1 Introduction & Exam Overview

1.1 About ASSE 5110 and the Series 5000 Program 1.2 Eligibility, 40-Hour Course, Written & Practical Format 1.3 Validity, Recertification, and Retake Rules

2 Hydraulics Fundamentals

2.1 Pressure, Head, and Atmospheric Reference 2.2 Static vs Flowing Conditions for Testers 2.3 PSID and How Differentials Are Measured

3 Backpressure, Backsiphonage & Differentials

3.1 Backpressure: Causes and Field Examples 3.2 Backsiphonage: Causes and Field Examples 3.3 How Differentials Drive Relief and Air-Inlet Action 3.4 When and Why Backflow Occurs in Distribution Systems

4 Cross-Connection Recognition

4.1 Health Hazard vs Non-Health Hazard Classification 4.2 Common Cross-Connections and Correct Protection 4.3 Containment vs Isolation Strategies

5 RP and DC Assemblies

5.1 RP (ASSE 1013) Components and Operation 5.2 RP Relief Valve Theory and Zone Protection 5.3 DC (ASSE 1015) Components and Operation 5.4 When to Use RP vs DC

6 PVB, SVB & Detector Assemblies

6.1 PVB (ASSE 1020) Components and Operation 6.2 SVB (ASSE 1056) Components and Operation 6.3 RPDA and DCDA Detector Assemblies (1047/1048) 6.4 Non-Testable Devices Testers Must Recognize

7 Test Equipment & Calibration

7.1 Three-Valve Differential Pressure Gauges 7.2 Five-Valve Gauges and Hose Discipline 7.3 Bleeding, Hookup Sequence, and Air Elimination 7.4 Calibration, Accuracy, and Field Verification

8 RP & DC Field Test Procedures

8.1 RP Field Test Procedure (USC 10th Edition) 8.2 RP Pass/Fail Criteria and Troubleshooting 8.3 DC Field Test Procedure 8.4 DC Failures and Common Causes

9 PVB/SVB Tests & Practical Sequence

9.1 PVB Field Test Procedure 9.2 SVB Field Test Procedure 9.3 Comparing the Four Practical-Exam Assemblies 9.4 Hands-On Sequence Under Practical Exam Pressure

10 Installation Requirements & Inspection

10.1 Orientation, Clearance, and Elevation Rules 10.2 RP Drainage, Air Gap, and Flood Protection 10.3 Freeze Protection and Thermal Expansion 10.4 Pre-Test Visual Inspection

11 Codes, Standards & Manuals

11.1 ASSE Series 5000 and 5110 Professional Qualifications 11.2 Device Standards 1013, 1015, 1020, 1056 11.3 USC Manual of Cross-Connection Control 10th Edition 11.4 AWWA M14, EPA 816-R-03-002, and SDWA Framework

12 Reporting, Boundaries & Exam Prep

12.1 Field Test Reports and Pass/Fail Language 12.2 Purveyor Notification and Record Retention 12.3 Tester vs Repairer vs Surveyor Boundaries 12.4 Written Exam Strategy, Study Plan, and Next Credentials

5.3 DC (ASSE 1015) Components and Operation

Key Takeaways Explain This Topic AI

ASSE 1015 defines the double check valve assembly (DC): two independently acting check valves, two resilient-seated shutoffs, and test cocks—with no differential pressure relief valve

DCs are approved for non-health hazards (pollution) under backpressure and backsiphonage conditions appropriate to local code—not for contamination/health-hazard service

Field testing verifies each check holds tight at ≥ 1.0 psid (USC-style criteria); there is no relief opening test because there is no relief

Without a relief, reverse leakage can occur without an external atmospheric discharge signal, which is a core limitation versus the RP

DCDA (ASSE 1048) is a related fire-line form with a metered bypass; full detector-assembly detail belongs in the PVB/SVB/detectors chapter

Last updated: August 2026

5.3 DC (ASSE 1015) Components and Operation

Quick Answer: An ASSE 1015 double check valve assembly (DC) has two independently acting check valves , two resilient-seated shutoff valves , and test cocks —and no differential pressure relief valve. It is used for non-health hazards (pollution), not contamination. Field tests verify each check ≥ 1.0 psid tight. The missing relief is why programs forbid DCs on toxic or pathogenic loads.

What “double check” means in product standards

A double check valve assembly is not merely “two check valves somewhere in a pipe.” Like the RP, it is a listed assembly : two checks in series, factory-assembled with shutoffs and test cocks so the unit can be isolated and field-tested as a package. The governing product standard for the ordinary potable-service DC is ASSE 1015 .

Compare side by side at the component level:

  • Feature RP (ASSE 1013) DC (ASSE 1015)
  • Check valves Two independent Two independent
  • Differential relief valve Yes (between checks) No
  • Shutoff valves Two resilient-seated Two resilient-seated
  • Test cocks Four (typical) Four (typical)
  • Atmospheric dump Relief to air gap None
  • Health hazard use Yes No (non-health only)
  • Backpressure capability Yes Yes (non-health)
  • Backsiphonage capability Yes Yes (non-health)

If a question shows a cutaway with a relief port between the checks, it is an RP , not a DC—even if someone loosely calls both “double checks” in casual speech. Professional language: RP vs DC .

Flow path and normal operation

Forward flow through a DC:

Enter shutoff #1 .

Open check #1 against its spring/seat.

Pass the intermediate chamber (there is no reduced-pressure relief sensing circuit like an RP).

Open check #2 .

Exit shutoff #2 .

Under static conditions, both checks seat. Protection against reverse flow depends entirely on both seats remaining tight . There is no third device that opens to atmosphere if the first check leaks. That is the operational simplicity—and the operational limitation—of the DC.

Test cocks

A standard DC assembly provides test cocks positioned so a differential gauge can measure the pressure drop across each check (inlet vs intermediate, intermediate vs downstream, per the adopted procedure). Typical bodies still present four test cocks in order similar to RP numbering conventions, but the tests performed differ because there is no relief opening measurement. Chapter 8 covers the DC procedure step-by-step; here, know that test cocks exist so each check can be proven independently .

What the field test proves on a DC

Under USC-style criteria used throughout ASSE 5110 training:

Check #1 must hold ≥ 1.0 psid tight (no reverse leakage under the test method).

Check #2 must hold ≥ 1.0 psid tight.

There is no relief-opening test and no “check #1 must be 5.0 psid” rule—those belong to the RP . Mixing the two assemblies’ numbers is one of the most common written-exam errors.

  • Test element DC (1015) RP (1013)
  • Relief opening N/A ≥ ~2.0 psid measured
  • Check #1 ≥ 1.0 psid tight ≥ 5.0 psid and above relief
  • Check #2 ≥ 1.0 psid tight Tight against backpressure (no psid)

If either DC check fails to hold 1.0 psid, the assembly fails. Repair or replacement follows local program rules; the tester’s immediate duty is accurate measurement and reporting.

Hazard classification: non-health only

Cross-connection control distinguishes:

Pollution / non-health hazard — aesthetic or non-toxic degradation (certain closed heating loops without chemicals, some irrigation without toxic additives, specific fire lines without antifreeze, etc., as classified by the AHJ ).

Contamination / health hazard — pathogens, toxic chemicals, sewage, medical waste, and similar risks.

A DC may be accepted only for non-health hazards when the hydraulic condition includes continuous pressure and possible backpressure or backsiphonage and local code allows a DC for that use. A DC is not a substitute for an RP on a health hazard—even if the DC is new, listed, and passes a 1.0 psid test. Passing mechanical criteria does not upgrade the hazard rating of the device type.

Exam trap language to watch:

“Toxic boiler chemicals” → RP (or air gap), not DC.

“Hospital waste sterilizer with chemical residual” → RP , not DC.

“Fire sprinkler without chemicals (where code allows DC/DCDA)” → DC family may apply; detector forms are common on fire lines.

“Car wash with soaps and reclaim” → typically health-hazard thinking → RP territory unless AHJ documents otherwise.

Always remember: the tester reports assembly condition; the purveyor/AHJ sets required protection type. If the wrong type is installed, report what you find; do not “pass” a health-hazard service just because the DC numbers look good.

Limitations versus the RP (exam-critical)

No atmospheric indication — Reverse leakage past both checks can contaminate the supply side without a visible dump to air.

No intermediate reduced-pressure fail-safe — The RP’s zone + relief is specifically designed so a failing first check tends to discharge rather than silently pressurize toward the inlet.

Lower degree of hazard approval — Standards and codes place DCs below RPs for protection hierarchy.

Same need for annual testing — Two checks can foul, stick open, or wear; non-testable dual checks (different product class) are not the same as a 1015 assembly.

These limitations are why “cheaper and no discharge water” never justifies a DC on a toxic feed line.

Body materials, orientation, and inspection basics

Like RPs, DCs appear in bronze, ductile iron, and stainless constructions with resilient seats. Horizontal installation is common; manufacturer orientation listings still control. Shutoffs must be resilient-seated for isolation and testing. Visual pre-test checks include:

Presence of both shutoffs and all test cocks.

No unauthorized bypass around the assembly.

Access for gauge hookup and shutoff operation.

Identification plate / marking consistent with a listed DC (1015), not a dual check (often ASSE 1024 class devices) that is not the same testable assembly.

Non-testable dual checks and residential dual checks are different products . Do not treat them as ASSE 1015 DCs on the practical exam or on a containment report.

DCDA: fire-line cousin (preview only)

A double check detector assembly (DCDA) , product standard ASSE 1048 , is used primarily on fire protection services. It combines a main-line double check with a bypass line containing a smaller check arrangement and a meter that registers low flows (leaks or unauthorized use) the large fire-line meter might miss. Hazard rating remains in the non-health family unless the fire system is chemically treated (then RPDA / RP logic applies).

For this chapter, remember only:

DCDA = DC-type protection + detector metering for fire lines.

Full component detail, RPDA ( ASSE 1047 ), and fire-specific testing nuances appear in the PVB, SVB & detector assemblies chapter.

Do not confuse 1015 (DC) with 1048 (DCDA) or 1047 (RPDA) on number-matching questions.

Mini case: irrigation without chemical injection

A municipal park irrigates turf with potable water and no fertilizer or pesticide injection on the protected branch. The purveyor classifies the service as non-health and requires a DC at the point of connection. Annual test: both checks hold 1.4 and 1.2 psid. Report pass for the mechanical criteria if the installation is complete and the required assembly type matches the program. If the same park later adds a chemical injector , the hazard class may change—then a DC that still “passes 1.0” is the wrong protection type , and the program must upgrade (typically to RP). Testers who understand hazard vs. numbers prevent false confidence.

Bridge to selection

You can now describe RP and DC internals and test targets. Section 5.4 turns that into a decision matrix : when each assembly is correct, common traps, cost/maintenance tradeoffs, and who decides required protection.