20.6 Warranty Administration, the Eleven-Month Walk-Through & Post-Occupancy Evaluation

Architect Registration Examination ARE 5.0

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: ARE 5.0 Structure, Delivery & Scoring

1.1 The Six Divisions: Items, Durations, Sections & Objectives 1.2 Eligibility, PSI Delivery, Fees, Scheduling & Rescheduling 1.3 Cut Scores, Score Reports, Provisional Feedback & Retakes

2 Chapter 2: Licensure Path, Item Types & Test-Day Strategy

2.1 Education Standard, AXP Hours, Settings & Reporting Rules 2.2 The NCARB Record, Score Validity Policy & Reciprocity 2.3 Item Types, Case Studies, Exam Tools, Breaks & Pacing

3 Chapter 3: Practice Management — Firm Resources, Conduct & the Work Environment

3.1 Assessing Practice Resources: Staffing, Development & Capital Investment 3.2 Regulating the Work Environment: FLSA, Antidiscrimination Law, OSHA & ADA Title III 3.3 Ethical Standards, the NCARB Rules of Conduct & the Standard of Care 3.4 Business Structures, Firm Ownership Rules & Practice-Wide Methodologies

4 Chapter 4: Practice Management — Firm Finances & Financial Health

4.1 Utilization, Overhead, Break-Even & Net Multiplier 4.2 Liquidity, Solvency & Reading Firm Financials Strategically 4.3 Accrual vs. Cash Accounting & the Architectural Balance Sheet 4.4 The Income Statement, Net Operating Revenue & Cash Flow Management

5 Chapter 5: Practice Management — Risk, Insurance & Business Development

5.1 Risk Management & the Firm’s Insurance Portfolio 5.2 Contractual Risk Allocation, Intellectual Property & Dispute Resolution 5.3 Client Requests, Compensation Methods, Project Delivery & Project Risk

6 Chapter 6: Project Management — Team, Resources & Consultants

6.1 Assembling the Project Team: Roles, Authority & Selection Criteria 6.2 Allocating & Managing Project Resources: Hours, Rates & Leveling 6.3 Consultant Selection, Qualifications-Based Selection & Scope Boundaries 6.4 AIA C401: Flow-Through, Consultant Standard of Care, Insurance & Payment

7 Chapter 7: Project Management — Work Planning, Scheduling & Budget Control

7.1 The Project Work Plan & Phase Fee Allocation 7.2 Work Breakdown Structures, Scheduling Methods & Dependency Logic 7.3 Critical Path Calculations, Float & Schedule Compression 7.4 Project Communication: Paths, Instruments, Meetings & the Record 7.5 Monitoring the Project Budget with Earned Value Management 7.6 Scope Creep, Additional Services & Written Authorization

8 Chapter 8: Project Management — Contracts, Approvals & Quality Control

8.1 AIA B101: Initial Information, Standard of Care & Basic Services 8.2 B101: Owner Duties, Cost of the Work, Copyright, Termination & Compensation 8.3 The Owner-Contractor Agreement & A201 Contractor Responsibilities 8.4 A201: Architect Administration, Changes, Claims & Separate Contractors 8.5 Regulatory Compliance, Authorities Having Jurisdiction & Project Approvals 8.6 Documenting a Project for the Specified Delivery Method 8.7 Quality Assurance, Quality Control, Constructability & the Record

9 Chapter 9: Programming & Analysis — Site & Environmental Conditions

9.1 Climate Classification, Solar Geometry & Passive Site Opportunities 9.2 Microclimate, Wind, Topography, Grading & Site Hydrology 9.3 Environmental Due Diligence: CERCLA Liability & Phase I / Phase II Assessments 9.4 Soil Mechanics, Geotechnical Investigation & Foundation Selection 9.5 Vehicular Circulation, Access Management, Parking & Emergency Access

10 Chapter 10: Programming & Analysis — Zoning, Codes & Site Infrastructure

10.1 Pedestrian Circulation, Site Utilities & Contextual Constraints 10.2 Zoning Authority, Euclidean and Form-Based Codes & Bulk Standards 10.3 Non-Conforming Uses, Variances, Easements & Parking Feasibility 10.4 IBC Occupancy Classification, Mixed Occupancy & Incidental Uses 10.5 IBC Construction Types, Fire-Resistance Ratings & Compartmentation

11 Chapter 11: Programming & Analysis — Building Programming & Feasibility

11.1 Programming Methodology, Net vs. Gross Area & Building Efficiency 11.2 Adjacency Matrices, Bubble Diagrams, Blocking & Stacking 11.3 Evaluating an Existing Building Against a Program 11.4 Reviewing Project Budget & Schedule Feasibility Against Scope 11.5 Identifying Building & Structural System Alternatives at Programming

12 Chapter 12: Project Planning & Design — Siting, Configuration, Codes & Life Safety

12.1 Building Siting, Neighborhood Context, Zoning Application & Configuration 12.2 IBC Allowable Area: Tabular Area, Frontage & Sprinkler Increases 12.3 Building Height, Story Limits, Mixed Occupancy & Unlimited Area Buildings 12.4 Means of Egress Components & Occupant Load Calculation 12.5 Exit Count, Remoteness, Egress Capacity, Travel Distance & Dead Ends 12.6 Accessible Routes, Slopes, Protruding Objects & Ramp Design 12.7 Door Clearances, Operating Hardware & Accessible Toilet Room Geometry

13 Chapter 13: Project Planning & Design — Structural & Mechanical Systems

13.1 Selecting Structural Systems: Steel, Concrete, Wood & Masonry 13.2 Lateral Force-Resisting Systems, Wind Loads & Seismic Design 13.3 Thermal Comfort, ASHRAE Standard 55 & Psychrometrics 13.4 HVAC System Typologies, Spatial Allocation & Central Plant Equipment 13.5 Potable Water Supply, Drainage, Waste & Vent Systems 13.6 Electrical Distribution, Emergency Power, Lighting & Daylighting 13.7 Fire Suppression, Standpipes, Conveying, Security & Communications

14 Chapter 14: Project Planning & Design — Envelope, Materials & Cost

14.1 Envelope Thermodynamics, Heat Transfer & Fenestration Performance 14.2 Thermal Bridging, Continuous Insulation & Thermal Mass 14.3 Passive Solar Heating, Natural Ventilation & Daylighting Architecture 14.4 Material Selection Criteria, Fire Performance & Vapor Permeance 14.5 Life Cycle Assessment, Embodied Carbon & Material Transparency 14.6 Galvanic Compatibility, Thermal Movement & Masonry Durability 14.7 Cost Estimating by Phase & Contingency Planning 14.8 Life-Cycle Cost Analysis, Present Value & Value Engineering

15 Chapter 15: Project Development & Documentation — Roofing, Waterproofing & Wall Assemblies

15.1 Low-Slope Roofing Systems, Membranes & Drainage Geometry 15.2 Flashing, Parapets, Copings & Roof Penetration Detailing 15.3 Steep-Slope Roofing & Below-Grade Waterproofing 15.4 Enclosure Control Layers & Rain Screen Cladding Systems 15.5 Vapor Retarders, Permeance Classes & Dew Point Control

16 Chapter 16: Project Development & Documentation — Connections, Coordination & Interiors

16.1 Structural Steel Connections & Base Plate Detailing 16.2 Concrete Reinforcing, Cover & Building Movement Joints 16.3 Sizing Structural, Mechanical, Electrical & Plumbing Components 16.4 Ceiling Plenum Coordination, Clash Detection & Level of Development 16.5 Vertical Chases, Shaft Walls, Through-Penetration Firestopping & Rated Joints 16.6 Interior Partition Framing, Head-of-Wall Details & Rated Gypsum Assemblies 16.7 Sound Isolation, STC, NRC & Reverberation Time 16.8 Door and Frame Construction & Fire Door Assemblies Under NFPA 80 16.9 Hardware Functions, Fire-Protection vs. Fire-Resistance Glazing

17 Chapter 17: Project Development & Documentation — Drawings, Specifications & Estimates

17.1 The National CAD Standard, Sheet Modules & Title Blocks 17.2 Drawing Cross-Referencing, Coordination & Revision Control 17.3 Documenting Site Features: Survey, Civil, Grading, Utilities & Landscape 17.4 The Project Manual & CSI MasterFormat Divisions 17.5 Section Numbering & the CSI Three-Part SectionFormat 17.6 Specification Methods & Document Precedence 17.7 Quantity Takeoff Estimating, General Conditions, Overhead & Alternates

18 Chapter 18: Construction & Evaluation — Procurement, Bidding & Preconstruction

18.1 Procurement Methods & AIA A701 Instructions to Bidders 18.2 Addenda Mechanics & Surety Bonds 18.3 The Preconstruction Conference & Administrative Protocols 18.4 Submittal Schedules, Long-Lead Items, Permits & Special Inspections 18.5 Bid Opening, Bidder Qualification & Discrepancy Rules 18.6 Alternates, Allowances, Unit Prices & Contract Award

19 Chapter 19: Construction & Evaluation — Observation & Contract Administration

19.1 The Architect’s Site Observation Role & the Means and Methods Firewall 19.2 Rejecting Non-Conforming Work, Special Inspections & Field Reports 19.3 Submittal Workflow, Review Responsibility & Action Stamps 19.4 Delegated Design, Design-Assist & Deferred Submittals 19.5 Requests for Information & Architect’s Supplemental Instructions 19.6 Change Orders, Construction Change Directives & Instrument Comparison

20 Chapter 20: Construction & Evaluation — Payment, Closeout & Evaluation

20.1 The Schedule of Values & the Application and Certificate for Payment 20.2 Stored Materials, Retainage, Certification Duties & Withholding 20.3 Substantial Completion & the Punch List Protocol 20.4 The Certificate of Substantial Completion & Its Legal Consequences 20.5 Final Completion, Final Payment & the Closeout Package 20.6 Warranty Administration, the Eleven-Month Walk-Through & Post-Occupancy Evaluation

20.6 Warranty Administration, the Eleven-Month Walk-Through & Post-Occupancy Evaluation

Key Takeaways Explain This Topic AI

The eleven-month walk-through identifies defects while the contractor is still obligated to return and correct them under the one-year correction period.

The one-year correction period is a contractual remedy, and its expiration does not extinguish the owner’s warranty rights or right to sue for defective work.

Post-occupancy evaluation measures how the completed building actually performs against the goals set during programming.

POE methods include occupant surveys, walkthroughs, measured performance data, energy benchmarking, and comparison against the original program.

Under AIA B101 post-occupancy evaluation is an additional service, so it must be authorized and compensated separately from basic services.

Last updated: September 2026

Warranty Administration & The Eleven-Month Walk-Through

Architects must carefully distinguish between two legal warranty concepts defined in AIA Document A201: ┌────────────────────────────────────────────────────────────────────────┐

  • │ WARRANTY vs. CORRECTION OF WORK │
  • ├──────────────────────────────────┬─────────────────────────────────────┤
  • │ GENERAL WARRANTY (A201 § 3.5) │ ONE-YEAR CORRECTION (A201 § 12.2.2) │
  • ├──────────────────────────────────┼─────────────────────────────────────┤
  • │ • Work is of good quality │ • Contractor must promptly correct │
  • │ • Free from defects not inherent │ non-conforming work upon notice │
  • │ • Conforms to Contract Documents │ • Runs for 1 year from Substantial │
  • │ • Governed by statutory breach │ Completion │
  • │ of contract limits (4-10 years)│ • Specific, expedited remedy │
  • └──────────────────────────────────┴─────────────────────────────────────┘
  • The Eleven-Month Warranty Walk-Through

Under AIA Document B101™–2017 Section 12.2.2 (and Section 4.2.8), the architect's Basic Services include a vital closeout duty:

"The Architect shall, prior to the expiration of one year from the date of Substantial Completion, without additional compensation, conduct a meeting with the Owner to review the facility operations and performance."

In standard practice, this meeting is conducted as the Eleven-Month Walk-Through . Approximately 11 months after the Date of Substantial Completion, the architect inspects the facility with the owner's facility manager to examine how materials and building systems have performed over a complete annual cycle of heating and cooling seasons. The architect identifies latent defects—such as hairline stucco cracking, sticking fire doors, failing roof flashing seals, or unbalanced HVAC air distribution—and documents them in a formal warranty punch list. This gives the owner time to serve formal written notice on the general contractor before the one-year correction period permanently expires under Section 12.2.2.

Post-Occupancy Evaluation (POE)

A Post-Occupancy Evaluation (POE) is a rigorous, structured assessment of a completed building's operational performance, energy efficiency, and occupant comfort, conducted after the facility has been occupied for a meaningful duration (typically 6 to 12 months post-move-in).

Core Methodologies of POE

Comprehensive POEs integrate three distinct research methodologies:

Qualitative & Behavioral Assessment:

Occupant Satisfaction Surveys: Gathering structured user feedback regarding thermal comfort, visual glare, acoustic privacy, and space utilization.

Interviews and Focus Groups: In-depth qualitative discussions with administrative leaders, custodial staff, and facility operators.

Behavioral Mapping: Observing actual spatial traffic flows, informal gathering patterns, and unauthorized space adaptations.

Quantitative & Environmental Testing (IEQ):

Thermal Comfort Verification: Continuous logging of dry-bulb temperature, mean radiant temperature, relative humidity, and air speed to assess compliance with ASHRAE Standard 55.

Indoor Air Quality (IAQ): Measuring carbon dioxide ( C O 2 CO_2 C O 2 ​ ) concentrations (ppm), total volatile organic compounds (TVOCs), particulate matter ( P M 2.5 PM_{2.5} P M 2.5 ​ and P M 10 PM_{10} P M 10 ​ ), and ventilation rates.

Acoustics: Field measuring sound transmission class (STC), Noise Criteria (NC) curves, and reverberation time ( R T 60 RT_{60} R T 60 ​ ).

Lighting & Daylighting: Measuring horizontal work-plane illuminance (lux/foot-candles), daylight glare probability (DGP), and lighting power density ( W / f t 2 W/ft^2 W / f t 2 ).

Calibrated Energy Benchmarking:

Comparing modeled design energy consumption against actual monthly utility billing data.

Calculating actual Energy Use Intensity (EUI) in k B T U / f t 2 / y e a r kBTU/ft^2/year k BT U / f t 2 / ye a r and contrasting it with the original energy model and Regional Portfolio Manager benchmarks to identify operational drift or equipment scheduling errors.

Contractual Classification under AIA Document B101

A heavily tested contractual point on the ARE 5.0 is the legal status of a POE:

POE is NOT a Basic Service: An architect is not contractually obligated to conduct a Post-Occupancy Evaluation as part of standard design and construction administration fees.

AIA B101 Section 4.1.18: Under AIA Document B101–2017, Post-Occupancy Evaluation is explicitly classified as a Supplemental Service (or Additional Service).

If an owner desires a formal POE with occupant surveys, environmental datalogging, and calibrated energy modeling, the service must be identified in the initial agreement or authorized via a formal contract amendment, with the architect receiving additional professional compensation .

Correction Period Versus Warranty

Candidates routinely merge two things that the contract keeps separate.

  • One-year correction period Warranty
  • Source AIA A201 Section 12.2.2 A201 Section 3.5, plus manufacturer and specified special warranties

Duration One year from substantial completion Whatever the contract or manufacturer states — often 5, 10, or 20 years

What it is A contractual period during which the contractor must return and correct non-conforming work A promise that the work conforms to requirements

What it is not A limit on the owner's rights Expired when the correction period ends

The essential point: the expiration of the one-year correction period does not extinguish the owner's warranty rights or its right to sue for defective work. The correction period is an additional, efficient remedy — the owner can demand that the contractor fix it rather than suing for the cost of repair. After that year, the owner's remedies remain, but they run through the warranty and through the statutes of limitation and repose.

The eleven-month walk-through exists precisely because of that structure: it identifies defects while the contractor is still obligated to return and correct them at no cost.