • Complete mutual accord on Scope Change, Cost Change, Time Change. │
  • └────────────────────────────────────────────────────────────────────────┘
  • Requests for Information (RFIs): Protocol & Claim Boundaries

A Request for Information (RFI) is a formal written inquiry initiated by the contractor to seek clarification or interpretation of the Contract Documents (drawings, specifications, or details) when an ambiguity, conflict, or omission is encountered in the field.

Architect's Responsibilities under A201 Section 4.2.14

Under AIA A201 Section 4.2.14, the architect must review and respond to RFIs with reasonable promptness , adhering to any agreed-upon submittal and RFI response schedule established at the preconstruction conference (typically 7 to 14 calendar days). The architect's response must be written and may include supplementary sketches or revised details.

The Critical Legal Boundary: An RFI Is NOT a Change Authorization

An architect's response to an RFI provides interpretation of the design intent— it does not authorize a change in the Contract Sum or Contract Time . This boundary is a frequent source of contractor claims and ARE exam questions:

If the contractor believes that an architect's RFI response clarifies a detail by introducing additional materials, higher-grade finishes, or more labor-intensive assemblies not originally included in the Contract Documents, the contractor must not proceed with the work .

Under AIA A201 Section 15.1.3, the contractor must provide written notice of a claim for an increase in Contract Sum or Contract Time to the owner and architect within 21 days after the occurrence of the event giving rise to the claim (or within the timeframe specified in the contract).

If the contractor proceeds to execute the work based on an RFI response without giving timely written notice of a claim, the contractor waives all legal rights to seek additional compensation or time extensions later.

RFI Tracking and Risk Management

In contemporary practice, contractors sometimes submit hundreds of speculative or unnecessary RFIs ("shotgun RFIs") to construct a paper trail for future delay claims. Architects mitigate this risk by maintaining a rigorous RFI tracking log recording: RFI number, date received, drawing/specification reference, subject, date returned, days in review, and whether the response impacted cost or time. If an RFI asks a question that is already clearly answered in the drawings or specifications, the architect should respond factually by referencing the exact sheet and detail number, noting that the inquiry is covered under the base contract.

Minor Changes in the Work: Architect's Supplemental Instructions (AIA G710)

Under AIA A201 Section 7.4, the architect possesses independent unilateral authority to order minor adjustments to the work:

"The Architect may order minor changes in the Work that are consistent with the intent of the Contract Documents and do not involve an adjustment in the Contract Sum or an extension of the Contract Time. The Architect's order for minor changes shall be in writing. If the Contractor believes that the proposed minor change in the Work will affect the Contract Sum or Contract Time, the Contractor shall notify the Architect and shall not proceed to implement the change in the Work."

The standard AIA instrument used for this purpose is AIA Document G710™ (Architect's Supplemental Instructions - ASI) .

Legal Characteristics of an ASI

Signatures Required: The ASI is issued and signed by the Architect only . Neither the owner's signature nor the contractor's signature is required for the instruction to become binding.

Absolute Financial & Schedule Restrictions: An ASI CANNOT increase or decrease the Contract Sum , and it CANNOT increase or decrease the Contract Time . It must represent zero financial impact ($0.00) and zero schedule impact (0 calendar days).

Typical Applications: Clarifying an un-dimensioned partition location; shifting an interior gypsum wall 2 inches to allow clearance for a plumbing waste riser; substituting a specified paint color for another color within the same manufacturer formulation tier; reversing the swing of an interior door that does not affect egress ratings.

Contractor's Safeguard: If the contractor receives an ASI and determines that the instruction will, in fact, cause an expenditure of additional labor or materials or cause a schedule delay, the contractor must immediately notify the architect in writing and refuse to execute the work. If the contractor proceeds with the ASI work without written notice, the contractor forfeits any right to claim additional money or time.