2.2 Oxygen-Clean Materials: Delivery, Handling & Recleaning

ASSE 6010 Medical Gas Systems Installer Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: The Credential, Codes & Medical Gas Fundamentals

1.1 The ASSE 6010 Credential: Eligibility, Exam Format & Recertification 1.2 Codes, Referenced Standards & the Medical Gas Team 1.3 Medical Gases, Hazards & Permitted Uses 1.4 Risk Categories & Category 1, 2, and 3 Piped Systems 1.5 Key NFPA 99 Definitions & Terminology

2 Chapter 2: Piping Materials, Oxygen Cleanliness & Joining Methods

2.1 Tube Specifications for Medical Gas and Vacuum Piping 2.2 Oxygen-Clean Materials: Delivery, Handling & Recleaning 2.3 Joining Methods: Permitted and Prohibited Joints

3 Chapter 3: Brazing Medical Gas Piping

3.1 Joint Preparation, Fittings, Filler Metals & Flux 3.2 Nitrogen Purge: Setup, Control & Final Tie-In Exception 3.3 Heating, Filling & Inspecting Brazed Joints 3.4 Brazing Procedure & Brazer Qualification, Records and Continuity

4 Chapter 4: Installing the Distribution Piping

4.1 Pipe Sizing, Protection & Permitted Locations 4.2 Supports, Buried Piping, Flexible Connectors & System Interconnections

5 Chapter 5: Valves, Station Outlets, Alarms & Labeling

5.1 Valve Requirements: Source, Main Line, Riser, Service & In-Line Valves 5.2 Zone Valves & Zone Valve Box Assemblies 5.3 Station Outlets & Inlets, Manufactured Assemblies & Pressure Indicators 5.4 Warning Systems: Master, Area & Local Alarms 5.5 Labeling, Identification & Color Codes

6 Chapter 6: Central Supply Systems & Source Equipment

6.1 Central Supply Locations, Cylinder Manifolds, Line Controls & Relief Valves 6.2 Cryogenic Supplies, Reserves, EOSC, IBER & Oxygen Concentrators 6.3 Medical Air Compressor Systems 6.4 Medical-Surgical Vacuum, WAGD & Medical Support Gas Sources

7 Chapter 7: Testing, Verification & Documentation

7.1 Installer Tests I: Blowdown, Initial Pressure, Cross-Connection & Piping Purge 7.2 Installer Tests II: 24-Hour Standing Pressure & Vacuum Tests, Inspection & Witnessing 7.3 System Verification: The Verifier's Test Sequence 7.4 Tie-Ins, Breached Systems, Operational Flow & Gas Concentration Tests 7.5 Documentation, Records & System Turnover

2.2 Oxygen-Clean Materials: Delivery, Handling & Recleaning

Key Takeaways Explain This Topic AI

Tubes, valves, fittings, outlets, and other piping components must be cleaned for oxygen service per CGA G-4.1 before installation; fittings may be cleaned by a supplier or agency other than the manufacturer.

Each tube length is delivered plugged or capped by the manufacturer, and all components stay sealed until they are prepared for installation.

Contaminated interiors may be recleaned on site with a hot water and alkaline solution of 1 lb sodium carbonate or trisodium phosphate per 3 gal of potable water, followed by a hot potable water rinse.

Material that is contaminated internally and is not clean for oxygen service must not be installed.

The installer must furnish documentation certifying that the installed piping materials meet the cleaning requirement.

Last updated: October 2026

Why Cleanliness Is a Code Requirement

A medical gas pipeline carries oxygen and nitrous oxide straight to patients. Hydrocarbons, cutting oil, pipe-thread dope, dust, or metal chips inside the pipe can ignite in an oxygen stream. They can also be carried into ventilators and anesthesia machines. NFPA 99 handles this risk in two layers: components are cleaned at the factory , and the installer keeps them clean through delivery, storage, cutting, assembly, and testing.

Cleaning Before Installation

NFPA 99 requires tubes, valves, fittings, station outlets, and other piping components to have been cleaned for oxygen service by the manufacturer before installation, following the mandatory requirements of CGA G-4.1, Cleaning Equipment for Oxygen Service . One exception exists: fittings may be cleaned by a supplier or agency other than the manufacturer. This rule covers positive-pressure medical gas components. Valves for any positive-pressure service must likewise be cleaned for oxygen service by the manufacturer.

The installer must furnish documentation certifying that all installed piping materials comply with the cleaning requirement. Keep packing slips, mill certifications, and manufacturer cleanliness certifications with the job records. The verifier and the AHJ may ask for them.

Delivery and Storage

Item NFPA 99 delivery rule

Tube Each length delivered plugged or capped by the manufacturer and kept sealed until prepared for installation

Fittings, valves, other components Delivered sealed and labeled , and kept sealed until prepared for installation

Metallic flexible joints Cleaned at the factory for oxygen service and received with certification of cleanliness

The code does not prescribe a storage rack, but good practice follows from the rules above:

Keep tube and fittings in a dedicated, dry, covered area away from oils, solvents, thread sealants, and dust-producing trades.

Store tube off the floor or ground on clean supports, and leave the caps on until the length is cut.

After cutting a length, recap the remaining tube right away with a clean cap or plug.

Never tape over the bore. Adhesive residue is exactly the kind of contaminant you are trying to keep out.

Handling During Installation

Several NFPA 99 requirements apply while the system is going together:

Store and handle to avoid contamination. The interiors of cleaned tubes, fittings, and components must be stored and handled so they are not contaminated before assembly and brazing.

Examine before joining. Tubes, fittings, valves, and other components must be visually examined internally before they are joined. You are confirming that they have not been contaminated and are free of obstructions or debris.

Keep openings sealed. During and after installation, openings in the piping system must be kept sealed. This keeps a nitrogen atmosphere in the piping and keeps debris out.

Use clean tools. The cutting wheels on tube cutters must be free of grease, oil, and any lubricant unsuitable for oxygen service.

Keep chips out. When deburring, prevent chips from entering the tube.

When Contamination Happens: On-Site Recleaning

NFPA 99 lets the installer reclean, but only within limits.

Who: the installer, on site.

What: interior surfaces of tube ends, fittings, and other components that were cleaned for oxygen service by the manufacturer but became contaminated before installation.

How: thoroughly scrub the interior surfaces with a clean, hot water and alkaline solution of sodium carbonate or trisodium phosphate , mixed at 1 lb (0.5 kg) to 3 gal (11 L) of potable water . Then thoroughly rinse with clean, hot, potable water .

Alternatives: other aqueous cleaning solutions may be used if they follow the mandatory requirements of CGA G-4.1.

Fitting sockets: if a socket becomes contaminated before brazing, reclean it for oxygen service as above, then clean it for brazing with a clean, oil-free stainless steel or brass wire brush .

Caution

NFPA 99 also states that material that has become contaminated internally and is not clean for oxygen service shall not be installed . If you cannot reclean a part to oxygen-service condition, such as a long tube with oil throughout its bore, scrap it. Do not install it and hope the purge test will catch the problem.

Related Cleanliness Rules Elsewhere in the Code

Threaded joints , where permitted, are made up with PTFE tape or another oxygen-service sealant applied only to the male threads . Take care that no sealant gets inside the pipe.

Leak detectants used in pressure testing must be safe for use with oxygen and contain no ammonia .

Breaching existing piping , such as tapping into a positive-pressure patient gas or support gas line, may not leave copper particles or debris in the pipe. Any debris must stay contained in the work area.

Nitrogen NF is the required purge and test gas because it is clean, dry, and oil-free. Compressed shop air is never a substitute.

A Quick Decision Table

Situation on the job Correct action

Tube bundle arrives with several end caps missing and dust in the bores Reclean affected ends per NFPA 99, or reject lengths that cannot be returned to oxygen-clean condition

  • Fitting bag torn open in the gang box Inspect; reclean the socket and interior per the code method before use
  • Cutting oil found inside a cut length Do not install unless it can be recleaned to oxygen-service condition

Brass valve with factory extensions delivered sealed and labeled Keep it sealed until installation and examine it internally before joining