19.3 Submittal Workflow, Review Responsibility & Action Stamps

Architect Registration Examination ARE 5.0

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: ARE 5.0 Structure, Delivery & Scoring

1.1 The Six Divisions: Items, Durations, Sections & Objectives 1.2 Eligibility, PSI Delivery, Fees, Scheduling & Rescheduling 1.3 Cut Scores, Score Reports, Provisional Feedback & Retakes

2 Chapter 2: Licensure Path, Item Types & Test-Day Strategy

2.1 Education Standard, AXP Hours, Settings & Reporting Rules 2.2 The NCARB Record, Score Validity Policy & Reciprocity 2.3 Item Types, Case Studies, Exam Tools, Breaks & Pacing

3 Chapter 3: Practice Management — Firm Resources, Conduct & the Work Environment

3.1 Assessing Practice Resources: Staffing, Development & Capital Investment 3.2 Regulating the Work Environment: FLSA, Antidiscrimination Law, OSHA & ADA Title III 3.3 Ethical Standards, the NCARB Rules of Conduct & the Standard of Care 3.4 Business Structures, Firm Ownership Rules & Practice-Wide Methodologies

4 Chapter 4: Practice Management — Firm Finances & Financial Health

4.1 Utilization, Overhead, Break-Even & Net Multiplier 4.2 Liquidity, Solvency & Reading Firm Financials Strategically 4.3 Accrual vs. Cash Accounting & the Architectural Balance Sheet 4.4 The Income Statement, Net Operating Revenue & Cash Flow Management

5 Chapter 5: Practice Management — Risk, Insurance & Business Development

5.1 Risk Management & the Firm’s Insurance Portfolio 5.2 Contractual Risk Allocation, Intellectual Property & Dispute Resolution 5.3 Client Requests, Compensation Methods, Project Delivery & Project Risk

6 Chapter 6: Project Management — Team, Resources & Consultants

6.1 Assembling the Project Team: Roles, Authority & Selection Criteria 6.2 Allocating & Managing Project Resources: Hours, Rates & Leveling 6.3 Consultant Selection, Qualifications-Based Selection & Scope Boundaries 6.4 AIA C401: Flow-Through, Consultant Standard of Care, Insurance & Payment

7 Chapter 7: Project Management — Work Planning, Scheduling & Budget Control

7.1 The Project Work Plan & Phase Fee Allocation 7.2 Work Breakdown Structures, Scheduling Methods & Dependency Logic 7.3 Critical Path Calculations, Float & Schedule Compression 7.4 Project Communication: Paths, Instruments, Meetings & the Record 7.5 Monitoring the Project Budget with Earned Value Management 7.6 Scope Creep, Additional Services & Written Authorization

8 Chapter 8: Project Management — Contracts, Approvals & Quality Control

8.1 AIA B101: Initial Information, Standard of Care & Basic Services 8.2 B101: Owner Duties, Cost of the Work, Copyright, Termination & Compensation 8.3 The Owner-Contractor Agreement & A201 Contractor Responsibilities 8.4 A201: Architect Administration, Changes, Claims & Separate Contractors 8.5 Regulatory Compliance, Authorities Having Jurisdiction & Project Approvals 8.6 Documenting a Project for the Specified Delivery Method 8.7 Quality Assurance, Quality Control, Constructability & the Record

9 Chapter 9: Programming & Analysis — Site & Environmental Conditions

9.1 Climate Classification, Solar Geometry & Passive Site Opportunities 9.2 Microclimate, Wind, Topography, Grading & Site Hydrology 9.3 Environmental Due Diligence: CERCLA Liability & Phase I / Phase II Assessments 9.4 Soil Mechanics, Geotechnical Investigation & Foundation Selection 9.5 Vehicular Circulation, Access Management, Parking & Emergency Access

10 Chapter 10: Programming & Analysis — Zoning, Codes & Site Infrastructure

10.1 Pedestrian Circulation, Site Utilities & Contextual Constraints 10.2 Zoning Authority, Euclidean and Form-Based Codes & Bulk Standards 10.3 Non-Conforming Uses, Variances, Easements & Parking Feasibility 10.4 IBC Occupancy Classification, Mixed Occupancy & Incidental Uses 10.5 IBC Construction Types, Fire-Resistance Ratings & Compartmentation

11 Chapter 11: Programming & Analysis — Building Programming & Feasibility

11.1 Programming Methodology, Net vs. Gross Area & Building Efficiency 11.2 Adjacency Matrices, Bubble Diagrams, Blocking & Stacking 11.3 Evaluating an Existing Building Against a Program 11.4 Reviewing Project Budget & Schedule Feasibility Against Scope 11.5 Identifying Building & Structural System Alternatives at Programming

12 Chapter 12: Project Planning & Design — Siting, Configuration, Codes & Life Safety

12.1 Building Siting, Neighborhood Context, Zoning Application & Configuration 12.2 IBC Allowable Area: Tabular Area, Frontage & Sprinkler Increases 12.3 Building Height, Story Limits, Mixed Occupancy & Unlimited Area Buildings 12.4 Means of Egress Components & Occupant Load Calculation 12.5 Exit Count, Remoteness, Egress Capacity, Travel Distance & Dead Ends 12.6 Accessible Routes, Slopes, Protruding Objects & Ramp Design 12.7 Door Clearances, Operating Hardware & Accessible Toilet Room Geometry

13 Chapter 13: Project Planning & Design — Structural & Mechanical Systems

13.1 Selecting Structural Systems: Steel, Concrete, Wood & Masonry 13.2 Lateral Force-Resisting Systems, Wind Loads & Seismic Design 13.3 Thermal Comfort, ASHRAE Standard 55 & Psychrometrics 13.4 HVAC System Typologies, Spatial Allocation & Central Plant Equipment 13.5 Potable Water Supply, Drainage, Waste & Vent Systems 13.6 Electrical Distribution, Emergency Power, Lighting & Daylighting 13.7 Fire Suppression, Standpipes, Conveying, Security & Communications

14 Chapter 14: Project Planning & Design — Envelope, Materials & Cost

14.1 Envelope Thermodynamics, Heat Transfer & Fenestration Performance 14.2 Thermal Bridging, Continuous Insulation & Thermal Mass 14.3 Passive Solar Heating, Natural Ventilation & Daylighting Architecture 14.4 Material Selection Criteria, Fire Performance & Vapor Permeance 14.5 Life Cycle Assessment, Embodied Carbon & Material Transparency 14.6 Galvanic Compatibility, Thermal Movement & Masonry Durability 14.7 Cost Estimating by Phase & Contingency Planning 14.8 Life-Cycle Cost Analysis, Present Value & Value Engineering

15 Chapter 15: Project Development & Documentation — Roofing, Waterproofing & Wall Assemblies

15.1 Low-Slope Roofing Systems, Membranes & Drainage Geometry 15.2 Flashing, Parapets, Copings & Roof Penetration Detailing 15.3 Steep-Slope Roofing & Below-Grade Waterproofing 15.4 Enclosure Control Layers & Rain Screen Cladding Systems 15.5 Vapor Retarders, Permeance Classes & Dew Point Control

16 Chapter 16: Project Development & Documentation — Connections, Coordination & Interiors

16.1 Structural Steel Connections & Base Plate Detailing 16.2 Concrete Reinforcing, Cover & Building Movement Joints 16.3 Sizing Structural, Mechanical, Electrical & Plumbing Components 16.4 Ceiling Plenum Coordination, Clash Detection & Level of Development 16.5 Vertical Chases, Shaft Walls, Through-Penetration Firestopping & Rated Joints 16.6 Interior Partition Framing, Head-of-Wall Details & Rated Gypsum Assemblies 16.7 Sound Isolation, STC, NRC & Reverberation Time 16.8 Door and Frame Construction & Fire Door Assemblies Under NFPA 80 16.9 Hardware Functions, Fire-Protection vs. Fire-Resistance Glazing

17 Chapter 17: Project Development & Documentation — Drawings, Specifications & Estimates

17.1 The National CAD Standard, Sheet Modules & Title Blocks 17.2 Drawing Cross-Referencing, Coordination & Revision Control 17.3 Documenting Site Features: Survey, Civil, Grading, Utilities & Landscape 17.4 The Project Manual & CSI MasterFormat Divisions 17.5 Section Numbering & the CSI Three-Part SectionFormat 17.6 Specification Methods & Document Precedence 17.7 Quantity Takeoff Estimating, General Conditions, Overhead & Alternates

18 Chapter 18: Construction & Evaluation — Procurement, Bidding & Preconstruction

18.1 Procurement Methods & AIA A701 Instructions to Bidders 18.2 Addenda Mechanics & Surety Bonds 18.3 The Preconstruction Conference & Administrative Protocols 18.4 Submittal Schedules, Long-Lead Items, Permits & Special Inspections 18.5 Bid Opening, Bidder Qualification & Discrepancy Rules 18.6 Alternates, Allowances, Unit Prices & Contract Award

19 Chapter 19: Construction & Evaluation — Observation & Contract Administration

19.1 The Architect’s Site Observation Role & the Means and Methods Firewall 19.2 Rejecting Non-Conforming Work, Special Inspections & Field Reports 19.3 Submittal Workflow, Review Responsibility & Action Stamps 19.4 Delegated Design, Design-Assist & Deferred Submittals 19.5 Requests for Information & Architect’s Supplemental Instructions 19.6 Change Orders, Construction Change Directives & Instrument Comparison

20 Chapter 20: Construction & Evaluation — Payment, Closeout & Evaluation

20.1 The Schedule of Values & the Application and Certificate for Payment 20.2 Stored Materials, Retainage, Certification Duties & Withholding 20.3 Substantial Completion & the Punch List Protocol 20.4 The Certificate of Substantial Completion & Its Legal Consequences 20.5 Final Completion, Final Payment & the Closeout Package 20.6 Warranty Administration, the Eleven-Month Walk-Through & Post-Occupancy Evaluation

19.3 Submittal Workflow, Review Responsibility & Action Stamps

Key Takeaways Explain This Topic AI

Shop drawings, product data, and samples are not contract documents, so approving a submittal does not change the contract requirements.

The contractor must review, approve, and stamp submittals before transmitting them, and the architect may return unstamped submittals without review.

The architect reviews for conformance with the design concept and the information given in the contract documents, not for dimensions, quantities, or means and methods.

Standard actions are approved, approved as noted, revise and resubmit, and rejected, and each carries different consequences for fabrication.

Under A201 Section 3.12.8 a deviation is effective only if the contractor gives specific written notice of it and the architect approves that specific deviation in writing.

Last updated: September 2026

Submittal Processing Workflow under AIA A201 Section 3.12

During construction administration, the processing and review of contractor submittals represents one of the architect's most time-intensive and legally sensitive duties. Submittals encompass several distinct categories of technical documentation:

Shop Drawings: Drawings, diagrams, schedules, and other data specially prepared for the work by the contractor, subcontractor, manufacturer, supplier, or distributor to illustrate some portion of the work (A201 Section 3.12.1). Examples include structural steel fabrication details, precast concrete panel layout drawings, and custom architectural millwork elevations.

Product Data: Illustrations, standard schedules, performance charts, instructions, brochures, diagrams, and other information furnished by the contractor to illustrate materials or equipment for some portion of the work (Section 3.12.2). Examples include mechanical air handler cut sheets, plumbing fixture schedules, and roofing membrane technical specifications.

Samples: Physical examples that illustrate materials, equipment, or workmanship and establish standards by which the work will be judged (Section 3.12.3). Examples include masonry brick mock-up panels, paint draw-downs, carpet swatches, and anodized aluminum finish coupons.

The Fundamental Legal Rule: Submittals Are NOT Contract Documents

A central principle of construction law codified in AIA A201 Section 3.12.4 states unequivocally:

"Shop Drawings, Product Data, Samples, and similar submittals are not Contract Documents. Their purpose is to demonstrate how the Contractor proposes to conform to the information given and the design concept expressed in the Contract Documents for those portions of the Work for which the Contract Documents require submittals."

Because submittals are not Contract Documents, an architect's stamp on a shop drawing cannot legally alter the Contract Sum, extend the Contract Time, or modify the contract drawings and specifications. Contract requirements can only be altered through formal contract modification instruments: Change Orders, Construction Change Directives, or Architect's Supplemental Instructions. ┌────────────────────────────────────────────────────────────────────────┐

  • │ SUBMITTAL PROCESSING CYCLE │
  • ├────────────────────────────────────────────────────────────────────────┤
  • │ 1. Subcontractor / Fabricator prepares Shop Drawings / Product Data. │
  • │ 2. General Contractor reviews, verifies field measurements, checks │
  • │ coordination with adjacent trades, and STAMPS approval. │
  • │ ► IF UNSTAMPED: Architect returns immediately WITHOUT ACTION. │
  • │ 3. Architect & Consultants review submittal ONLY for conformance with │
  • │ the design concept and Contract Documents. │
  • │ 4. Architect applies Action Stamp (Approved / Approved as Noted / │
  • │ Revise & Resubmit / Rejected) and returns to Contractor. │
  • │ 5. Fabricator initiates production only upon receiving appropriate stamp│
  • └────────────────────────────────────────────────────────────────────────┘
  • The Contractor's Review Stamp (A201 Section 3.12.5)

A critical gatekeeping requirement under AIA A201 Section 3.12.5 mandates that the contractor must perform an exhaustive internal coordination review before transmitting any submittal to the architect:

"The Contractor shall review for compliance with the Contract Documents, approve, and submit to the Architect, Shop Drawings, Product Data, Samples, and similar submittals required by the Contract Documents... By submitting Shop Drawings, Product Data, Samples, and similar submittals, the Contractor represents to the Owner and Architect that the Contractor has (1) reviewed and approved them, (2) determined and verified materials, field measurements, and field construction criteria related thereto, or will do so, and (3) checked and coordinated the information contained within such submittals with the requirements of the Work and of the Contract Documents."

The Rule of the Unstamped Submittal: If a general contractor forwards a subcontractor's shop drawings directly to the architect without the contractor's review and approval stamp, the architect must return the submittal immediately without action . The architect must not review it, log it, or pass it to consulting engineers. If the architect reviews an unstamped submittal, the architect effectively performs the general contractor's coordination duty, assuming legal liability for dimensional interferences, field layout errors, and trade clash detection.

Architect's Review Responsibility & Action Stamps

Under AIA A201 Section 4.2.7, the architect's contractual duty regarding submittal review is carefully delimited:

"The Architect will review and approve, or take other appropriate action upon, the Contractor's submittals such as Shop Drawings, Product Data, and Samples, but only for the limited purpose of checking for conformance with information given and the design concept expressed in the Contract Documents."

Section 4.2.7 specifically protects the architect against operational overreach:

Review of submittals is not conducted for the purpose of determining the accuracy and completeness of other details such as dimensions and quantities .

Review does not constitute approval of safety precautions or of any construction means, methods, techniques, sequences, or procedures .

Approval of a specific item does not indicate approval of an assembly of which the item is a component.

Standard Submittal Action Stamp Categories

Architectural firms utilize standardized submittal action stamps. Understanding the exact contractual meaning of each action is essential for practice and the ARE:

Stamp Action Contractual Meaning Next Steps for Contractor

Approved / No Exceptions Taken Submittal conforms to the design concept and Contract Documents. Contractor is authorized to proceed with fabrication, ordering, and installation.

Approved as Noted / Make Corrections Noted Submittal conforms to design concept subject to minor handwritten notations or corrections marked by architect. Contractor may proceed with fabrication and installation incorporating marked changes; no resubmission required.

Revise and Resubmit Submittal contains significant errors, omissions, or non-conforming details that must be corrected. Contractor cannot fabricate; submittal must be corrected and resubmitted for full review.

Rejected Submittal is completely non-compliant with design concept, specifications, or basis of design product. Contractor must select a compliant product/system and submit an entirely new submittal package.

Risk Management Warning: Architects must never use words such as "Accepted" or "Checked" without qualification, nor should they stamp submittals with notes such as "Approved for Dimensions." Verifying field dimensions is solely the contractor's responsibility under Section 3.12.5.

The Strict Rule on Deviations (A201 Section 3.12.8)

Contractors frequently propose deviations from the contract drawings or specifications during the submittal process—sometimes to resolve field conflicts, and other times to substitute cheaper materials. AIA A201 Section 3.12.8 establishes a rigid two-prong standard governing deviations:

"The Contractor shall not be relieved of responsibility for deviations from the requirements of the Contract Documents by the Architect's approval of Shop Drawings, Product Data, Samples, or similar submittals unless the Contractor has specifically notified the Architect of such deviation in the submittal and (1) the Architect has given written approval to the specific deviation as a minor change in the Work, or (2) a Change Order or Construction Change Directive has been issued authorizing the deviation."

If a contractor changes a specified high-performance waterproofing membrane to an inferior product by quietly including the cut sheet in a 400-page submittal packet, and the architect inadvertently stamps the packet "Approved," the contractor is NOT relieved of the contractual duty to install the specified membrane . Because the contractor failed to provide specific written notification calling out the deviation, the contractor remains legally liable for removing the non-conforming material and installing the specified product at their own expense.