Study guide
20.1 The Schedule of Values & the Application and Certificate for Payment
Architect Registration Examination ARE 5.0
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: ARE 5.0 Structure, Delivery & Scoring
1.1 The Six Divisions: Items, Durations, Sections & Objectives 1.2 Eligibility, PSI Delivery, Fees, Scheduling & Rescheduling 1.3 Cut Scores, Score Reports, Provisional Feedback & Retakes
2 Chapter 2: Licensure Path, Item Types & Test-Day Strategy
2.1 Education Standard, AXP Hours, Settings & Reporting Rules 2.2 The NCARB Record, Score Validity Policy & Reciprocity 2.3 Item Types, Case Studies, Exam Tools, Breaks & Pacing
3 Chapter 3: Practice Management — Firm Resources, Conduct & the Work Environment
3.1 Assessing Practice Resources: Staffing, Development & Capital Investment 3.2 Regulating the Work Environment: FLSA, Antidiscrimination Law, OSHA & ADA Title III 3.3 Ethical Standards, the NCARB Rules of Conduct & the Standard of Care 3.4 Business Structures, Firm Ownership Rules & Practice-Wide Methodologies
4 Chapter 4: Practice Management — Firm Finances & Financial Health
4.1 Utilization, Overhead, Break-Even & Net Multiplier 4.2 Liquidity, Solvency & Reading Firm Financials Strategically 4.3 Accrual vs. Cash Accounting & the Architectural Balance Sheet 4.4 The Income Statement, Net Operating Revenue & Cash Flow Management
5 Chapter 5: Practice Management — Risk, Insurance & Business Development
5.1 Risk Management & the Firm’s Insurance Portfolio 5.2 Contractual Risk Allocation, Intellectual Property & Dispute Resolution 5.3 Client Requests, Compensation Methods, Project Delivery & Project Risk
6 Chapter 6: Project Management — Team, Resources & Consultants
6.1 Assembling the Project Team: Roles, Authority & Selection Criteria 6.2 Allocating & Managing Project Resources: Hours, Rates & Leveling 6.3 Consultant Selection, Qualifications-Based Selection & Scope Boundaries 6.4 AIA C401: Flow-Through, Consultant Standard of Care, Insurance & Payment
7 Chapter 7: Project Management — Work Planning, Scheduling & Budget Control
7.1 The Project Work Plan & Phase Fee Allocation 7.2 Work Breakdown Structures, Scheduling Methods & Dependency Logic 7.3 Critical Path Calculations, Float & Schedule Compression 7.4 Project Communication: Paths, Instruments, Meetings & the Record 7.5 Monitoring the Project Budget with Earned Value Management 7.6 Scope Creep, Additional Services & Written Authorization
8 Chapter 8: Project Management — Contracts, Approvals & Quality Control
8.1 AIA B101: Initial Information, Standard of Care & Basic Services 8.2 B101: Owner Duties, Cost of the Work, Copyright, Termination & Compensation 8.3 The Owner-Contractor Agreement & A201 Contractor Responsibilities 8.4 A201: Architect Administration, Changes, Claims & Separate Contractors 8.5 Regulatory Compliance, Authorities Having Jurisdiction & Project Approvals 8.6 Documenting a Project for the Specified Delivery Method 8.7 Quality Assurance, Quality Control, Constructability & the Record
9 Chapter 9: Programming & Analysis — Site & Environmental Conditions
9.1 Climate Classification, Solar Geometry & Passive Site Opportunities 9.2 Microclimate, Wind, Topography, Grading & Site Hydrology 9.3 Environmental Due Diligence: CERCLA Liability & Phase I / Phase II Assessments 9.4 Soil Mechanics, Geotechnical Investigation & Foundation Selection 9.5 Vehicular Circulation, Access Management, Parking & Emergency Access
10 Chapter 10: Programming & Analysis — Zoning, Codes & Site Infrastructure
10.1 Pedestrian Circulation, Site Utilities & Contextual Constraints 10.2 Zoning Authority, Euclidean and Form-Based Codes & Bulk Standards 10.3 Non-Conforming Uses, Variances, Easements & Parking Feasibility 10.4 IBC Occupancy Classification, Mixed Occupancy & Incidental Uses 10.5 IBC Construction Types, Fire-Resistance Ratings & Compartmentation
11 Chapter 11: Programming & Analysis — Building Programming & Feasibility
11.1 Programming Methodology, Net vs. Gross Area & Building Efficiency 11.2 Adjacency Matrices, Bubble Diagrams, Blocking & Stacking 11.3 Evaluating an Existing Building Against a Program 11.4 Reviewing Project Budget & Schedule Feasibility Against Scope 11.5 Identifying Building & Structural System Alternatives at Programming
12 Chapter 12: Project Planning & Design — Siting, Configuration, Codes & Life Safety
12.1 Building Siting, Neighborhood Context, Zoning Application & Configuration 12.2 IBC Allowable Area: Tabular Area, Frontage & Sprinkler Increases 12.3 Building Height, Story Limits, Mixed Occupancy & Unlimited Area Buildings 12.4 Means of Egress Components & Occupant Load Calculation 12.5 Exit Count, Remoteness, Egress Capacity, Travel Distance & Dead Ends 12.6 Accessible Routes, Slopes, Protruding Objects & Ramp Design 12.7 Door Clearances, Operating Hardware & Accessible Toilet Room Geometry
13 Chapter 13: Project Planning & Design — Structural & Mechanical Systems
13.1 Selecting Structural Systems: Steel, Concrete, Wood & Masonry 13.2 Lateral Force-Resisting Systems, Wind Loads & Seismic Design 13.3 Thermal Comfort, ASHRAE Standard 55 & Psychrometrics 13.4 HVAC System Typologies, Spatial Allocation & Central Plant Equipment 13.5 Potable Water Supply, Drainage, Waste & Vent Systems 13.6 Electrical Distribution, Emergency Power, Lighting & Daylighting 13.7 Fire Suppression, Standpipes, Conveying, Security & Communications
14 Chapter 14: Project Planning & Design — Envelope, Materials & Cost
14.1 Envelope Thermodynamics, Heat Transfer & Fenestration Performance 14.2 Thermal Bridging, Continuous Insulation & Thermal Mass 14.3 Passive Solar Heating, Natural Ventilation & Daylighting Architecture 14.4 Material Selection Criteria, Fire Performance & Vapor Permeance 14.5 Life Cycle Assessment, Embodied Carbon & Material Transparency 14.6 Galvanic Compatibility, Thermal Movement & Masonry Durability 14.7 Cost Estimating by Phase & Contingency Planning 14.8 Life-Cycle Cost Analysis, Present Value & Value Engineering
15 Chapter 15: Project Development & Documentation — Roofing, Waterproofing & Wall Assemblies
15.1 Low-Slope Roofing Systems, Membranes & Drainage Geometry 15.2 Flashing, Parapets, Copings & Roof Penetration Detailing 15.3 Steep-Slope Roofing & Below-Grade Waterproofing 15.4 Enclosure Control Layers & Rain Screen Cladding Systems 15.5 Vapor Retarders, Permeance Classes & Dew Point Control
16 Chapter 16: Project Development & Documentation — Connections, Coordination & Interiors
16.1 Structural Steel Connections & Base Plate Detailing 16.2 Concrete Reinforcing, Cover & Building Movement Joints 16.3 Sizing Structural, Mechanical, Electrical & Plumbing Components 16.4 Ceiling Plenum Coordination, Clash Detection & Level of Development 16.5 Vertical Chases, Shaft Walls, Through-Penetration Firestopping & Rated Joints 16.6 Interior Partition Framing, Head-of-Wall Details & Rated Gypsum Assemblies 16.7 Sound Isolation, STC, NRC & Reverberation Time 16.8 Door and Frame Construction & Fire Door Assemblies Under NFPA 80 16.9 Hardware Functions, Fire-Protection vs. Fire-Resistance Glazing
17 Chapter 17: Project Development & Documentation — Drawings, Specifications & Estimates
17.1 The National CAD Standard, Sheet Modules & Title Blocks 17.2 Drawing Cross-Referencing, Coordination & Revision Control 17.3 Documenting Site Features: Survey, Civil, Grading, Utilities & Landscape 17.4 The Project Manual & CSI MasterFormat Divisions 17.5 Section Numbering & the CSI Three-Part SectionFormat 17.6 Specification Methods & Document Precedence 17.7 Quantity Takeoff Estimating, General Conditions, Overhead & Alternates
18 Chapter 18: Construction & Evaluation — Procurement, Bidding & Preconstruction
18.1 Procurement Methods & AIA A701 Instructions to Bidders 18.2 Addenda Mechanics & Surety Bonds 18.3 The Preconstruction Conference & Administrative Protocols 18.4 Submittal Schedules, Long-Lead Items, Permits & Special Inspections 18.5 Bid Opening, Bidder Qualification & Discrepancy Rules 18.6 Alternates, Allowances, Unit Prices & Contract Award
19 Chapter 19: Construction & Evaluation — Observation & Contract Administration
19.1 The Architect’s Site Observation Role & the Means and Methods Firewall 19.2 Rejecting Non-Conforming Work, Special Inspections & Field Reports 19.3 Submittal Workflow, Review Responsibility & Action Stamps 19.4 Delegated Design, Design-Assist & Deferred Submittals 19.5 Requests for Information & Architect’s Supplemental Instructions 19.6 Change Orders, Construction Change Directives & Instrument Comparison
20 Chapter 20: Construction & Evaluation — Payment, Closeout & Evaluation
20.1 The Schedule of Values & the Application and Certificate for Payment 20.2 Stored Materials, Retainage, Certification Duties & Withholding 20.3 Substantial Completion & the Punch List Protocol 20.4 The Certificate of Substantial Completion & Its Legal Consequences 20.5 Final Completion, Final Payment & the Closeout Package 20.6 Warranty Administration, the Eleven-Month Walk-Through & Post-Occupancy Evaluation
20.1 The Schedule of Values & the Application and Certificate for Payment
Key Takeaways Explain This Topic AI
The schedule of values on AIA G703 allocates the entire contract sum across the work and becomes the basis for evaluating every payment application.
Front-loading assigns disproportionate value to early work so the contractor is paid ahead of value in place, leaving the owner exposed if the contractor defaults.
AIA G702 combines the contractor’s application with the architect’s certificate on a single form, but they are legally distinct acts.
The G702 computes the contract sum to date, total completed and stored to date, retainage, total earned less retainage, previous payments, and the current payment due.
A change order that is approved but not yet incorporated into the schedule of values will distort the percentage complete on the next application.
Last updated: September 2026
The Schedule of Values (AIA Document G703)
During the Construction Phase, the disbursement of capital from the owner to the contractor is governed by progress payments. To ensure that disbursements accurately track the physical reality of work in place, AIA Document A201™–2017 (General Conditions of the Contract for Construction) establishes a rigorous administrative framework anchored by the Schedule of Values (SOV) .
Under AIA A201 Section 9.2, the general contractor is contractually mandated to submit a Schedule of Values to the architect prior to submitting the very first application for payment:
"Where the Contract is based on a stipulated sum or Guaranteed Maximum Price, the Contractor shall submit a schedule of values to the Architect before the first Application for Payment, allocating the entire Contract Sum to the various portions of the Work. The schedule of values shall be prepared in the form, and supported by the data to substantiate its accuracy, required by the Architect."
Structure and Role of AIA Document G703
The standard industry instrument for the Schedule of Values is AIA Document G703™ (Continuation Sheet) , which serves as the itemized companion to AIA Document G702™ (Application and Certificate for Payment). The G703 organizes the total contract value into discrete line items arranged by the Construction Specifications Institute (CSI) MasterFormat® divisions (e.g., Division 03 Concrete, Division 05 Metals, Division 09 Finishes, Division 26 Electrical).
Key columns on AIA Document G703 include:
- Column A: Item Number
- Column B: Description of Work
- Column C: Scheduled Value (the allocated contract amount for that line item)
- Column D: Work Completed from Previous Applications (not including current period)
- Column E: Work Completed This Period
- Column F: Materials Presently Stored (not in Work Completed)
- Column G: Total Completed and Stored to Date (Columns D + E + F)
- Column H: % Complete (Column G ÷ Column C)
- Column I: Balance to Finish (Column C − Column G)
- Column J: Retainage (if variable rate applies)
Once reviewed and approved by the architect, the Schedule of Values serves as the contractual mathematical baseline for evaluating all subsequent monthly payment applications. The architect evaluates the contractor's claimed percentages of completion against the physical work observed during site visits.
The Risk of Front-Loading (Unbalanced Bidding)
A primary responsibility of the architect during the initial review of the SOV is detecting and preventing front-loading (also termed an unbalanced schedule of values). Front-loading occurs when a contractor artificially inflates the scheduled values of early construction activities (such as mobilization, site clearing, mass excavation, subgrade utilities, and foundations) while depressing the values of trades executed near the end of the project (such as drywall, architectural woodwork, painting, flooring, and mechanical testing, adjusting, and balancing). ┌────────────────────────────────────────────────────────────────────────┐
- │ THE DANGER OF FRONT-LOADING │
- ├────────────────────────────────────────────────────────────────────────┤
- │ NORMAL ALLOCATION: │
- │ • Mobilization & Earthwork: Real Cost = $200,000 ──► SOV = $200,000 │
- │ • Interior Finishes: Real Cost = $800,000 ──► SOV = $800,000 │
- │ │
- │ FRONT-LOADED ALLOCATION: │
- │ • Mobilization & Earthwork: Real Cost = $200,000 ──► SOV = $500,000 ◄──┤ (Overpaid by $300k)
- │ • Interior Finishes: Real Cost = $800,000 ──► SOV = $500,000 ◄──┤ (Underfunded by $300k)
- │ │
- │ RISK EXPOSURE: If the contractor defaults or abandons the project at │
- │ month 8, the remaining unpaid contract balance ($500,000) is wholly │
- │ insufficient to pay a completion contractor to finish the $800,000 in │
- │ remaining finish trades! │
- └────────────────────────────────────────────────────────────────────────┘
Contractors front-load to generate an interest-free working capital loan from the owner to fund other jobs or corporate overhead. However, if the contractor experiences financial distress, default, or bankruptcy mid-project, the owner is left with an underfunded contract where the remaining balance is grossly insufficient to hire a replacement contractor to complete the remaining work. Under Section 9.2, the architect has the legal authority and duty to demand line-item substantiation—such as executed subcontractor agreements, purchase orders, and supplier bids—and must reject any unbalanced SOV before certifying the first payment application.
AIA Document G702: Application and Certificate for Payment
AIA Document G702™ is the summary instrument executed monthly by the contractor and the architect. It presents a high-level, nine-line financial accounting of the project from contract inception through the current billing date. ┌────────────────────────────────────────────────────────────────────────┐
- │ AIA DOCUMENT G702: 9-LINE SUMMARY │
- ├──────┬──────────────────────────────────────────┬──────────────────────┤
- │ LINE │ CONTRACT ACCOUNTING ITEM │ MATHEMATICAL BASIS │
- ├──────┼──────────────────────────────────────────┼──────────────────────┤
- │ 1 │ Original Contract Sum │ Baseline Agreement │
- │ 2 │ Net Change by Change Orders │ Executed COs Only │
- │ 3 │ Contract Sum to Date │ Line 1 ± Line 2 │
- │ 4 │ Total Completed & Stored to Date │ G703 Column G Total │
- │ 5 │ Retainage (Total Withheld) │ Line 5a + Line 5b │
- │ 6 │ Total Earned Less Retainage │ Line 4 − Line 5 │
- │ 7 │ Less Previous Certificates for Payment │ Line 6 of Prior App │
- │ 8 │ Current Payment Due │ Line 6 − Line 7 │
- │ 9 │ Balance to Finish, Including Retainage │ Line 3 − Line 6 │
- └──────┴──────────────────────────────────────────┴──────────────────────┘
- Detailed Analysis of the 9 Lines
Line 1: Original Contract Sum: The base contract amount established in the Owner-Contractor Agreement (e.g., AIA A101™).
Line 2: Net Change by Change Orders: The cumulative algebraic sum of all fully executed Change Orders (AIA Document G701™). Critical Rule: Only fully executed Change Orders signed by owner, contractor, and architect may be included on Line 2. Pending Change Orders, unpriced Construction Change Directives (CCDs), and unadjudicated claims cannot be incorporated into the Contract Sum.
Line 3: Contract Sum to Date: The adjusted total contract value (Line 1 plus or minus Line 2).
Line 4: Total Completed and Stored to Date: The total dollar value of all permanent work installed to date plus approved materials stored on or off site. This figure corresponds directly to the bottom-line total of Column G on AIA Document G703.
Line 5: Retainage: The cumulative amount of retainage withheld. Line 5 is typically divided into Line 5a (retainage on completed work) and Line 5b (retainage on stored materials).
Line 6: Total Earned Less Retainage: The total value earned by the contractor to date minus retainage (Line 4 minus Line 5).
Line 7: Less Previous Certificates for Payment: The total amount previously certified by the architect for payment (Line 6 from the immediately preceding certified G702).
Line 8: Current Payment Due: The net dollar amount payable to the contractor for the current billing cycle (Line 6 minus Line 7).
Line 9: Balance to Finish, Including Retainage: The remaining funds obligated by the owner under the contract (Line 3 minus Line 6). This number represents the owner's remaining financial liability to achieve Final Completion.